Solicitation/RFP with proposal requirements and evaluation factors for Phase One of this multiple award construction contract (MACC) set-aside for Small Business (FAR 52.219-6) concerns. THE SOLICITATION AND PRE-PROPOSAL PRESENTATION WILL BE AVAILABLE IN ELECTRONIC FORMAT ONLY. No hard copies will be provided. The pre-proposal presentation will be uploaded for viewing as an attachment to the RFP. IT IS THE CONTRACTORS RESPONSIBILITY TO CHECK THE WEBSITE DAILY FOR ANY AMENDMENTS AND/OR CLARIFICATIONS TO.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Standard Form 1442, Block 10: Insert the follow ing language on the front of the SF1442:
INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SMALL BUSINESS SET-ASIDE FOR NEW CONSTRUCTION, RENOVATION AND REPAIR OF GENERAL BUILDING CONSTRUCTION AT VARIOUS LOCATIONS WITHIN THE NAVFAC SOUTHWEST AREA OF RESPONSIBILITY INCLUDING BUT NOT LIMITED TO CALIFORNIA, ARIZONA, NEVADA, UTAH, COLORADO, AND NEW MEXICO
This procurement is 100% set-aside for Small Business concerns for general construction projects at various locations w ithin the NAVFAC Southw est area of responsibility, how ever, it is anticipated that the majority of the w ork w ill be performed in San Diego County, California.
NAICS: 236220 Small Business Size Standard: $33.5 Million Maximum dollar amount for all contracts combined is $99,000,000 Task Order range is $8,000,000 to $15,000,000 Minimum Guarantee is $5,000 Offerors must demonstrate a minimum aggregate bonding capacity of $30 million to allow for the management of multiple concurrent projects at the higher dollar magnitude w ithin the task order range.
Construction Contract – Net 14 days for payment (FAR 52.232-27)
NANCY J. LESAGE 619-532-
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
25-Oct-2013
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______1 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Each TaskOrder
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________2 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________03 Dec 2013 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVFAC SOUTHWEST
CAPITAL IMPROVEMENTS CONTRACTS CORE
CODE RAQ20
1220 PACIFIC HWY
SAN DIEGO CA 92132-5190
N62473
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
619-532-4789FAX:TEL: TEL: FAX:
N62473-14-R-0001 132
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 1 Each
SMALL BUSINESS MACC
FFP
This is an indefinite delivery indefinite quantity (IDIQ) contract for general construction with no pre-established fixed contract prices. The actual amount of work to be performed and the time of such performance will be determined by the Contracting Officer or his/her properly authorized representative, who will issue written task orders to the Contractor. Award of the task order will be on a firm-fixed price basis. Maximum of $99,000,000 is for all contracts combined and will serve as the maximum/NTE amount of the entire contract period. The Government has the option to extend the term of the contract for up to four (4) 12-month periods by written notice to the Contractor within the performance period specified in the Schedule.
MAX
NET AMT
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
000101 UNDEFINED Each Proposed Task Order (PTO) 0001
FFP
MAX
NET AMT
Section 00100 - Bidding Schedule/Instructions to Bidders
SECTION 00100
SECTION 00100
INSTRUCTION TO OFFERORS
1. Inquiries
Inquiries regarding the Request for Proposal (RFP) shall be submitted electronically using the Request for Information (RFI) form provided as an attachment or as an email that contains the same information. The Point of Contact (POC) for inquiries is Nancy LeSage at 619-532-3671, e-mail at nancy.lesage@navy.mil , or via fax at (619) 532-4789. The Government does not intend to respond to inquiries submitted less than 10 days before the proposal receipt date.
2. Proposal Submittal Requirements
Proposals submitted in response to this solicitation shall be formatted as follows and furnished in the number of copies stated herein. A cover letter shall accompany the proposal.
