DID_FOR_CDRL_A001.pdf

PDF 18 KB Posted

Attached to
Environmental Database Services Federal contract opportunity
Solicitation number
N64267-14-T-0321
Issued by
Department of the Navy Naval Sea Systems Command

About this file

DID FOR CDRL A001

View the file

Other files for this federal contract opportunity

Other files attached to Environmental Database Services, newest first.
File Type Posted
Questions_-_N64267-14-T-0321.docx DOCX document
DID_FOR_CDRL_A003.pdf PDF
DID_FOR_CDRL_A005.pdf PDF
DID_FOR_CDRL_A002.pdf PDF
CDRL_A005_Computer_Software_Product.RA30.DID.pdf PDF
CDRL_A003_Software_Design_Doc.RA30.DID.pdf PDF
WD_San_Diego.pdf PDF
CDRL_A002_Database_Design_Doc.RA30.DID.pdf PDF
CDRL_A001_Progress_Rep.RA30.DID.pdf PDF
DID_FOR_CDRL_A004.pdf PDF
CDRL_A004_Contractors_Personnel_Roster.RA30.DID.pdf PDF
Environmental_Services_Solicitation.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: Contractor's Progress, Status and Management Report

Number: DI-MGMT-80227 Approval date: 05 Sep 1986 AMSC Number: N3947 Limitation:

DTIC Applicable: GIDEP Applicable:

Preparing Activity:

Use/relationship:

The Contractor's Progress, Status and Management Report indicates the progress of work and the status of the program and of the assigned tasks, reports costs, and informs of existing or potential problem areas.

This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement for this data included in the contract.

This DID may be applied in any contract and during any program phase.

This DID supersedes DI-A-2090A, DI-A-3025A, UDI-A-22050B, UDI-A-22052A, UDI-A-23960, DI-A-30024, and DI-A- 30606.

Paragraphs 10.3.f, 10.3.g, and 10.3.h herein should be tailored on DD Form 1423 when such cost data is already submitted through a sophisticated cost reporting system under the contract.

Requirements:

Contract. This data item is generated by the contract which contains a specific and discrete work task to develop this data product.

Format. This report shall be electronic in Microsoft Word document format. Pages shall be sequentially numbered. All attachments shall be identified and referenced in the text of the report. The report shall be prepared in the contractor's format and shall be legible and suitable for reproduction.

Content. The report shall include:

a. A front cover sheet which includes the contractor's name and address, the contract number, the nomenclature of the system or program, the date of the report, the period covered by the report, the title of the report, either the serial number of the report or the Contract Data Requirements List (CDRL) sequence number, the security classification, and the name of the issuing Government activity;

b. Description of the progress made against milestones during the reporting period;

c. Results. positive or negative, obtained related to previously-identified problem areas, with conclusions and recommendations;

d. Any significant changes to the contractor's organization or method of operation, to the project management network, or to the milestone chart;

e. Problem areas affecting technical or scheduling elements, with background and any recommendations for solutions beyond the scope of the contract;

f. Problem areas affecting cost elements, with background and any recommendations for solutions beyond the scope of the contract;

g. Cost curves showing actual and projected conditions throughout the contract;

h. Any cost incurred for the reporting period and total contractual expenditures as of reporting date;

i. Person-hours expended for the reporting period and cumulatively for the contract;

j. Any trips and significant results;

k. Record of all significant telephone cal1s and any commitments made by telephone;

l. Summary of Engineering Change Proposal (ECP) status, including identification of proposed ECPs, approved ECPs, and implemented ECPs, if any;

m. Contract schedule status;

n. Plans for activities during the following reporting period;

o. Name and telephone number of preparer of the report;

p. Appendixes for any necessary tables, references, photographs, illustrations, and charts.

End of DI-MGMT-80227