RFI 8_12 Q_A.pdf
PDF 208 KB Posted
- Attached to
- Construction-B80 2nd Floor Interior Renovation Project Federal contract opportunity
- Solicitation number
- N6660421R0360
About this file
This document contains questions and answers regarding a construction project solicitation. The solicitation is for interior renovations and repairs to rooms and stairs in Building 80 at the Naval Sea Systems Command, including demolition work, provision of conference rooms and restrooms, and does not require contractors to be JCP certified. Details provided include confirmation that sheet S-501 shows railing details but no completed staircase drawing, and that there is no preferred blind manufacturer. Contractors can request drawings and specifications via Sam.gov or by emailing contacts provided with company and CAGE code information.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B80 2nd Floor Upgrade Site visit 7_28.pdf | ||
| RFI 8_16.pdf | ||
| RFI 8-13 Q_A.pdf | ||
| Additional Photos of the Jobsite.pdf | ||
| B80 2nd FLoor RFI Q-A.pdf | ||
| Attachment_4_ Covid Questionare.pdf | ||
| Attachment 3 Past Performance Questionare.pdf | ||
| N6660421R0360.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
-Sheet S-501 provides the stair elevation and railing detail. Please confirm the vertical (up the staircase) and horizontal (on the landing) length of the railing. Also, is there a drawing that shows the completed staircase and railing?
ANSWER: The handrail detailed on sheet S-501 provides the details on how to construct the handrail.
The length of the railing is defined by Code, namely the UFC and must meet ADA compliance. There is no drawing for the completed staircase and railing.
-Is there a preferred manufacturer NUWC uses for its blinds ANSWER: There is no preferred manufacturer for blinds. The Government does not intend to limit competition amongst product manufacturers. Blinds must comply with the criteria specified within the contract documents.