TGI_3819P14122A01_c0v0_FY26.pdf
PDF 163 KB Posted
- Solicitation number
- N6264925RA024
About this file
This is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, focused on replacing the electrical grade sheet deck covering system in Emergency Switchgear Room No. One (6-30-2-E). The project involves removing and replacing 370 square feet of existing electrical grade sheet deck covering, including 310 square feet of deck covering system and 60 square feet on a false floor, specified to MIL-DTL-15562, Type One, with a blue mableized color. The work includes deck plating and vertical structural surfaces up to one inch from the complete deck covering system level.
The project is scheduled for contractor work from 7/21/2026 to 11/19/2027, with potential asbestos and lead hazards identified. SRF-JRMC will provide government-furnished material and services, including crane and rigging, utility services (electrical, low pressure air, water, and steam), safety inspections, gas-free inspections, and quality assurance inspections. The task involves carpentry, painting, electrical work, and quality assurance personnel, with material orders for floor matting prepared by M. Haga from Code 231B.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
23-AUG-2024 0835
20.14.15.0.8993 (August 2024) ICN: 3819P14122 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-30-2-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE ELECTRICAL GRADE SHEET DECK COVERING SYSTEM IN 6-30-2-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
EE010196
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
HAGA, MASAMICHI 231B 3152432513 12-JUL-2024
APPROVED BY: CODE: PHONE: DATE:
NAKANO, SEIICHI 231B 3152434519 12-JUL-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EE01-0196
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 6-30-2-E 6 P
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
141A0022
1. SCOPE/PURPOSE:
1.1 Title: Electrical Grade Sheet Deck Covering System in 6-30-2-E; replace
1.2 Location of Work:
1.2.1 Emergency Switchgear Room No. One (6-30-2-E)
1.3 Identification:
1.3.1 Quantity (310 SF), Electrical Grade Sheet Deck Covering System [Existing]
1.3.2 Quantity (60 SF), Electrical Grade Sheet on False Floor [Existing]
1.3.3 Quantity (370 SF in Total), Electrical Grade Sheet
Specification: MIL-DTL-15562, Type One
TGI Short Form
23-AUG-2024 0835
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14122 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-30-2-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE ELECTRICAL GRADE SHEET DECK COVERING SYSTEM IN 6-30-2-E
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
Color: Blue Mableized
1.3.4 Quantity (370 SF in Total), Deck Plating, including vertical structural surface up to height of One inch from complete electrical grade sheet deck covering system level
Remarks: The area excepts inside of false floor and foundation
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.5.2 Potential Lead Hazard
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/19/2027
2. PROCEDURE:
2.1 Accomplish the requirements of 009-26 of Ref. No. One, including Attachment D, for removal of each existing equipment listed in 1.3.1 and 1.3.2, and installation of each new equipment listed in 1.3.3.
2.1.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 9, for each area listed in 1.3.4.
2.2 Notes:
2.2.1 Planner: Code 231B M. Haga, 243-2513
Planner: Code 233 K. Uchimura, 080-9350-1432
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN EE01-0196 is related to this TGI.
2.3 Government Furnished Material (GFM):
2.3.1 SRF-JRMC will provide GFM listed in the Material List.
2.4 SRF-JRMC will provide the following service work: (TGI No. 3819P14122S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
23-AUG-2024 0835
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14122 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-30-2-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE ELECTRICAL GRADE SHEET DECK COVERING SYSTEM IN 6-30-2-E
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbol(s).
23-AUG-2024 0835
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14122 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-30-2-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE ELECTRICAL GRADE SHEET DECK COVERING SYSTEM IN 6-30-2-E
FOUO Pg 4 of 4
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 CARP HRs, PNTR HRs, QA HRs, SFTR HRs, ELEC HRs 22/KE PC N
Preservation Work CFM: $ for all deck covering, paints, thinners, nonslip tape, sampler/analyze asbestos and lead, and MISC such as covering material and other consumable.
22/MQ CS N
Electrical Work CFM: $ for banding material, fasteners, insulation tape, plastic bags, rope, and other consumable.
22/MQ CS N
Process Funding Document. 10/CT OM N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
500 M MATTING,FLOOR, MATERIAL
ORDER FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 7220 010249040 NA 4 N 40905067 1/RO
501 M MATTING,FLOOR, MATERIAL
ORDER FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 7220 010249040 NA 4 N 40475232 2/RO
502 M MATTING,FLOOR, MATERIAL
ORDER FOR KTR
ORIG: C231B M.HAGA 243-2513
9Q 7220 010249040 NA 4 N 40905066 1/RO
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P14122 KEY OP: A01