This document is an amendment to a Request for Interest issued by the Department of the Navy for a potential long-term lease under 10 U.S.C. 2667 of 11,000 acres of underutilized, non-excess agriculture land at Naval Air Station Lemoore. The amendment provides government responses to industry questions, presentation slides from an Industry Day and Site Tour held on February 29, 2024, and a list of companies registered to attend the Industry Day. Interested entities are sought to develop and operate critical energy resiliency infrastructure and/or water utility options on the land to support the installation's mission while contributing to the government's energy and water goals. The deadline for responses to the RFI is May 1, 2024 at 4:00 PM Pacific Time.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES I
3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
SOUTHWEST DIVISION
NAVAL FACILITIES ENGINEERING COMMAND
CONTRACTS DEPARTMENT
1220 PACIFIC HIGHWAY
SAN D I EGO, CA 92132-5187
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county State and ZIP Code)
FACILITY CODECODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
is extended, is not extended.The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning______ copies of the amendment; (b) By acknowledging receipt of this amendment on each copx of the offer submitted; or (c) By separate letter or telegram which includes a reference of the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIED THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
Except as provided herein, at/ terms and conditions of the document referenced in Item 19A or 10A, as heretofore changed, remains unchanged and In full force and effect
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
BYBY
(Signature of Contracting Officer)(Signature of Person Authorized to Sign)
STANDARD FORM 30 (REV. 10-83)
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDERED IS MODIFIED TO REFLECTTHE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) erin.wilson Line erin.wilson Line
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor) . For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting offier's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification) .
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
Total contract price increased by $
Total contract price decreased by $
Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
A reference to the letter determination; and
A statement of the net amount determined to be due in settlement of the contract.
(g)
(h)
(i)
(ii)
(1)
(2)
(3)
(4)
(5)
(6)
(i)
(ii)
(iii)
STANDARD FORM 30 (REV. 10-83) BACK
(1) Accounting classification Net increase $
March 12, 2024
RFI No. N6247324RP00064
AMENDMENT ONE (1)
GOVERNMENT RESPONSES TO INDUSTRY QUESTIONS
REQUEST FOR INTEREST (RFI) No. N6247324RP00064
The Navy held an Industry Day and Site Tour for interested industry entities on February 29, 2024 at Naval Air Station, Lemoore. The Industry Day provided an opportunity for representatives of the government and industry to meet for presentations and a site tour.
If you submitted a clarifying question on the RFI to NAVFACHQNavySWEULs@us.navy.mil, please note that it has been received and all comments and questions will be reviewed for appropriate action.
Individual responses may not be provided. The Government retains the right to respond to all, a portion of or provide no response to interested proposer’s questions. The Government will post any prepared response(s) to written questions via SAM.gov.
INDUSTRY CLARIFYING
QUESTION:
DEPARTMENT OF NAVY (DoN)
RESPONSE:
Request for Interest N6247324RP00064 – Naval Air Station Lemoore Energy Enhanced Use Lease
Industry Day and Site Tour
1 Can we get a copy of the slides used during the Industry Day presentation?
The Navy held an Industry Day and Site Tour for interested entities on February 29, 2024 at Naval Air Station, Lemoore. Industry Day presentation slides are attached hereto on pages 4 through 41 as part of this Amendment One (1).
2 Can we get a list of all the participants from Industry Day and Site Tour?
The Navy held an Industry Day and Site Tour for interested entities on February 29, 2024 at Naval Air Station, Lemoore. A list of all registered companies is attached hereto on page 42 as part of this Amendment One (1).
Clarifying Questions
3 Where will answers to Industry’s clarifying questions be posted?
The Government will post any prepared response(s) to written questions via SAM.gov.
The Government retains the right to respond to all, a portion of, or provide no response to Industry Questions.
Industry Day Presentation Slides
Welcome!