The cover letter shall include—
(a) The solicitation number;
(b) The name, address, telephone and facsimile numbers, and email address of the Offeror;
(c) The DUNS Number, CAGE Code, and Tax Identification Number (TIN) of the Offeror;
(d) The DUNS Number and CAGE Code of each Joint Venture member (if available);
(e) The DUNS Number and CAGE Code of each Lead Design Firm (if available);
(f) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(g) Names, titles, phone and facsimile numbers, and email addresses of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation and;
(h) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
In addition to the cover letter, the Offeror shall submit an Offeror’s Team Consent Form for each subcontractor/teaming partner (e.g., team member, legal partner, subcontractor (i.e. lead design firm), parent company, subsidiary, or other affiliated company, etc.) identified in the Offeror’s proposal.
Proposals shall be submitted in three ring binders or bound, with tabs or separators. Page limits, if stipulated, must be adhered to. Proposals shall be submitted on 8.5” X 11” paper, utilizing both sides of the paper.
The format for the proposal is as follows:
Phase One:
-Cover Letter -Offeror’s Team Consent Form(s) -Joint Venture Agreement (if applicable) -First two pages of SF1442 - with blocks 14 through 20c completed – (All amendments issued must be acknowledged with the number and corresponding issue date) -Financial Questionnaire (Original in sealed envelope from financial institution in original proposal folder only) -Surety Form -FAR Clause 52.209-7 - with (b) completed & DFARS Clause 252.209-7999 - with (b) completed
-VETS-100 and/or VETS-100A Report Submission Confirmation (or Statement of Non-applicability)
Tab 1 - Factor 1, Technical Approach (Exhibit “A,” Organizational Chart, and Signed Copies of
Agreements or Letters of Commitment for Each Member of the Offeror’s Team) Tab 2 - Factor 2, Experience (Exhibits “B”)
Factor 3, Past Performance (Exhibits “C” or CCASS/ACASS Evaluations) (Evaluations should immediately follow the project shown on Exhibit “B” to which they pertain)
THE FOLLOWING EVALUATION FACTORS ARE APPLICABLE ONLY TO THOSE
OFFERORS WHO ARE SELECTED TO PROCEED TO PHASE TWO OF THE SOURCE
SELECTION PROCESS. DO NOT SUBMIT TABS 4 THROUGH 7 IN PHASE ONE PROPOSALS.
Phase Two:
Tab 4 - Factor 4, Safety (Exhibit “D”) Tab 5 - Factor 5, Technical Solution (Narrative and Drawings) Tab 6 - Factor 6, Energy and Sustainable Design (Narrative) Tab 7 - Factor 7, Price (In sealed envelope in original proposal folder only) – The envelope shall contain the following original documents: SF1442 (Solicitation, Offer, and Award) with blocks 14 through 20c completed; Bid Bond (in the amount of 20% for PTO #0001)
Representations and Certifications, Financial Questionnaires, and Surety Forms will not be rated.
However, they will be considered in assessing the Offeror’s responsibility.
Offerors are asked to submit only the information/exhibits required. Do not submit any additional information such as brochures, CDs, or other pre-printed materials.
A total of one (1) original and three (3) hard copies of the complete Phase One proposal in response to this RFP must be received by this office no later than the date and time stated in Block 13 of the SF1442.
Offerors should address all Phase One evaluation factors and shall submit the proposal to the following address:
Naval Facilities Engineering Command Southwest Capital Improvements Contracts Core /RAQ20.NL Attention: Nancy LeSage 1220 Pacific Highway, Building 127 San Diego, CA 92132-5190
Proposal must be clearly marked on the outside of the package with the solicitation number.
LATE PROPOSAL SUBMITTALS WILL NOT BE CONSIDERED. Read the following information carefully.
It is an Offeror's responsibility to deliver its proposal to the proper place at the proper time which includes allowing a reasonable amount of time for the delivery of the proposal (FAR 15.208(a)). Proposals that are received after the stated date and time in Block 13 of the SF1442 will not be considered.
Offerors shall ensure that proposals are mailed or sent by courier in a timely manner to be delivered to the NAVFAC Southwest facility no later than the date and time stated in Block 13 of the SF1442.
