This document provides an amendment to a federal solicitation for electrical work. The amendment incorporates responses to contractor questions, extends the deadline for questions to August 3rd and extends the proposal deadline to August 15th. Additional drawings and specifications are included. The solicitation requires the relocation of electrical equipment and replacement of a transformer at Building 339 at Naval Support Activity Monterey. The base bid includes demolition and removal of existing medium voltage and low voltage equipment, and installation of new equipment outdoors. There are optional items to relocate a photovoltaic inverter above grade and provide temporary power to Building 310. Only proposals from woman-owned small businesses will be considered for this opportunity with the Department of the Navy.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 August 2022
Subj: AMENDMENT 002 – SOLICITATION NO. N6247322R3201: RELOCATE ELECTRICAL PANEL
AND REPLACE TRANSFORMER, BLDG. NO. 339, NAVAL SUPPORT ACTIVITY MONTEREY
(NSAM), CA 93943-5035
A. Subject amendment incorporates Government responses to contractor submitted Requests for Information
(RFIs) into the solicitation.
B. The due date for contractor submission of RFIs is extended to 2:00 P.M. (PST), Wednesday, 3 August 2022.
C. The proposal due date is extended to 11:59 P.M. (PST), Monday, 15 August 2022.
D. All other paragraphs, provisions, and conditions of this solicitation remain unchanged.
E. The following sketches/drawings, and accompanying specifications/other attachments are included, and herein incorporated into the solicitation via Amendment 002:
1. 6363561-E16
2. 6363565-E20
3. 6363566-E21
4. 18048240-E0.50
5. 18048246-E7.01
6. 18048248-E8.50
7. 18048249-E8.51
8. 18048250-E9.01
9. Aerial View - Project Location
10. B339 Single Line Diagram – Conceptual
11. Basement Equipment
12. Desired Equipment Relocation
13. Electrical Distribution System Modified HV Electrical Site Plan
14. HVSS-10 and Switchboard Enclosure
15. MH4 Interior
16. MH4 Location
17. PV Inverter Enclosure Example
18. PV Inverter
19. RFI 023
20. RFI 033
21. T34 - Primary Feeders
22. T34 - Secondary Feeders
23. T34
REQUESTS FOR INFORMATION (RFIs)
[RFI 001] “During the site visit it was said that there was additional documents for this project. Can you please send out the part 1-6 RFP files and asbuilts for this project?”
[GOV RESPONSE RFI 001] Amendment 001 incorporated additional attachments and available as-built drawings into the solicitation. Additional sketches/drawings, and accompanying specifications/other attachments are incorporated into the solicitation within this amendment, Amendment 002.
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND SOUTHWEST
FACILITIES ENGINEERING AND ACQUISITION DEPARTMENT
511 GARDNERS ROAD, BUILDING 426
MONTEREY, CA 93943-5035
AMENDMENT 002 – SOLICITATION NO. N6247322R3201: RELOCATE ELECTRICAL PANEL AND
REPLACE TRANSFORMER, BLDG. NO. 339, NAVAL SUPPORT ACTIVITY MONTEREY (NSAM), CA
93943-5035
[RFI 002] “Drawings and Plans that were to be included with the RFP are needed. Unable to proceed with any additional RFI’s until we have the plans and drawings.”
[GOV RESPONSE RFI 002] Amendment 001 incorporated additional attachments and available as-built drawings into the solicitation. Additional sketches/drawings, and accompanying specifications/other attachments are incorporated into the solicitation within this amendment, Amendment 002.
[RFI 003] “Will you be providing the Site Visit Sign in sheet? My first RFI is to confirm that this is to be awarded to a WOSB?”
[GOV RESPONSE RFI 003] No, a sign-in sheet will not be provided to contractors. Yes, consideration will only be given to Woman Owned Small Business (WOSB) firms.
[RFI 004] “The RFP clearly states that the Superintendent may not serve as the Quality Control Manager. Can the Superintendent or Quality Control Manager have other duties and serve as the Site Safety Health Officer? Or, will a separate SSHO be required? Three separate individuals.”
[GOV RESPONSE RFI 004] The Superintendent may serve as the SSHO for this project.