We will begin at 1000 PT
Naval Air Station (NAS) Lemoore
29 February 2024
Enhanced Use Lease (EUL) – Site 2 Developer Conference
Enhanced Use Lease (EUL) Developer Conference
Agenda
Check-in and Registration 9:00 – 10:00 AM
Welcome and Opening Remarks 10:00 – 10:30 AM
EUL Concept Overview and Base Requirements 10:30 – 11:15 AM
EUL Real Estate Process 11:15 – 11:30 AM
PG&E Connection Overview 11:30 – 11:45 AM
EUL Technical Process Q&A 11:45 AM – 12:30 PM
Lunch 12:30 – 1:45 PM
Site Tour 2:00 – 3:00 PM
Welcoming Remarks
CAPT Shawn P. O’Connor – Commanding Officer, NAS Lemoore CDR Samuel Lee – Public Works Officer, NAS Lemoore
Captain Shawn P. O’Connor Commanding Officer
Commander Lou Findlay Executive Officer
Master Chief Joseph Silveira Master Chief
Commander Sam Lee Public Works Officer
Mission:
As the Navy’s largest Master Jet Base, man, train, and equip the aviation mission supporting the F/A 18E/F Super Hornet and the F-35C Lighting II.
Naval Air Station Lemoore
Major Supported Commands
TOTAL NAS LEMOORE TENANTS: 54
Major Commands
• Strike Fighter Wing Pacific
• Joint Strike Fighter Wing (established 2 years early 01 AUG 2018)
• Fleet Readiness Center West (FRCW)
• Naval Health Clinic Lemoore
• Carrier Air Wings
• CVW-2
• CVW-9
• CVW-11
• CVW-17
• CVW-1 (VFA-136)
Other Commands
• F/A-18 E/F Fleet Replacement Squadron (VFA-122)
• F-35C FRS (VFA-125) reestablished 12 Jan 2017
• Strike Fighter Weapons School Pacific
• Center for Naval Aviation Technical Training Unit (CNATTU)
• Naval Aviation Maintenance Center for Excellence (NAMCE)
• 14 FA-18E/F and 2 F-35C Deployable Squadrons http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=&url=http://www.military.com/unitpages/unit.do?id%3D722428&psig=AFQjCNFelyLjsOeh3riyds5VefZUWa3u2A&ust=1477682944291630 https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwjWiOHh4oXQAhUJSCYKHci2BskQjRwIBw&url=https://en.wikipedia.org/wiki/Carrier_Air_Wing_Two&psig=AFQjCNGdsODyXgTq7fbgV3QA_Un-OcJKLQ&ust=1478028330871565 https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwia3Z2N44XQAhVCOCYKHZr1AJcQjRwIBw&url=https://en.wikipedia.org/wiki/Carrier_Air_Wing_Nine&psig=AFQjCNHPk8GmPI_WEUGaE0FVEA1qhUuztQ&ust=1478028419015737 http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwjj5sip44XQAhWD4iYKHUZBDoUQjRwIBw&url=http://militarybest.com/caairwi11cvw.html&bvm=bv.137132246,d.eWE&psig=AFQjCNE1ApFTe38BqcrpQM5dxwj9WgCtdQ&ust=1478028470652029 http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwjOyOzA44XQAhXDKCYKHecvAqMQjRwIBw&url=http://military.wikia.com/wiki/Carrier_Air_Wing_Seventeen&bvm=bv.137132246,d.eWE&psig=AFQjCNGPKWjtDqpm5MC7_NjczywoTxs4TQ&ust=1478028509488290 http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwj4xv3044XQAhVEzVQKHUI_DWQQjRwIBw&url=http://www.csfwp.navy.mil/&bvm=bv.137132246,d.eWE&psig=AFQjCNEXiGEvG9_nNhSXeqnxp6z2TrwuUw&ust=1478028637937184
NAS Lemoore Growth
NASL Completed Growth
• 19% increase in Squadrons (3)
• 2 FA-18 Squadrons; VFA 86, VFA 136
• 1 F-35C FRS VFA 125 FY17
• CJSFW established 2018
• NAMCE established 2018 (400 pers)
• 13% increase (1500+) in Military, Civilians, Contractors & Dependents
NASL Remaining Growth
• Complete manning of VFA-125 (600+) in MIL, Civilians, Contractors & Dependents
• CVW 14 re-establishment – potentially command staff and 2 squadron re-balance NASL End State
• 11 F/A-18 E/F Fleet Squadrons
• 1 F/A-18 E/F FRS Squadron
• 7 F-35C Fleet Squadrons
• 1 F-35C FRS Squadron
• 1 Search and Rescue (SAR) unit
Land Overview
City of Fresno Population ≈ 542,530 Kings County Population ≈ 153,617
Hanford Population ≈ 56,475 Lemoore Population ≈ 26,200
NAS Lemoore Population ≈ 14,700 (Active Duty, DoD CIVs, Dependents, Contractors)
Encroachment
As required by the state of California NAS Lemoore identified the Military Influence Area (MIA)
• NASL MIA is a designated 614 sq mile Geographic Planning Area
• Military Operations may impact local community or;
• Local community may impact flight operations
NASL EUL Potential Sites