Offerors intending to deliver the proposals in person to the facility at the address above are cautioned that this NAVFAC Southwest facility is located in downtown San Diego within a secure Government facility. It is recommended that the Offeror allows for delays in driving through downtown San Diego caused by traffic (both freeway and downtown), train/trolley crossing, parking at the pay lots/meters near the facility, and gaining access to a secure Government facility. No parking or offloading of proposals is available at the Government facility. Proposals are to be delivered to the mailroom in Building 128 and reasonable time shall be allowed for the person in the mailroom to receive and time stamp the proposal. The stamp time is determined from the NAVFAC Southwest facility mailroom time stamp and not any other time keeping equipment that the Offeror may own. Immediately upon proposal delivery the Offeror shall leave the Government facility. An Offeror that does not leave the premises may be requested to leave or escorted by Government security personnel.
3. Pre-Proposal Presentation
(a) A formal "in-person" pre-proposal conference and site visit will not be conducted. The pre-proposal presentation will be posted on the Federal Business Opportunities website at https://www.fbo.gov and Navy Electronic Business opportunities website at https://www.neco.navy.mil/ as an attachment to the RFP. Prospective Offerors are urged to view the pre-proposal presentation. The pre-proposal presentation should be viewed prior to submitting any questions regarding the RFP. Prospective Offerors are advised that the pre-proposal presentation is provided solely for the purpose of explaining the concepts involved in the project and the specifications, terms, and conditions of this solicitation.
(b) A list of Frequently-Asked-Questions (FAQ) with appropriate responses is also provided as an attachment to the RFP. As with the pre-proposal presentation, all firms are encouraged to review the FAQ. The FAQ should be viewed prior to submitting any questions regarding the RFP.
(c) Failure of a prospective Offeror to submit any questions will be construed to mean that the Offeror fully understands all requirements of the solicitation.
(d) All prospective Offerors are advised that this solicitation will remain unchanged unless it is amended in writing. Amendments will be posted on the websites https://www.fbo.gov and https://www.neco.navy.mil/
4. Financial Questionnaire
Offerors shall submit the Financial Questionnaire to their financial institution and request the financial institution complete the questionnaire with regard to the Offeror’s firm. Upon completion of the questionnaire, the financial institution should place the completed questionnaire in a sealed envelope showing the return address of the financial institution and forward it to the Offeror so that the Offeror can include the questionnaire (in the sealed envelope) with the original Offeror’s proposal.
If the Offeror is a joint venture, information should be submitted for the joint venture. If there is no information for the joint venture, information should be submitted for each joint venture partner.
5. Surety Form
Offerors shall submit the Surety Form to report their surety bonding information, verifying aggregate bonding capacity, current available bonding, as well as single project limit. Ensure the name of the Offeror’s surety, including the name and phone number of the Offeror’s agent within the surety, is shown on the form.
If the Offeror is a joint venture, one Surety Form shall be submitted for the joint venture, not the individual partners.
6. System for Award Management
The System for Award Management (SAM) is combining federal procurement systems and the Catalog of Federal Domestic Assistance into one new system. This consolidation includes the functionality from the following systems:
* Central Contractor Registry (CCR)
* Federal Agency Registration (Fedreg)
* Online Representations and Certifications Application (ORCA)
* Excluded Parties List System (EPLS)
Contractors must be registered in the System for Award Management (SAM) prior to award of a DoD contract. In order to participate on this solicitation, contractors must also complete electronic representations and certifications (Reps & Certs). For more information and to complete the electronic Reps & Certs, see the SAM website at http://www.sam.gov. A contract cannot be awarded to a contractor not registered in SAM. Remember to review the NAICS codes listed in your SAM record and make sure that you have listed the NAICS code for this procurement.
Note: FAR Clause 52.209-7 and DFARS Clause 252.209-7999 are not found in the electronic Reps & Certs in SAM;
therefore, Offerors shall submit Section 00600 of this RFP which includes FAR Clause 52.209-7 with paragraph (b) completed to report whether or not they have current active Federal contracts and grants with a total value greater than $10,000,000 and Offerors shall submit DFARS Clause 252.209-7999 with paragraph (b) completed to report whether or not they have any unpaid Federal tax liability or were convicted of a felony criminal violation under a Federal law within the preceding 24 months.
