Amendment P0001.pdf
PDF 156 KB Posted
- Attached to
- Bldg 77L HVAC Repair Federal contract opportunity
- Solicitation number
- N6449824Q5065
About this file
This document is an Amendment to a solicitation for a Firm Fixed Price (FFP) Construction contract for Bldg 77L HVAC Repair at the Philadelphia Navy Yard. The amendment provides the government's responses to submitted questions, which clarify that the requirement is for installing new guardrails (2 rail systems) on 4 bridges on the south side of Building 77L. The solicitation response date remains unchanged as May 2, 2024 at 12:00 pm EST. All other terms and conditions of the original solicitation remain unchanged. The original solicitation, Solicitation Number N6449824Q5065, is a 100% Small Business Set-aside requirement being competed by the Department of the Navy Naval Sea Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6449824Q5065 Amendment 0002.pdf | ||
| Copy of Copy of SOW Attachment (5) Schedule of Values.xlsx | XLSX spreadsheet | |
| RFQ N6449824Q5065.pdf | ||
| SOW Attachment (2) Photographs - Existing HVAC.docx | DOCX document | |
| SOW Attachment (8) Requirements for Contractor Lift Operations.pdf | ||
| SOW Attachment (1) Site Map - PNBC.pdf | ||
| SOW Attachment (6) Activity Hazard Analysis Form.docx | DOCX document | |
| SOW Attachment (4) ENG FORM 4025R Transmittal Form_rev1.pdf | ||
| SOW Attachment (9) Mobile Construction Equipment Checklist.pdf | ||
| Attachment 12 PPQ Past Performance Questionnaire.docx | DOCX document | |
| SOW Attachment (10) Contractor Production Report Form.docx | DOCX document | |
| SOW Attachment (7) Contract Progress Report.pdf | ||
| SOW Attachment (11) Insulation Resistance Test Report.pdf | ||
| SOW Attachment (3) SECNAV 5512.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See description of Amendment 0001 on page tw o.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Apr-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6449824Q5065
X 9B. DATED (SEE ITEM 11)
12-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Apr-2024
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0242, TYNISE CAIN
TYNISE.S.CAIN.CIV@US.NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6449824Q5065
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Amendment 0001 is hereby issued to provided Government response to submitted questions. The solicitation response date remains unchanged, 2 May 2024 12:00pm EST.
All other terms and conditions remain unchanged.
Questions/Answers:
Q1. Is the intent to install new guardrails (2 rail systems) at only one location where we are replacing equipment?
A1. There are 4 bridges that need the guardrails (on both sides of the bridge). This is for the southern 4 bridges only.
Q2. If the intent is to install new guardrails at other locations, how many locations part of the scope of work?
A2. The system (guardrails) shall be installed at the entrances and exits of each upper roof bridges on the south side of Building 77L (four (4) bridges).
SOW Paragraph 2.18.3 and 2.19 detail the guardrails. There are 4 bridges that need the guardrails (on both sides of the bridge). This is for the southern 4 bridges only.