AICUZ
Air Operations
Natural Resources
• Six designated natural resources management areas (NRMAs) with 621 acres restricted from development
• Parcels surrounding the landfill o Burrowing owl habitat, potential development restrictions
• Bird/Wildlife Aircraft Strike Hazard (BASH) o Development should use best practices to avoid attracting birds and wildlife to the airfield
• Potential development should maintain existing Ag related infrastructure (e.g., wells, water lines and access roads)
• Existing evaporation ponds are likely contaminated, reuse may present challenges
Questions
EUL Concept Overview and Base Requirements
Calvin Kawamura – Southwest Energy Program Director Adam Hill – NAVFAC Southwest EUL Project Manager Doug Macurda – NAVFAC Southwest EUL Project Manager
Industry Day Overview
Objective: Engage with industry and the development community to discuss potential EUL projects and opportunities. The purpose of an EUL Industry Day is to provide information on EUL programs, projects, and processes and to encourage potential developers to submit information and future proposals for EUL projects.
EULs are innovative compared to traditional utility projects for several reasons:
• Public-Private Partnership between the military and private sector entities, where the private sector provides financing and expertise to support energy and water resilience initiatives on military installations.
• Flexibility: EULs allow the military to enter into a wide range of agreements with private sector entities to achieve energy and water resiliency goals.
• EULs provide an opportunity to test and implement innovative technologies and business models that are designed to support energy and water resilience.
• EULs allow for more efficient use of land on military installations, as the land can be used for multiple purposes, including energy and water resilience initiatives.
• EULs encourage collaboration between the military, private sector, and local communities, as all parties work together to achieve common goals related to energy and water resilience.
Mission Objective: NASL prioritizes energy resiliency and redundancy while maintaining operations during utility service disruptions and is committed to energy and water conservation, which is crucial during the F/A-18 Super Hornet transition to the F-35C Joint Strike Fighter that will increase energy use.
The EUL is important for NAS Lemoore’s mission objectives by:
• Providing a long-term value stream NAS
Lemoore via up-front capital investment, ground lease payments, cash and/or In-Kind Consideration.
• Supplying reliable and resilient energy and water to sustain daily operations, such as, training and supporting military personnel and providing logistical support for missions.
• Improving energy and water efficiency can also help reduce costs and enhance sustainability.
• Entering a long-term ground lease with responsible party(ies) who will provide good-stewardship over the property
Naval Air Station (NAS) Lemoore
The Navy is seeking industry feedback on implementing innovative and critical energy infrastructure resiliency projects aboard NAS Lemoore.
To best achieve this project goal, the DON seeks information on potential long-term partnerships to plan, design, construct and operate facilities that may include, but are not limited to:
• Upgrades to aging electrical distribution infrastructure
• Replacement of legacy electrical equipment (transformers, switchgear, etc.)
• Upgrades to water distribution infrastructure, pre/post storage tanks, pump stations or other supporting infrastructure
• Maximize water conservation through activities that positively impact groundwater recharge, stormwater retention, and sustainable land management
• Align with the FY2023 Buildings Strategic Plan which aims to reduce potable water consumption by 15%
Feedback will be considered Proprietary and Business Confidential and will not be shared with other industry parties.
