Hawaiian Electric RFP Process - Industry Day MCBH 11.16.23.pdf
PDF 702 KB Posted
- Attached to
- Request for Information (RFI) for Marine Corps Base Hawaii - Kaneohe Bay Energy Resilience
- Solicitation number
- N62742
About this file
This document outlines Hawaiian Electric's renewable energy procurement process and upcoming request for proposals. Hawaiian Electric seeks renewable energy projects through a multi-step solicitation and evaluation process. Developers must meet eligibility requirements and submit initial proposals, which are evaluated on price and non-price factors like community outreach and environmental compliance. Shortlisted bidders provide best and final offers then detailed evaluations determine selection for contract negotiations. Non-price criteria include experience, project development status, financial strength, and community benefits packages. Interconnection studies are required. The upcoming April 2024 IGP RFP will procure renewables to meet integrated grid plan targets, with awards anticipated in late 2025. This RFP overview aligns with the Department of the Navy's related RFI seeking information on energy resilience projects for Marine Corps Base Hawaii Kaneohe Bay.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Confidential RFP-related InformationConfidential RFP-related Information
Request for Proposals Process MCBH Industry Day November 16, 2023
Confidential RFP-related Information
Hawaiian Electric’s Goals RFP Process Upcoming RFP
Agenda
Integrated Grid Plan www.hawaiianelectric.com/igp
Energy Price Stability Reliability & Resilience Retire Fossil Fuel Generation Meet Renewable/Decarbonization Goals Acknowledge Economic Uncertainty
RFP Objectives
Renewable Energy Procurement Process
Community Outreach Meetings
Regulatory Approval
Process for RFP Final RFP
Issued Developers
Submit Proposals
Eligibility and Threshold Evaluation
Initial Evaluation
Select Priority List
Best and Final Offer
Submission Detailed
Evaluation Selection of
Final Award(s)
Contract Negotiations* / Public Meeting
Regulatory Approval
Process for PPA(s)
Projects Online
Public Comment Opportunities
* Interconnection Requirements Study concurrent
Initial Evaluation
Non-Price Evaluation
Price Evaluation
Evaluation Process
Priority List
Eligibility and Threshold
Requirement Evaluation
BAFO
Detailed Evaluation
Final Award Group
Eligibility Requirements General and administrative
Threshold Requirements Sufficiently Developed Demonstrated Technology Acceptable Execution Risk
Price and Non-Price Evaluation
Evaluation
Eleven Non‐Price Criteria Double Weighted Single Weighted
Community Outreach Experience and Qualifications
State of Project Development and Schedule Environmental Compliance and Permitting Plan Performance Standards Financial Strength and Financing Plan
Proposed Contract Modifications
Cultural Resource Impacts
Carbon Emissions (introduced in Stage 3)
Technical Model
Land Use and Impervious Cover (introduced in
CBRE)
One Overall Non‐Price Criterion Underperformance Infractions
Previous Performance (introduced in Stage 3)
NOTE: Details reflect previous RFP requirements and may not be identical in future RFPs.
Community Feedback Incorporated Higher scoring to projects that are proposed on land zoned commercial, industrial, land that greater impervious cover, or reclaimed land.
Procedural improvements made to further ensure the protection and preservation of cultural resources.
Prioritizing local labor and prevailing wage incorporated in the RFP.
Additional requirements for developers to provide monthly updates to the community prior to and throughout the construction process.
Requirement for community benefits packages to address critical needs in host communities.
Ongoing Energy Equity Docket (2022-0250) may result in additional changes to RFPs.
Community Benefits Package New in Stage 3 RFPs Based on feedback from Community Outreach meetings on Oahu At lease $3,000 per MW Documented community benefits package highlighting the distribution of funds
Actions and/or programs aimed at addressing specific needs identified by the host community
OR to a 501(c)(3) not-for-profit community-based organization(s) to directly address host community-identified needs
Part of the Community Outreach non-price criteria
NOTE: Details reflect previous RFP requirements and may not be identical in future RFPs.
Interconnection Process
Required with Proposal
• Models
At Priority List Selection
• $15,000 for model review
At Final Award
• Updated models due in 30 days
• IRS Agreement
• SIS to start 60 days after selection
• PPA executed after studies completedNOTE: Details reflect previous RFP requirements and may not be identical in future RFPs.
Upcoming IGP RFP April 2024 •IGP 1st Procurement Draft RFP submitted to
PUC
Sept 2024 •IGP 1st RFP Issued
4Q 2024 •IGP Long‐term RFP issued
July 2025 •IGP 1st RFP Awards
Q4 2025 •IGP 2nd RFP Issued
Q4 2026 •IGP 2nd RFP Awards
2029‐2030
•IGP
Procurements in service
For updates and more information, please see:
www.hawaiianelectric.com/competitivebidding
Mahalo for your time.
Any questions?
For updates and more information, please see:
www.hawaiianelectric.com/competitivebidding