[RFI 005] “Part 3 Statement of Work/Project Program, Para. 2.1 indicates that the new medium voltage selector switch must be installed outdoors and secured on top of a concrete pad. Does the Government have a desired location for the new medium voltage switch?”
[GOV RESPONSE RFI 005] “The KTR shall determine placement of the new equipment after surveying site utilities. See attachment images “Aerial View - Project Location.jpg” and “Desired Equipment Relocation.jpg” for desired location.
[RFI 006] “Part 3 Statement of Work/Project Program, Para. 1.1 and 2.1 both indicate that there is an existing 750 KVA oil filled transformer located exteriorly west of Bldg. 339 to be replaced. Is this the same transformer identified in the Statement of Work as ‘Building 339 transformer (T34)?’ At the site visit it was indicated that this transformer was not to be replaced. Please clarify.”
[GOV RESPONSE RFI 006] T34 is to be replaced. T2 is not to be replaced. See attachment image “Aerial View - Project Location’ and “T34” for identification and location of transformers.
[RFI 007] “Part 3 Statement of Work/Project Program, 2.1 also states that the new transformer (T34) mentioned above be relocated to a new location. Does the Government have a desired location for the new transformer?”
[GOV RESPONSE RFI 007] The KTR shall determine placement of the new equipment after surveying site utilities.
See attachment images “Aerial View - Project Location” and “Desired Equipment Relocation’ for desired location.
[RFI 008] “Part 3 Statement of Work/Project Program, 2.1 states to replace the existing low voltage load center service entrance equipment (switchboard) located in the electrical basement of Bldg. 339. This panel was not identified at the site visit. Is the low voltage service load center (switchboard) to be replaced the same as the panel identified as panel ‘M’ on the Single Line Diagram provided with Amendment #0001?”
[GOV RESPONSE RFI 008] Scope is to replace and relocate HVSS-10 and Secondary Service equipment in basement. The lighting panel and Power Monitoring Interface is to remain in place. Demolish and dispose vacant communication rack. See attachment image “HVSS-10,” “Switchboard Enclosure,” and “Basement Equipment” for equipment identification.
[RFI 009] “The single line diagram as-built drawing provided with Amendment #0001 indicates that the medium oil-filled switch, 750 KVA transformer, and the low voltage load center service entrance equipment referred to in the Statement of Work is all included within one enclosure (1 piece of equipment). However, the Statement of Work suggests otherwise. Please clarify.”
[GOV RESPONSE RFI 009] See attachment image “HVSS-10,” “Switchboard Enclosure” and “T34” for equipment identification.
[RFI 010] “Will a Commissioning Agent be required?”
[GOV RESPONSE RFI 010] No.
[RFI 011] “Will a third party Commissioning Agent be required?”
[GOV RESPONSE RFI 011] No.
[RFI 012] “Can The QC Manager, SSHO and Superintendent be one person?”
[GOV RESPONSE RFI 012] The Superintendent may serve as the SSHO for this project.
[RFI 013] “Will a Fire Protection Engineer be required?”
[GOV RESPONSE RFI 013] No.
[RFI 014] “Due to the current state of the market the time for procurement of long lead items can take up to 52+ weeks after the product submittal has been approved by the Government. Contractor would recommends that the period of performance be changed from 550 calendar days to 655 calendar days due to Design Phase, Procurement Long Lead times and Unknown impact on lead times due to COVID‐19 impact.”
[GOV RESPONSE RFI 014] The request for the period of performance to be extended is not necessary beyond 550 calendar days as the contractor will have the ability to request additional time if equipment is delayed due to COVID-19 impacts.
[RFI 015] “Once RFI questions are answered we are requesting that the proposal due date be extended by 21 calendar days.”
[GOV RESPONSE RFI 015] Government has extended the proposal due date via this amendment to 15 August, 2022. Further delay of proposal submission would not allow for adequate time to award this contract prior to the end of this fiscal year.
[RFI 016] “Contractor would recommend that the project be awarded within 30 days of proposal submission as the manufactures and vendors will only hold their price for no more than 30 days due to the current state of the market.”
[GOV RESPONSE RFI 016] Proposals must be valid for 60 calendar days after submission. This requirement remains unchanged.
