This is a Standard Form 30 (SF 30) Amendment of Solicitation for a federal contract opportunity issued by the Naval Supply Fleet Logistics Center Yokosuka in Japan.
Amendment 0003, effective 13 July 2026, extends the quote submission closing date from 13 July 2026 to 27 July 2026 at 11:00 AM Japan Standard Time (JST) to allow prospective contractors adequate time to prepare quotations. The amendment addresses government responses to additional technical questions regarding contractor responsibilities under solicitation N6264926QB0400, which involves providing Unit Dolly equipment, jacking systems, dolly lifting fixtures, and operators for work specific to dry-dock #6. Key clarifications include: the Unit Dolly is limited to removal of listed items specified in the Performance Work Statement (PWS); the Ship Repair Facility (SRF) is responsible for transporting offloaded items from dry-dock #6 to the SRF shop; KTR's (the contractor's) scope is limited to providing the unit dolly, jacking system, dolly lifting fixtures, and operators; the maximum jacking height requirement is at least 1 foot (30 cm) or higher; and any additional equipment, tools, or resources requested beyond the PWS scope must be submitted via a Contract Funding Request (CFR) for contract modification. All other terms, conditions, specifications, and provisions of the original solicitation remain unchanged. Offers must acknowledge receipt of this amendment prior to the extended deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): The purpose of this solicitation amendment 0003 is to:
1. Provide Government Responses to Additional Technical Questions received.
Q4: Is the transportation of the four shaft-related items, which have been offloaded from the dry dock, to the SRF shop included within the scope of this work?
A4: Unit Dolly is only for removal of listed items in the PWS. Work is specific to dry-dock #6. SRF will be responsible of moving offloaded items from dry-dock #6 to SRF shop.
Q5: Is our understanding correct that KTR's responsibility under this contract is limited to providing the unit dolly, jacking system, dolly lifting fixtures, and the required operators?
A5: YES, KTR is providing unit dolly, jacking system, dolly lifting fixtures and operator.
Q6: If any additional equipment, tools, or resources are required from KTR, please provide details.
A6: The PWS states that the contractor shall provide all tools, equipment, and any other items necessary to deliver and operate the Unit Dolly for the duration of the requirement to successfully execute the tasks. In the event of the project team requesting additional equipment, tools resources, outside of what is written in this PWS; the expectation is that the KTR will submit a CFR and it will be addressed via contract modification.
Q7. What is the maximum lifting height of the jacking system?
A7. As stated in solicitation amendment 0002, jacking height required is at least 1 ft (30 cm) or higher.
2. Extend the quote submission closing date from 13 July 2026 to 27 July 2026, 11:00 AM Japan Standard Time (JST) to allow prospective contractors adequate time to prepare their quotation.
All other terms, conditions, specifications, and provisions of the original solicitation remain unchanged.
Solicitation/Contract Form Continuation
The following changes have been made:
INFORMATION FROM TO
Response Due Date 13 Jul 2026 27 Jul 2026
N6264926QB0400003
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0003 |
| EffDate: 13 Jul 2026 |
| ReqNo: See Continuation Sheet |
| ProjNo: |
| IssCode: N62649 |
| AdmCode: |
| IssuedBy: NAVSUP FLT LOG CTR YOKOSUKA |
PSC 473 BOX 11, FPO AP 96349-1500
FPO, AP 96349-1500
UNITED STATES
Janice Arrieta, Email: janice.o.arrieta.ln@us.navy.mil Telephone: 0468162793 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: N6264926QB040 |
| SolDate: 29 May 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Continuation |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: Maria Crispina C. Mallari |
| ContDate: |
| CODate: 13 Jul 2026 |