7. Federal Contractor Program
In accordance with Federal Acquisition Regulation (FAR) 22.1303, any contractor or subcontractor with a contract of $100,000 or more with the Federal Government must take affirmative action to hire and promote qualified targeted veterans which includes, special disabled veterans, veterans of the Vietnam-era, recently separated veterans, and any other veterans who served on active duty during a war or in a campaign or expedition for which a campaign badge has been authorized.
Companies must file an annual VETS-100 report, which shows the number of targeted veterans in their work force by job category, hiring location, and number of new hires, including targeted veterans hired during the reporting period and the maximum number and minimum number of employees of such contractor during the period covered by the report. Instructions, information and follow-up assistance is provided at VETS-100 Internet site at http://vets.dol.gov/vets100/ or employers may contact the VETS-100 Processing Center at (301) 306-6752 or e-mail at helpdesk@vets100.com.
A contract cannot be awarded to a contractor that has not submitted a required annual form VETS-100, Federal Contractor Veterans’ Employment Report (VETS-100 Report) if subject to the reporting requirements of 38 U.S.C. 4212(d) for that fiscal year.
8. Incurred Expenses
The Government is not responsible for any costs incurred or associated with preparation and submission of a proposal in response to this solicitation.
9. No Alternate or Multiple Proposals
Neither multiple proposals, nor proposal variations or options, nor alternate or alternative proposals will be considered in the evaluation.
SECTION 00210
SECTION 00210
BASIS OF AWARD AND EVALUATION FACTORS
1. BASIS OF AWARD
Selection of contractor(s) will be accomplished using Source Selection Procedures on the basis of Best Value to the Government, considering price and other factors combined. Interested firms are expected to review the RFP and participate in a pre-proposal conference and site visit, provide proposed prices for the initial project, and provide proposal information requested to evaluate their technical and past performance factors.
The Two Phase Design-Build procedures of FAR 36.3 will be used for this procurement. Phase One of the solicitation is in accordance with FAR Part 36.3. Phase One evaluation will result in a determination of the most highly qualified Offerors. These Offerors will be requested to submit a Phase Two proposal. The maximum number of Offerors that will be selected to submit a Phase Two proposal is five (5), unless the contracting officer determines that a number greater than five (5) is in the Government’s interest and is consistent with the purposes and objectives of two-phase design-build contracting. Phase Two of the solicitation shall require submission of technical and price proposals by the Offerors selected in Phase One, which will be evaluated separately in accordance with Part 15. The Government intends to evaluate proposals and award contract(s) without discussions.
The Government anticipates three or more multiple award construction contracts. Offerors are advised that those Offerors who are selected to proceed to Phase Two are not guaranteed receipt of a contract award. Award of the basic multiple award construction contracts will be made to those responsible Offerors whose proposals conforming to the solicitation are determined to be the most advantageous to the Government considering past performance, technical, and price factors. The Government reserves the right to award three or more contracts under this solicitation or to award only the initial project (Proposed Task Order 0001) identified in the RFP as a single-action contract. The Government reserves the right not to award the Proposed Task Order 0001. The Government reserves the right to substitute or add other design-build projects that meet the scope of the MACC.
The Government reserves the right to reject any or all basic contract offers at any time prior to award; to negotiate with any one or all Offerors; to award the contract to other than the Offeror submitting the lowest total price; and to award contracts to three or more Offerors submitting proposals determined by the Source Selection Authority to be the most advantageous to the Government.
OFFERORS ARE ADVISED THAT IT IS DEFINITELY POSSIBLE THAT AN AWARD MAY BE MADE
WITHOUT DISCUSSIONS OR ANY CONTACT CONCERNING THE PROPOSALS RECEIVED.
Therefore, proposals should be submitted initially on the most favorable price and technical terms. Offerors should not assume that they would be contacted or afforded the opportunity to qualify, discuss, or revise their proposal.
Firms participating in the pre-proposal conference and site visit will not be compensated for their participation.
Successful Offerors will receive the following contract awards:
Best Value receives award with a minimum guarantee and the initial project, if the Government chooses to award it.
