This document contains a Contract Data Requirements List (CDRL) and details of a federal contract opportunity for supplies and components in support of the Naval Surface Warfare Center Panama City Division and the US Navy. The CDRL outlines four data items that will be required under the contract, including a Quality Assurance Program Plan, Contractor's Safety Plan, Accident/Incident Reports, and specifies delivery methods and approval processes. The federal contract opportunity is a solicitation seeking multiple suppliers to provide hardware, materials, and supplies for various Navy and Marine Corps programs. Supplies may include COTS and OEM items across a wide range of federal supply classes. The solicitation number is N61331-19-R-0015 and offers are due by 13 May 2019, with an anticipated award date of 3 June 2019. The contracting agency is the Department of the Navy Naval Sea Systems Command.

Exhibit A

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/Pr No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

Multi-Award Supply Contract (MASC) 190397

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A001 Quality Assurance Program Plan (QAPP)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-QCIC-81794 SOW PARA 3.3 NSWC PCD 18 ESTIMATED

TOTAL PRICE

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED 2TIMES 30 DAC b. COPIES

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft Final

A 10 DARC Reg Repro

16. REMARKS NSWC PCD Code E 1 1 1

Blk 8: Approval shall be for format and technical content. NSWC PCD will review the initial submittal and comment within 15 days after receipt. All NSWC PCD comments shall be incorporated into the subsequent submittal.

Blk 9: Data shall be marked in accordance with Section D of the basic contract.

Blk 13: “DARC” means “Days After Receipt of Government Comments”. Submit updates as required when major program changes dictates.

Blk 14: Reproducible copy shall be submitted as Microsoft Word 2010 files via e-mail to:

John.R.Link1@navy.mil Tommy.Bushman1@navy.mil

NSWC PCD Code 022 1 1 1

15. TOTAL 2 2 2

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

John R. Link, NSWC PCD Code E 07 March 2019 Tommy Chatman 08 March 2019

DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 4 Pages 1161/183 mailto:John.R.Link1@navy.mil mailto:Tommy.Bushman1@navy.mil

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/Pr

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

Multi-Award Supply Contract (MASC) 190397

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A002 Contractor’s Safety Plan

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-SAFT-82080 SOW PARA 3.4 NSWC PCD 18 ESTIMATED

TOTAL PRICE

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED 2TIMES 30 DAC b. COPIES

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft Final

A 10 DARC Reg Repro

16. REMARKS NSWC PCD Code E 1 1 1

Blk 8: Approval shall be for format and technical content. NSWC PCD will review the initial submittal and comment within 15 days after receipt. All NSWC PCD comments shall be incorporated into the subsequent submittal.

Blk 9: Data shall be marked in accordance with Section D of the basic contract.

Blk 13: “DARC” means “Days After Receipt of Government Comments”. Submit updates as required when major program changes dictates.

Blk 14: Reproducible copy shall be submitted as Microsoft Word 2010 files via e-mail to:

John R. Link, NSWC PCD Code E 07 March 2019 Tommy Chatman 08 March 2019

DD Form 1423-1, JUN 90 Previous editions are obsolete Page 2 of 4 Pages 1161/183

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/Pr

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

Multi-Award Supply Contract (MASC) 190397

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A003 Accident / Incident Report Accident Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-SAFT-81563 SOW PARA 3.5 NSWC PCD 18 ESTIMATED

TOTAL PRICE

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED ASREQ SEE BLK 16 b. COPIES

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft Final

A 10 DARC Reg Repro

16. REMARKS NSWC PCD Code E 1 1 1

Blk 8: Approval shall be for format and technical content. NSWC PCD will review the initial submittal and comment within 5 days after receipt. All NSWC PCD comments shall be incorporated into the subsequent submittal.

Blk 9: Data shall be marked in accordance with Section D of the basic contract.

Blk 12: Initial submittals are due no later than 2 working days after accident/incident.

Blk 13: “DARC” means “Days After Receipt of Government Comments”.

Blk 14: Reproducible copy shall be submitted as Microsoft Word 2010 files via e-mail to:

John R. Link, NSWC PCD Code E 07 March 2019 Tommy Chatman 08 March 2019

DD Form 1423-1, JUN 90 Previous editions are obsolete Page 3 of 4 Pages 1161/183

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/Pr

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

Multi-Award Supply Contract (MASC) 190397

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A004 Accident / Incident Report Damage Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-SAFT-81563 SOW PARA 3.6 NSWC PCD 18 ESTIMATED

TOTAL PRICE

7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT REQUIRED ASREQ SEE BLK 16 b. COPIES

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft Final

A 10 DARC Reg Repro

16. REMARKS NSWC PCD Code E 1 1 1

Blk 8: Approval shall be for format and technical content. NSWC PCD will review the initial submittal and comment within 5 days after receipt. All NSWC PCD comments shall be incorporated into the subsequent submittal.

Blk 9: Data shall be marked in accordance with Section D of the basic contract.

Blk 12: Initial submittals are due no later than 2 working days after accident/incident involving equipment damage.

Blk 13: “DARC” means “Days After Receipt of Government Comments”.

Blk 14: Reproducible copy shall be submitted as Microsoft Word 2010 files via e-mail to:

John R. Link, NSWC PCD Code E 07 March 2019 Tommy Chatman 08 March 2019

DD Form 1423-1, JUN 90 Previous editions are obsolete Page 4 of 4 Pages 1161/183

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

FOR GOVERNMENT PERSONNEL FOR THE CONTRACTOR

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (x) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as “Provisioning”, “Configuration Management”, etc.

Item D. Enter name of system/item being acquired that data will support

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contact that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addresses and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through

15. Examples are: Tailoring of documents cited in Item 4;

Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor’s performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices shall be developed only from those costs which will be incurred, as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data.

The Government’s right to use the data shall be governed by the pertinent provisions of the contract.

DD Form 1423-1 Reverse, JUN