About this file

This document is an amendment to a solicitation for supplies and components in support of the Naval Surface Warfare Center Panama City Division and the US Navy. The amendment provides answers to forty questions from potential offerors to clarify requirements. Key supplies may include COTS and OEM items to support various Navy programs related to mine warfare, unmanned systems, acoustics, electro-optics, and more. The solicitation seeks multiple suppliers under FSC codes 20, 23, 25, 28, 29, 30, 35, 39, 40, 42, 43, 47, 48, 49, 54, 58, 59, 60, 61, 63, 66, 68, 69, 70, 81, 84, 95, and 99. The closing date remains 13 May 2019 with an anticipated solicitation issuance of 3 June 2019. The total contract value is estimated at $48 million over five years. No extensions will be granted to the closing date.

Questions and Answers

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is answ er questions recieved. Please see Summary of Changes for the questions and answ ers.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Jul-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6133119R0015

X 9B. DATED (SEE ITEM 11)

13-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Jul-2019

CODE

NSWC PCD (T. BUSHMAN)

TOMMY.BUSHMAN1@NAVY.MIL

110 VERNON AVE

PANAMA CITY FL 32407

N61331 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6133119R0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SF 30

SUMMARY OF CHANGES

The following have been added by full text

Amendment 0003:

Questions 1 thru 27 can be found in amendment 0002

Question 28: For attachment J.1 can you provide any suggested sources of supply for the sub-components?

Answer 28: There are no suggested sources of supply for the sub-components.

Question 29: What is the NSN for the overall AN/AQX-24A system?

Answer 29: The NSN for the top level Q24 Cradle is 2040-01-585-8550, Part Number 35658-1

Question 30: For attachent J.1 can the due date be extended in order to give us more time to source these components?

Answer 30: No extension will be provided for this requirement.

Question 31: In regards to the answer for question 7 on amendment 0002- Are we to assume the start date?

Answer 31: This requirement is intended to be awarded between August 31st and September 30th 2019.

Question 32: In regards to the answer for question 9 in amendment 0002-Not asking about the format, asking if a cost narrative is required and, if so, provide what type of specific information is to be submitted.

Answer 32: A cost narrative is not required but an offeror ‘may’ submit one to clarify pricing information.

Question 33: In regards to the answer for question 10 in amendment 0002-The response here indicates to provide a percentage goal for the small business plan and then answers to the following three questions for the SBP ask for dollarized amounts. Please be specific as to what is exactly required to be provided in the SB Plan for both labor and ODCs at the RFP contract level (not demand order level). The SB Plan document has many requirements and therefore we need specific answers.

Answer 33: In order to calculate dollar figures with the percentages, the offeror is to assume they will win 100%of the contract value, or $48 million.

Question 34: In regards to the answer for question 11 on amendment 0002- Question was asked so that the Small Bus Plan can be completed properly. Need to understand what value to use per offeror.

Answer 34: In light of the clarification, and for purposes of completing the Small Business Plan, offerors are to assume they shall win 100% of contract value, or $48 Million.

Question 35: In regards to the answer for question 12 on amendment 0002- Need a specific value.

Answer 35: $48 Million

Question 36: In regards to the answer for question 13 on amendment 0002- Need a specific value.

Answer 36: $48 Million

Question 37: In regards to the answer for question 14 on amendment 0002- Not having any awareness of the future Demand Orders requirements, it is nearly impossible to provide subcontractors information with this submittal..

Answer 37: This price proposal for Factor 4 is in regards to Attachments J.1-J.3. Its saying that no technical information shall be put with the price proposal and only U.S. dollars shall be utilized in the proposal which applies to prime and subcontractors. This requirement is for all future orders even if the subcontractors are not currently known. All proposals must be in U.S. dollars.

N6133119R0015

Question 38: Some of the raw aluminum to fabricate the cradle assemblies are not readily available due to the special dimensions and may take up to 65 weeks to procure through a special mill run at the foundry. Can Offerors propose an alternate delivery schedule?

Answer 38: Yes, offerors may propose an alternate delivery schedule for Attachment J.1. Please see amendment 0002 where the delivery schedule has been previously extended.

Question 39: The response to Question 10 in amendment 0002 eludes to the fact that only the demand orders need to be priced and not the RFP Section B. So, what is the TAV value we use and do we then still need to fill out RFP Section B?

Answer 39: Section B is for informational purposes only in regards to this RFP and does not require any alteration.

The TAV for Attachment J.5 in order to calculate dollar figures with percentages, the offeror is to assume they will win 100% of the contract value, or $49 Million. See CLIN 9001 for TAV Ceiling.

Question 40: In order to submit a compliant proposal, request due date extension until additional questions are answered.

Answer 40: No extensions will be accepted for this requirement closing date.