Second, third, and any additional selected contractor will each receive award with a minimum guarantee, and selection will be based on the same criteria as the first selection.
2. DEFINITIONS
DEFICIENCY: A material failure of a proposal to meet a solicitation requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
WEAKNESS: A flaw in the proposal that increases the risk of unsuccessful contract performance.
SIGNIFICANT WEAKNESS: A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance.
STRENGTH: An aspect of a proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
ACCEPTABLE FEATURES: A proposed method or technique in the proposal that addresses solicitation requirements such that no further explanation or documentation is necessary.
PAST PERFORMANCE: Relates to how well an Offeror has performed; e.g., the quality of work accomplished, schedule compliance, customer satisfaction.
RELEVANT EXPERIENCE: Pertains to work performed by an Offeror, within the prescribed timeframe, which is the same or similar to the work that may be ordered under this contract in terms of size, scope, and complexity.
Experience is distinct from past performance (how well an Offeror has performed).
SUSTAINABLE FEATURES: Features in the design, construction, and operation of facilities with the goal of conserving resources and minimizing adverse effects on the environment while enhancing occupant productivity, minimizing energy use, improving quality and durability of materials, increasing recycling and use of recycled products, waste reduction, etc. Relevant sustainable features are those that are the same or similar to those recognized by the USGBC LEED rating system.
PROJECT: A design-build or design-bid-build construction activity or task, with a single starting point and a single ending point.
COMBINED PROJECT(S): Projects with multiple starting and ending points, performed under separate task orders, delivery orders, or multiple contracts combined in a single description. No credit will be given for work performed under MACC/IDIQ contracts in the aggregate, for multiple projects completed under more than one task/delivery order.
RENOVATION, REPAIR, ALTERATION PROJECT TYPES: Refers to projects where the work primarily involves the modification of existing facilities.
NEW CONSTRUCTION: Refers to projects where the work primarily involves creating entirely new facilities (or new expansions to existing facilities where a new structure and foundation is provided as part of the expansion).
OFFEROR: Refers to the Contractor submitting the proposal as Offeror, including Joint Ventures, whose name appears in Block 14 of Standard Form (SF) 1442 (Solicitation, Offer and Award). In the event of a conflict or inconsistency between the Offeror’s name cited on the SF 1442 and any other part of the proposal, the SF 1442 is the conclusive document in determining the Offeror who is submitting the proposal.
OFFEROR'S TEAM: Applies to the Offeror, the Offeror's outside Lead Design Firm, and/or in-house Lead Designer(s) only; does not include subcontractors, consultants or members of a partnership/teaming agreement.
100% COMPLETE:
For construction projects: The facility is completely constructed and ready for the intended use.
For design projects: 100% plans and specifications signed off by an Architect-Engineer and ready for construction with final cost estimate. Does not include any Post Construction Award Support (PCAS).
LEAD DESIGN FIRM: Applies to the Offeror’s primary design consultant firm(s) and any in-house lead designer(s).
JOINT VENTURE (JV): A legal business entity formed between two or more companies (parties) to undertake the performance activities of a contract together.
FIVE-YEAR PERIOD: The prescribed timeframe for this solicitation that refers to the period of time for which projects may be submitted for relevant experience or relevant past performance consideration. The five-year period is calculated by counting back five years from the initial RFP issuance date.
DESIGN-BUILD: Refers to combining design and construction in a single contract with one contractor. Design-build projects require design of the project by a licensed professional (i.e. engineer, architect). Projects that only require shop drawing level effort are not design-build projects. Construction Management at Risk (CMAR) is not considered design-build.
DESIGN-BID-BUILD: Refers to the traditional delivery method where design and construction are sequential and contracted for separately with two contracts and two contractors.
SELF-PERFORM: Refers to performing relevant major trade work in-house without subcontractors. This does not include administrative or management functions. Relevant major trade work is that which is the same or similar to the work that may be ordered under this contract.
PAGE: Refers to one printed side of a piece of paper. (For example, 5 pieces of paper printed on both sides would result in 10 pages of narrative.)