[RFI 017] “Are buildings 339 and 310 served by separate utility meters?”
[GOV RESPONSE RFI 017] Yes.
[RFI 018] “Is the photovoltaic system on building 339 only serving building 310?”
[GOV RESPONSE RFI 018] There are two array systems on the roof of B339. One system serves B310 and the other serves B339.
[RFI 019] “Please provide photos of the rooftop PV entrance homeruns.”
[GOV RESPONSE RFI 019] See attachment image “PV Inverter.jpg.”
[RFI 020] “Please provide the underground wire size feeding transformer T-34.”
[GOV RESPONSE RFI 020] See attachment image “T34 – Primary Feeders.jpg”.
[RFI 021] “Please provide copies of 'as built' electrical drawings for buildings 339 & 310.”
[GOV RESPONSE RFI 021] As-built single line was provided for B339 in RFP Part 6. As-built drawings for B310 are attached. All relevant as-built drawings were provided in RFP – Part 6. Additional as-build drawings are attached. Please reference the following as-built drawings for details: “6363561-E16, 6363565-E20, and 6363566- E21”. See attached as-built drawings “18048240-E0.50, 18048246-E7.01, 18048248-E8.50, 18048249-E8.51, and 18048250 –E9.01” for B310 electrical details. All available as-built drawings are available at PW B426 Plan Files room.
[RFI 022] “Building 310 will need to have temporary power during construction. Can you provide the continuous loads or load profile of building 310?”
[GOV RESPONSE RFI 022] B339's max load profile was around 205 KVA within past year. There is no recorded historical data for B310's load profile. Reference electrical drawing "18048250-E9.01.pdf" for existing loading.
[RFI 023] “On the attached picture taken on the walk, location is the room with switch HVSS-10 which is to be relocated:
a. ID This HV switch not shown on Single line provided? Is this switch to be relocated? If so, how does it relate to the single line circuiting?
b. Enclosed breaker – ID this breaker we believe this to be the main to building 339? Again not on the single line? Is this breaker also to be relocated to above ground. If so we need to know the location of the gear this breaker feeds as these secondary feeders will need to be replaced. Will need the distance for estimating feeder cost.
c. Secondary feeders verify wire size as not shown on any docs that have been provided?
[GOV RESPONSE RFI 023] See attachment “B339 Single Line Diagram – Conceptual.jpg” and as-built drawings “6363561-E16, 6363565-E20,” and “6363566-E21” for component and equipment identification.
*Note: Diagram shall be verified on the field. The components and equipment are believed to be configured as shown. Components identified are to be removed. Simplification of new replacement system is desired.
See attachment “T34 – Secondary Feeders.jpg” for secondary feeders size.
Contractor’s attachment is provided for reference via attachment “RFI 023.”
[RFI 024] “Also, can we have the government ID the location of MH4 (Verify that this was the manhole that was opened on the job walk.) If so, we request that the government provide pictures of the interior with the existing splices? Type of existing splice? Will the government require new J-bars at this location.”
[GOV RESPONSE RFI 024] See attachment “MH4 Location.jpg” and as-built drawings “6363565-E20.” Depth is believed to be approximately 10 feet but requires verification. Detailed images of interior of manhole would require a base wide power outage. The Designer of Record (DOR) will determine any required new design features.
[RFI 025] “There appears to be conduits entering the side of HVSS-10 can the government ID the source of these conduits again not identified in as-built documentation.”
[GOV RESPONSE RFI 025] See attachment image “B339 Single Line Diagram – Conceptual” and as-built drawings “6363561-E16,” “6363565-E20,” and “6363566-E21” for component and equipment identification.
*Note: Diagram needs to be verified on the field. The components and equipment are believed to be configured as shown. Components identified are to be removed. Simplification of new replacement system is desired.
See attachment image “T34 – Secondary Feeders.jpg” for secondary feeders size.
[RFI 026] “We could not find instructions on what to do with the transformer once it is removed from Building 339.
Is the Contractor to remove and dispose of the transformer or do we give it back to the customer? Please confirm is the existing transformer 339 to be disposed has PCB’s?”
[GOV RESPONSE RFI 026] See RFP Part 2 Section 01 74 19, Part 3 Section 2.1 and Section 6, G1020, and Part 4 Section F2020.