In Kind Consideration
Examples of in-kind consideration (IKC) includes:
Energy Resiliency Projects
- Microgrids
- On-base renewable generation
- Energy storage and distribution
- Energy management
Maintenance, protection, alteration, repair, improvement, or restoration (including environmental restoration) of property or facilities
Installation infrastructure to support electrification of facilities and vehicles
Opportunities to reduce both water consumption and the corresponding energy required to support water requirements
The process for creating an EUL typically involves the following steps:
1. Identification of Navy land for potential EUL use: The Navy identifies land that is not currently being used for military purposes and may be suitable for an EUL.
2. Request for Proposals (RFP): The Navy issues a Request for Proposals (RFP) inviting private sector entities to submit proposals for using the identified land.
3. Proposal evaluation: The Navy evaluates proposals received in response to the RFP, considering factors such as the proposed use of the land, the financial benefits to the Navy, and the impact on the local community.
4. Negotiations: If a proposal is selected, the Navy enters into negotiations with the private sector entity to determine the terms and conditions of the EUL.
5. Approvals and Executions: The EUL must be approved by various parties, including the Secretary of the Navy, the Office of the Secretary of Defense, and other relevant government agencies, before it can be executed.
6. Implementation and monitoring: After the EUL is executed, the private sector entity begins to develop the land for its proposed use, and the Navy monitors the implementation of the EUL to ensure that it complies with the terms and conditions agreed upon.
This process is subject to various regulations and guidelines that ensure that EULs are consistent with the Navy's overall mission and goals, and that they provide the maximum benefit to the Navy and the local community.
EUL Studies, Financing and Offtake
Study considerations: Before an EUL project can begin, an EUL developer is responsible for a range of preconstruction surveying and analysis must be conducted to ensure that the project is feasible and will meet all legal and regulatory requirements. Some of the common types of preconstruction surveying and analysis include:
Financing considerations: EUL developers are typically responsible for securing the financing needed to complete the project. This may include securing loans from banks or other financial institutions, seeking investment from private equity firms, or raising capital through other means.
Offtake considerations: Once the project is completed, the developer must find a buyer for the energy or water that is produced. This may involve negotiating long-term offtake agreements with utilities, other government agencies, or private sector entities. The developer is responsible for ensuring that the offtake agreements are in place and that the project can generate the expected revenue.
• Environmental Analysis
• Archaeological Surveys
• Geotechnical Surveys
• Hazardous Materials Surveys
• Site Analysis
• Economic Analysis
• Zoning Analysis
Rest Break: 15 mins.
We will be back at 1105 PT
Real Estate Authority and Request for Interest Submittal Instructions
Lindsey Green – NAVFAC Southwest, Real Estate Contracting Officer Erin Grandgirard – NAVFAC Southwest, Senior Realty Specialist
Commercial Outleasing (COL) - What To Know Up Front
Real Estate Authority 10 U.S.C. 2667 – Leasing Authority – Navy Out-Lease property for receipt of In-Kind consideration defined as rehabilitation, on-going maintenance, new construction and/or redevelopment
Fair Market Value (FMV) Requirement
• Non-Federal users required to pay at least FMV. Government appraisal is proprietary and not shared
Competition Requirement
• Competitive procedures will be used for leasing use of DON real property
$750K Threshold 10 U.S.C. 2662
• Actions involving FMV over $750k require Congressional Notifications
COL - What To Know Up Front cont.
