This document is an Amendment (Amendment 0002) to Solicitation N6449824Q5065 for the Bldg 77L HVAC Repair project at the Philadelphia Navy Yard. The amendment provides responses to questions submitted by potential offerors after the site visit, including details on the emergency power off (EPO) switch, securing roof rails, BACnet controller programming, and ductwork modifications. The solicitation response date remains unchanged at May 2, 2024 at 12pm EST. All other terms and conditions of the solicitation remain unchanged.
The underlying solicitation is for a Firm Fixed Price (FFP) construction contract to repair the HVAC system in Building 77L at the Philadelphia Navy Yard. This requirement is being competed as a 100% Small Business Set-aside. A site visit was held on April 17, 2024. Proposals are due by May 2, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment P0001.pdf | ||
| Copy of Copy of SOW Attachment (5) Schedule of Values.xlsx | XLSX spreadsheet | |
| RFQ N6449824Q5065.pdf | ||
| SOW Attachment (2) Photographs - Existing HVAC.docx | DOCX document | |
| SOW Attachment (8) Requirements for Contractor Lift Operations.pdf | ||
| SOW Attachment (1) Site Map - PNBC.pdf | ||
| SOW Attachment (6) Activity Hazard Analysis Form.docx | DOCX document | |
| SOW Attachment (9) Mobile Construction Equipment Checklist.pdf | ||
| Attachment 12 PPQ Past Performance Questionnaire.docx | DOCX document | |
| SOW Attachment (10) Contractor Production Report Form.docx | DOCX document | |
| SOW Attachment (7) Contract Progress Report.pdf | ||
| SOW Attachment (11) Insulation Resistance Test Report.pdf | ||
| SOW Attachment (3) SECNAV 5512.pdf | ||
| SOW Attachment (4) ENG FORM 4025R Transmittal Form_rev1.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See description of Amendment 0002 on page tw o.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6449824Q5065
X 9B. DATED (SEE ITEM 11)
12-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-May-2024
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0242, TYNISE CAIN
TYNISE.S.CAIN.CIV@US.NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6449824Q5065
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Amendment 0002 is hereby issued to provide Government response to submitted questions. The solicitation response date remains unchanged, 2 May 2024 12pm EST.
All other terms and conditions remain unchanged.
Questions/Answers:
Q1. At the site visit, there was mention of installing an emergency shut off button, with that do they want it to shut off the main power to the unit and if so, how far is the breaker panel from the location of said shut off switch?
A1. EPO switch should be relayed directly to the unit for shutoff. It cannot be wired directly to the beakers.
Q2. For securing roof rails, do they just want weight blocks to secure the rails or secured to the roof and flashed in by a roofer?
A2. Weighted blocks is acceptable. Roof pad is required underneath pad. The Government does not want the securing roof rails bolted down to the roof.
Q3. For BACnet controller I know the only want the ability to see the unit status but there is graphics in the scoop for the BAS and didn’t know if that is for us or the current controls company to do that?
A3. Graphics on our DDC computers are to be supplied by contractor. The contractor needs to provide all programming to display unit status on our DDC computers (including programming graphics).
Q4. We are unable to see where the duct enters the building from inside, Are there any prints on this ductwork because with a new unit the dimensions and orientation will be different, and modifications will most likely be needed A4. During the site walkdown, we showed where the duct enters the building (in the room that was under construction). There are no prints available at this time.
Q5. The unit in the Pictures in “SOW Attachment (2) Photographs - Existing HVAC” word document indicates the unit to be replaced is AC-7, it this correct?
A5. Naming in field may be left over. This unit is currently not named AC-7, even though its written on the side of it.
Q6. If AC-7 is being replaced the original prints for AC-7 show room 1402, 1403, 1018, Where is 800 in relation to theses room?
A6. The location of room 800 is roughly within 75 feet and was identified during the site visit.