3. RELATIVE IMPORTANCE OF THE EVALUATION FACTORS
The relative importance of the evaluation factors is as follows:
a. Phase One: Phase One shall consist of Factors 1, 2, and 3. Factor 1 (Technical Approach) will be rated as either Acceptable or Unacceptable. If an Offeror is rated Unacceptable for Factor 1, they will not be invited to participate in Phase Two. Factors 2 and 3 are of equal importance to each other.
b. Phase Two: In making the best value award decision in Phase Two, Factors 2-6 and price will be considered. The technical factors (2, 4, 5, and 6) are of equal importance to each other and when combined are of equal importance to the performance confidence assessment (Factor 3, Past Performance). The combined non-price factors are approximately equal to price. The importance of price will increase if the Offerors’ non-price proposals are considered essentially equal in terms of overall quality, or if price is so high, or low, as to significantly diminish the value of a non-price proposal’s superiority to the Government.
According to FAR 15.304, the evaluation factors that apply to this acquisition are a part of this RFP and are evaluated individually. The applicable evaluation factors and submission requirements are identified below.
4. EVALUATION FACTORS
The evaluation factors for this procurement are:
PHASE ONE Basis of Evaluation/Submission Requirements/Criteria Description
FACTOR 1: TECHNICAL APPROACH
a. Proposal Submission Requirements:
The composition and management of the firms proposed as the design-build (DB) team for this contract will be evaluated in this factor.
The Offeror shall submit the following information under Tab “1”:
(1) Using Exhibit “A” (Offeror Team Composition and Management), provide a narrative describing the proposed primary construction firm(s) and primary design firm(s) for this contract and the rationale for proposing this arrangement. Provide the role, responsibilities, and contractual relationships between the various firms (see FAR Subpart 9.6). The narrative shall also include a simple organizational chart that clearly identifies the lines of authority between the entities. If the experience of an entity is being claimed in Factor 2, that entity must be named in the above narrative and organizational chart.
The technical approach narrative (Exhibit A) shall be limited to one (1) double-sided page (or two (2) single-sided pages) excluding the organizational chart. The information requested in item #2 below is not included in this page limitation.
(2) In addition to the narrative, the Offeror shall submit a signed copy of a joint venture agreement, partnership agreement, teaming agreement, approved mentor protégé agreement (MPA), or letter of commitment for each member of the Offeror’s team identified above (e.g., joint venture member, partner, team member, subcontractor, parent company, subsidiary, or other affiliated company, etc.).
b. Basis of Evaluation:
The assessment of the Offeror’s technical approach will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. This factor will be rated on an Acceptable or Unacceptable basis. Offerors that are rated Unacceptable will be found ineligible to proceed to Phase Two.
FACTOR 2: EXPERIENCE (See definition)
Submit Exhibit “B” (Construction/Design Experience Project Data Sheet) under Tab “2.”
(1) Construction Experience:
Submit a maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to projects that may be ordered under this contract. For purposes of this evaluation, relevant projects are further defined as new construction and/or renovation of commercial and institutional buildings, primarily by design-build or secondarily by design-bid-build, with a project construction cost of $8,000,000 or greater. Types of projects may include, but are not limited to: administration buildings, school buildings, hospitals, auditoriums, fire stations, gymnasiums, office buildings, hangars, laboratories, and parking structures.
At least one construction project shall demonstrate the Offeror’s experience with new construction
(see definition).
At least one construction project shall demonstrate the Offeror’s experience with renovation (see definition).
At least two construction projects shall demonstrate the Offeror’s experience with design-build (see definition).
Projects submitted for the Offeror shall be 100% complete (see definition) within the past five (5) years of the date of issuance of this RFP.
A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.
The attached Construction/Design Experience Project Data Sheet (Exhibit “B”) is MANDATORY and SHALL be used to submit project information. If the same project is being used to demonstrate construction and design experience, submit separate Project Data Sheets for construction and design.
Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e.: unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for each Joint Venture member. Offerors who fail to submit experience for all Joint Venture members may be rated lower. Offerors are still limited to a total of five (5) projects combined.
If an Offeror is utilizing experience information of affiliates/subsidiaries/predecessor/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.
