DI-MGMT-80227_Contractor's_Progress_Status_and_Mangement_Report.docx

Data Item Description DOCX document 18 KB Posted

Attached to
Information Assurance and Certification and Accreditation
Solicitation number
N64267-14-T-0202
Issued by

About this file

DID FOR CDRL A001

View the file

Other versions and copies of DI-MGMT-80227

File Revision Posted Attached to
A048_DID_(DI-MGMT-80227)_-_3_Feb_17.pdf Feb 3, 2017 MODELING, SIMULATION, AND ANALYSIS (MS&A) FOR SPACE AND CYBERSPACE CAPABILITIES
Exhibit CDRL B001_DI_MGMT_80227 Contractors Progress Status and Management Report.pdf Revision not stated SOFTWARE MAINTENANCE OF FIELDED TRAINING DEVICES (SWMFTS)
Exhibit CDRL B001_DI_MGMT_80227 Contractors Progress Status and Management Report.docx Revision not stated SOFTWARE MAINTENANCE OF FIELDED TRAINING DEVICES (SWMFTS)
Exhibit CDRL B001_DI_MGMT_80227 Contractor Progress Status and Management Report.docx Revision not stated SOFTWARE MAINTENANCE OF FIELDED TRAINING DEVICES (SWMFTS)
7. DID (DI-MGMT-80227).pdf Revision not stated Locksmith and Electronic Security System
A009 DI-MGMT-80227 Contractors Progress Status and Management Report.pdf Revision not stated DRAFT Solicitation for Flight School Training Support Services (FSTSS)
A009 DI-MGMT-80227 Contractors Progress Status and Management Report.pdf Revision not stated Draft Performance Work Statement (PWS) Contract Data Requirements Lists and (CDRLs) for Flight School Training Support Services (FSTSS)
DI-MGMT-80227.pdf Revision not stated B544 Duct Cleaning and Insulating
T53_DID_A001_DI_MGMT_80227_Transition_PhaseIn.pdf Revision not stated T53-L-703 Engine Overhauls / Repairs
T53_DID_A001_DI_MGMT_80227_Transition_PhaseIn.pdf Revision not stated PRE-SOLICITATION DAY TELECOM- T53-L-703 Engine Overhauls / Repairs
DI-MGMT-80227.pdf Revision not stated CODE 102 B575 GRINDING ROOM VENTILATION
DI_MGMT_80227.pdf Revision not stated Inertial Navigation Element Remanufacture - Sole Source to Northrop Grumman
DI-MGMT-80227.pdf Revision not stated 3D METAL ADDITIVE UPGRADE LAB
DI-MGMT-80227.pdf Revision not stated 500 AREA TEMPORARY TRAILERS
FA811917R0031_DID_DI_MGMT_80227_FD20301701792.pdf Revision not stated Aircraft and Airframe Structural Components
18aa__DI-MGMT-80227_(A001).pdf Revision not stated IA Services
DI-MGMT-80227_Contractor's_Progress_Status_and_Mangement_Report.docx Same revision and size as this file Revision not stated IA Support
FA810515R0008_DI-MGMT-80227.pdf Revision not stated TOMA Support
CDRL_A002_DID_DI-MGMT-80227_Contractor's_Progress-Status-Mgmt_Report.pdf Revision not stated Aerial Targets
0414-04_-_FATEPEN_Support_-_DID_DI-MGMT-80227_(Status_Report).pdf Revision not stated SPECIAL STUDIES AND ANALYSIS
Show all 20

Who attaches DI-MGMT-80227

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: CONTRACTOR’S PROGRESS, STATUS AND MANATGEMENT REPORT

Number: DI-MGMT-80227
Approval Date: 19860905
AMSC Number: N3947
Limitation: N/A
DTIC Applicable: N/A
GIDEP Applicable: N/A

Office of Primary Responsibility: N/SPAWAR

Applicable Forms: N/A

Use/relationship: The Contractor’s Progress, Status and Management Report indicates the progress of work and the status of the program and of the assigned tasks, reports costs, and informs of existing or potential problem areas.

Application / Interrelationship: This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement for this data included in the contract.

This DID may be applied in any contract and during any program phase.

This DID supersede DI-A-2090A, DI-A-3025A, UDI-A-22050B, UDI-A-22052A, UDI-A-23960, DI-A-30024, and DI-A-30606.

Paragraphs 10.3.f, 10.3.g, and 10.3.h herein should be tailored on DD Form 1423 when such cost data is already submitted through a sophisticated cost reporting system under the contract.

Requirements:

This data item is generated by the contract which contains a specific and discrete work task to develop this data product.

1. Reference documents. The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as cited in _________

2. Format. This report shall be typewritten on standard size (e.g., 8 ½” by 11”) white paper, and securely stapled. Pages shall be sequentially numbered. All attachments shall be identified and referenced in the text of the report. The report shall be prepared in the contractor’s format and shall be legible and suitable for reproduction.

3. Content. The report shall include:

a. A front cover sheet which includes the contractor’s name and address, the contract number, the nomenclature of the system or program, the date of the report, the period covered by the report, the title of the report, either the serial number of the report or the Contract Data Requirements List (CDRL) sequence number, the security classification, and the name of the issuing Government activity;

b. Description of the progress made against milestones during the reporting period;

c. Results, positive or negative, obtained related to previously-identified problem areas, with conclusions and recommendations;

d. Any significant changes to the contractor’s organization or method of operation, to the project management network, or to the milestone chart;

e. Problem areas affecting technical or scheduling elements, with background and any recommendations for solutions beyond the scope of the contract;

f. Problem areas affecting cost elements, with background and any recommendations for solutions beyond the scope of the contract;

g. Cost curves showing actual and projected conditions throughout the contract;

h. Any cost incurred for the reporting period and total contractual expenditures as of reporting date;

i. Person-hours expended for the reporting period and cumulatively for the contract;

j. Any trips and significant results;

k. Record of all significant telephone calls and any commitments made by telephone;

l. Summary of Engineering Change Proposal (ECP) status, including identification of proposed ECPs, approved ECPs, and implemented ECPs;

m. Contract schedule status;

n. Plans for activities during the following reporting period;

o. Name and telephone number of preparer of the report;

p. Appendixes for any necessary tables, references, photographs, illustrations, and charts.

4. End of DI-MGMT-81834.