Acquisition of Real Estate interests is unique
• Expressly authorized by law; not governed by Federal Acquisition Regulations
(FAR)
Admin Fees 10 U.S.C. 2695
• Lessee required to pay for DON administrative fees associated with lease execution
National Environmental Policy Act completion prior to lease execution
Site approval is required and can take up to six months
COL Process (Major Steps)
DON EUL/COL Examples
Energy EUL Examples
Example: Naval Weapons Station Seal Beach Energy Resilience
• ~60 acre parcel of unimproved land within NWS Seal Beach
• Up to 10 MW output of solar photovoltaics
• Up to 10 MW battery energy storage capacity
Example: Naval Air Station Lemoore Energy Resilience
• ~930 acre parcel of unimproved agriculture land outside NAS Lemoore fence line
• Multiple options for energy resilience being analyzed
NWS Seal Beach
NAS Lemoore
COL (Commercial Outlease) Example
Broadway Complex San Diego, CA
• 15 acres of Navy land
• 2.5-acres for 17 story, 373,000
SF Navy Administration Building as in-kind consideration
• 12.5-acres on 99-year lease for private development
373,000 SF Navy Administration Building
Request for Interest (RFI)
RFI Posted to SAM.gov [Notice ID N6247324RP00064]
Develop/utilize up to 11,000 acres of unimproved agriculture land
Highlights of RFI:
• Real Estate Authorities
• Project Objectives
• RFI Response Submission and Important Dates
• Supporting Document Enclosures
SCAN ME FOR RFI
RFI Important Dates and Submission Instructions
Date Milestone
February 29, 2024 Industry Day and Site Tour
April 11, 2024 Last day to submit Clarifying Questions
May 1, 2024 4:00 p.m. Pacific Time RFI RESPONSES DUE
Submit Clarifying Questions and RFI Submissions to NAVFACHQNavySWEULs@us.navy.mil mailto:NAVFACHQNavySWEULs@us.navy.mil
Real Estate Contracting Officer & Real Estate POCs
Lindsey Green – Real Estate Contracting Officer (RECO)
Erin Grandgirard – Senior Realty Specialist
Jonathan Mather – Realty Specialist
Per SECNAV, only RECOs are authorized to enter into, negotiate, modify or terminate real estate contracts
EUL Technical Process Q&A
Lunch Break: 12:30 – 1:45 PM
NAS Lemoore Lunch Options
Spuds (Buffet/Salad/Sandwiches/Pizza) 870 Franklin Ave., Lemoore 93246
Tailhook Bowling Center (Cheeseburgers/Sandwiches) 823 Hancock Cir., Lemoore 93246