(2) Design Experience:
Submit a maximum of five (5) relevant design projects for the design team that best demonstrate design experience on relevant projects that are similar in size, scope, and complexity to projects that may be ordered under this contract. For purposes of this evaluation, relevant projects are further defined as new construction and/or renovation of commercial and institutional buildings, primarily by design-build or secondarily by design-bid-build, with a project construction cost of $8,000,000 or greater. Types of projects may include, but are not limited to: administration buildings, school buildings, hospitals, auditoriums, fire stations, gymnasiums, office buildings, hangars, laboratories, and parking structures.
At least one design project shall demonstrate the design team’s experience with new construction (see definition).
At least one design project shall demonstrate the design team’s experience with renovation (see definition).
At least two design projects shall demonstrate the design team’s experience with design-build (see definition).
Projects submitted for the design team shall be 100% complete (see definition) within the past five (5) years of the date of issuance of this RFP. For design-build projects, the design portion of the contract shall have been completed within the past five (5) years of the date of issuance of this RFP.
A project is defined as a complete design effort performed under a single task order or contract/subcontract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.
The attached Construction/Design Experience Project Data Sheet (Exhibit “B”) is MANDATORY and SHALL be used to submit project information. If the same project is being used to demonstrate construction and design experience, submit separate Project Data Sheets for construction and design.
Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e.: unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.
If an Offeror is utilizing experience information of affiliates/subsidiaries/predecessor/ parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.
The Offeror may utilize experience of a design subcontractor to demonstrate design experience under this evaluation factor. The Offeror must provide a supporting joint venture agreement, partnership agreement, teaming agreement, or letter of commitment and an explanation of the meaningful involvement for the design subcontractor.
The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction and design projects as defined in the solicitation submittal requirements.
The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. Projects submitted in excess of the five (5) for Construction Experience and five (5) for Design Experience will not be considered.
Relevant projects where the Offeror and the proposed design firm(s) have previously worked together may be considered more favorably than those that have not worked together.
Relevant projects that demonstrate design-build experience may be considered more favorably than those that do not have design-build experience.
Relevant projects that demonstrate experience with sustainable features may be considered more favorably than those that do not demonstrate experience with sustainable features.
Offerors who submit relevant projects that demonstrate experience self-performing relevant features of work may receive a higher rating than those who do not demonstrate self-performance.
FACTOR 3: PAST PERFORMANCE
Submit Past Performance Questionnaires (Exhibit “C”) and CCASS/ACASS evaluations under Tab “2” immediately following each of the project data sheets to which they pertain. Submit any other past performance information under Tab “3.”
If a completed Construction Contractor Appraisal Support System (CCASS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for construction experience. If a completed AE Contractor Appraisal Support System (ACASS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for design experience. If there is not a completed CCASS or ACASS evaluation, submit a Past Performance Questionnaire (Exhibit “C”) for each project included in Factor 2 for both Construction Experience and Design Experience. The Offeror should provide completed Past Performance Questionnaires (PPQ) in the proposal. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact – Nancy LeSage at nancy.lesage@navy.mil.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 2 – Experience. Offerors may also address any adverse past performance issues.
Explanations shall not exceed one (1) double-sided page (or two (2) single-sided pages) in total.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
Performance award or additional information submitted will not be considered.
b. Basis of Evaluation:
This evaluation focuses on how well the Offeror performed on the relevant projects submitted under Factor 2
– Experience and past performance on other projects currently documented in known sources. More emphasis will be placed on more relevant projects. In addition to the above, the Government reserves the right to obtain information for use in the evaluation of past performance from any and all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s past performance will be used as a means of evaluating the Offeror’s probability to successfully meet the requirements of the RFP.
Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance and will receive an Unknown Confidence rating.
PHASE TWO Basis of Evaluation/Submission Requirements/Criteria Description
FACTOR 4: SAFETY
Submit Exhibit “D” (Safety Data Sheet / Safety Narrative) under Tab “4.”
The Offeror shall submit the following information: (For a joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture; however, only one safety narrative is required. EMR and DART Rates shall not be submitted for subcontractors.)