[RFI 027] “When sizing for the temporary generators we want to be assured we have the correct size and prefer they be sized to the peak loads and not to the main breaker size.
a. Please provide the maximum KVA peak load building 339 has experienced in the last year?
b. Please provide the maximum KVA peak load building 310 has experienced in the last year?
[GOV RESPONSE RFI 027] B339's max load profile was around 205 KVA within past year. There is no recorded historical data for B310's load profile. Reference electrical drawing "18048250-E9.01" for existing loading.
[RFI 028] “We cannot find any information in regards to the design criteria for the new transformer pad.
a. Is there a standard drawing for the pad showing pad size, concrete depth, and concrete reinforcing requirements? Please provide.”
[GOV RESPONSE RFI 028] Refer to "A1010 FOUNDATIONS: CONCRETE EQUIPMENT PADS" and "UFC 3- 550-01: Exterior Electrical Power Distribution" for new transformer pad requirements.
[RFI 029] “Section 2.2 of the RFP makes note the equipment is to be housed in a lockable shed with moisture control but there is nothing mentioned about the exterior elevations or what the shed is to be constructed of.
a. Is it the clients desire to construct the shed with similar exterior design features as in existing buildings 339 and 310?
b. Can the Gov. provide further information for building construction and features?”
[GOV RESPONSE RFI 029] See attachment “PV Inverter Enclosure Example” for example of desired enclosure.
The enclosure in the image houses a similar PV Inverter located at the exterior of Halligan Hall – B234. The enclosure must include a hurricane graded fence with 100% slats. The color scheme is to match the Dudley Knox Library – B339’s exterior color scheme.
[RFI 030] “When reviewing Manhole 4 there was not adequate lighting to see inside the manhole. Please provide the depth of and photos showing the inside of this manhole?”
[GOV RESPONSE RFI 030] See attachment image “MH4 Interior.” Depth is believed to be approximately 10 feet but requires verification. Detailed images of interior of manhole would require a base wide power outage.
[RFI 031] “Please verify the location of all pull boxes effecting buildings 339 and 310?”
[GOV RESPONSE RFI 031] All relevant as-built drawings were provided in RFP – Part 6. Additional as-build drawings are attached. Please reference the followings as-built drawings for details: “6363561-E16,” “6363565- E20,” and “6363566-E21.” See attached as-built drawings “18048240-E0.50,” “18048246-E7.01,” “18048248- E8.50,” “18048249-E8.51,” and “18048250 –E9.01” for B310 electrical details.
[RFI 032] “Please provide the current construction standards specific for the Navy Postgraduate School, at Monterey.”
[GOV RESPONSE RFI 032] Refer to RFP – Part 2 and Part 4, and Unified Facilities Criteria.
[RFI 033] “Please see attached redlined 'as built' drawings for building 339 illustrating two proposed new locations, (Section A and Section B) above grade for the new electrical equipment. The SOW calls for the new electrical equipment to be installed above grade. Are we able to utilize Section A, Section B, or both, as the proposed location of the new transformer, medium, low voltage, and (CLIN) PV Inverter outdoor switching enclosures?”
[GOV RESPONSE RFI 033] The KTR shall determine placement of the new equipment after surveying site utilities.
See attachment images “Aerial View - Project Location” and “Desired Equipment Relocation” for desired location.
The KTR shall determine placement of the new equipment after surveying site utilities. See attachment images “Aerial View - Project Location,” and “Desired Equipment Relocation” for desired location.
Desired location for the relocation of the PV Inverter is where Transformer (T34) currently is located.
Attachment Response: Section A may contain underground irrigation piping and 208V electrical feeds for B310.
Underground surveying is required for all locations. Section B would require proper tree removal.
Contractor’s attachment is available for reference as attachment titled “RFI 033.”
[RFI 034] “Man Hole 4 currently has HV circuits A, B and D running into it, we will be making modification to B and D. What is the tolerance for an outage on all three circuits while work is being done in the vault? Sunday for 8 hours? Please advise.”
[GOV RESPONSE RFI 034] The allowed max continuous outage time would be 10 hours on Saturday or Sunday.
Ashley N. Thornton Contracting Officer