Exchange Food Court (Subway/Panda) 796 Reeves Blvd., Lemoore 93246
McDonalds 870 Franklin Ave, Lemoore 93246
EUL Site Tour
Please Complete Waiver Form prior to boarding the bus
Companies Registered to Attend Industry Day and Site Tour
NAVAL AIR STATION, LEMOORE, POTENTIAL ENERGY ENHANCED USE LEASE
REQUEST FOR INTEREST #N6247324RP00064
Companies Registered to Attend Industry Day and Site Tour
February 29, 2024
1. AES 30. Salas Obrien
2. Ameresco 31. Siemens
3. Arup 32. Stantec
4. Becker Captial 33. Terra-Gen LLC
5. Bowen US 34. Zeltmatcher
6. CEG
7. Centrica
8. Deloitte
9. ECC
10. Edged Energy
11. Enchanted Rock
12. Energy Systems Group
13. Form Energy
14. Golden State Clean Energy
15. Goldman Sachs
16. Grid Scape
17. Hensel Phelps
18. Innovative Construction Solutions
19. Key Banc
20. Kiewit
21. Kleinfelder
22. Longroad Energy
23. Macquarie
24. Meridiam
25. Next Era
26. Noresco
27. Power Engineers
28. PowerSecure, Inc.
29. Provident Resouces Group
| Amendment One (1) - N6247324RP00064 12 March 24 |
| Amendment Five (5) - N6247323RP00008 30 Jan 23 |
| Amendment Three (3) - N6247323RP00008 19 Dec 2022 |
| Amendment 2 - N6247323RP00008 Combined |
| Amendment 2 - N6247323RP00008 |
| Lemoore Phase 2-Goverment Responses to RFIs 11 March 24 |
| NAS Lemoore EUL Industry Day Presentation_29FEB2024_Final |
| Welcome! |
| Slide Number 2 |
| Enhanced Use Lease (EUL) Developer Conference |
| Slide Number 4 |
| Naval Air Station Lemoore |
| Major Supported Commands |
| NAS Lemoore Growth |
| Land Overview |
| Encroachment |
| NASL EUL Potential Sites |
| AICUZ |
| Air Operations |
| Natural Resources |
| Questions |
| Slide Number 15 |
| Industry Day Overview |
| Naval Air Station (NAS) Lemoore |
| The Navy is seeking industry feedback on implementing innovative and critical energy infrastructure resiliency projects aboard NAS Lemoore. |
| In Kind Consideration |
| The process for creating an EUL typically involves the following steps: |
| EUL Studies, Financing and Offtake |
| Slide Number 22 |
| Slide Number 23 |
| Commercial Outleasing (COL) - What To Know Up Front |
| COL - What To Know Up Front cont. |
| COL Process (Major Steps) |
| DON EUL/COL Examples |
| Energy EUL Examples |
| COL (Commercial Outlease) Example |
| Request for Interest (RFI) |
| RFI Important Dates and Submission Instructions |
| Real Estate Contracting Officer & Real Estate POCs |
| Slide Number 33 |
| Slide Number 34 |
| Slide Number 35 |
| NAS Lemoore Lunch Options |
| Slide Number 37 |
Lemoore Phase 2-Goverment Responses to RFIs 11 March 24_page 42
| 1_CONTRACT_ID_CODE: N6247324RP00064 |
| Page: 1 |
| of Pages: 42 |
| 2_AMENDMENT/MODIFICATION NO: One (1) |
| 3_EFFECTIVE DATE: 03/12/2024 |
| 4_REQUISITIONPURCHASE_REQ: |
| 1_5_PROJECT_NO_11appitcab: |
| 6_ISSUED_BY: NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND SOUTHWEST |
REAL ESTATE DEPARTMENT
750 PACIFIC HIGHWAY
SAN DIEGO, CA 92132-5190
| CODE: REBL.EG |
| 7_ADMINISTERED_BY: |
| CODE1: |
| 8_NAME_AND_ADDRESS_OF_CON: N/A |
| CODE2: |
| FACILITY_CODE: |
| 9A_AMENDMENT_OF_SOLICITAT: |
| 9B_DATED_SEE_ITEM_1_1: |
| 10A_MODIFICATION_OF_CONTR: |
| 10B_DATED_SEE_ITEM_13: |
| The_above_numbered_solici: Off |
| is_extended: Off |
| 12_ACCOUNTING_AND_APPROPR: |
| 13A: Off |
| 13B: Off |
| 13C: Off |
| C_THIS_SUPPLEMENTAL_AGREE: |
| 13D: Yes |
| D_OTHER_Specify_type_of_m: Amendment One (1) to Solicitation N6247324RP00064 |
| E: |
| Contractor: Off |
| # of copies: |
| 14 DESCRIPTION_OF_AMENDMENT/MODIFICATION: The intent of this amendment is to make the following update/change: |
1) Government responses to industry questions as attached hereto on page 3.
2) The Navy held an Industry Day and Site Tour for interested entities on February 29, 2024 at Naval Air Station, Lemoore. Industry Day presentation slides as attached hereto on pages 4 through 41.
3) List of Companies registered to attend Industry Day and Site as attached hereto on page 42.
| 15A_NAME_AND_TITLE_OF_SIG: | |
| BY2: | |
| 15C_DATE_SIGNED: | |
| 16A_NAME_AND_TITLE_OF_CON: LINDSEY E. GREEN, Real Estate Contracting Officer | |
| BY1: | |
| 16C_DATE_SIGNED: | |
| RESET: | |
| Act ClaIn: | |
| NetInc: | |
| ActClaDe: | |
| NetDec: | |
| PriceInc: | |
| PriceDec: | |
| 2024-03-13T13:47:14-0700 | |
| GREEN.LINDSEY.E.1265653045 |
File details come from the government source that posted it. Updated .