(1) Experience Modification Rate (EMR):
For the three (3) previous complete calendar years (2010, 2011, 2012), submit your EMR (which compares your company’s annual losses in insurance claims against its policy premiums over a three (3) year period).
If you have no EMR, affirmatively state so and explain why. Any extenuating circumstances that affected the EMR and upward or downward trends should be addressed as part of this element. Lower EMRs will be given greater weight in the evaluation.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate:
For the three (3) previous complete calendar years (2010, 2011, 2012), submit your OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration. If you cannot submit an OSHA DART Rate, affirmatively state so, and explain why. Any extenuating circumstances that affected the OSHA DART Rate data and upward or downward trends should be addressed as part of this element. Lower OSHA DART Rates will be given greater weight in the evaluation.
(3) Technical Approach for Safety:
Describe the plan that the Offeror will implement to evaluate safety performance of potential subcontractors, as a part of the selection process for all levels of subcontractors. Also, describe any innovative methods that the Offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety narrative shall be limited to two pages.
b. Basis of Evaluation:
The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The Government will evaluate the Offeror’s overall safety record, the Offeror’s plan to select and monitor subcontractors, any and innovative safety methods that the Offeror plans to implement for this procurement. The Government’s sources of information for evaluating safety may include, but are not limited to, OSHA, NAVFAC’s Enterprise Safety Applications Management System (ESAMS), and other related databases. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete safety information regarding these submittal requirements rests with the Offeror. The evaluation will collectively consider the following:
- Experience Modification Rate (EMR)
- OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate
- Offeror Technical Approach to Safety
- Other sources of information available to the Government
(1) Experience Modification Rate (EMR):
The Government will evaluate the EMR to determine if the Offeror has demonstrated a history of safe work practices taking into account any upward or downward trends and extenuating circumstances that impact the rating. Lower EMRs will be given greater weight in the evaluation.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate:
The Government will evaluate the OSHA DART Rate to determine if the Offeror has demonstrated a history of safe work practices taking into account any upward or downward trends and extenuating circumstances that impact the rates. Lower OSHA DART Rates will be given greater weight in the evaluation.
(3) Technical Approach to Safety:
The Government will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The Government will also evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement. Those Offerors whose plan demonstrates a commitment to hire subcontractors with a culture of safety and who propose innovative methods to enhance a safe working environment may be given greater weight in the evaluation.
FACTOR 5: TECHNICAL SOLUTION
Submit the Technical Solution narrative and drawings under Tab “5.”
Provide a narrative, not exceed two (2) double-sided pages (or four (4) single-sided pages), describing the technical solution to the project that meets the requirements of the RFP. Address the following items in the narrative:
- Site layout including a description of the building orientation, roadways, pedestrian & vehicle traffic flow, parking (include ingress and egress), emergency vehicle access, antiterrorism (including ATFP standoff distances), and accessibility features.
- Interior circulation and adjacencies
Provide one (1) 11”x17” concept drawing of the Site Plan and one (1) 11”x17” concept drawing of the Floor Plan for the proposed project to demonstrate an understanding of the project objectives, design criteria, and understanding of the RFP requirements.
- Include the following major site components in the Site Plan: building orientation, roadways, pedestrian & vehicle traffic flow, parking (include ingress and egress), emergency vehicle access, antiterrorism (including ATFP standoff distances), and accessibility features.
- Include the following major interior components in the Floor Plan: interior circulation and adjacencies.
The Government will evaluate the narrative and conceptual drawings considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering requirements of the project.
The Government will evaluate the Offeror's technical solution to determine adherence to the technical requirements of the RFP.
FACTOR 6: ENERGY AND SUSTAINABLE DESIGN
Submit Energy and Sustainable Design information under Tab “6.”
Provide the following information, which describes how the project will meet or exceed the following sustainable design contract requirements.
(1) EPAct 2005 Energy Efficiency Narrative:
Using the guidance outlined in Part 3 of the RFP, provide a detailed narrative to describe whether the proposed solution will meet or exceed the goal of a 30% energy reduction using the ASHRAE Std 90.1-2007, Appendix G,…