C_09.0_Questions_and_Answers_Site_Visit.pdf
PDF 392 KB Posted
- Attached to
- Waterjet Waste Removal and Disposal Federal contract opportunity
- Solicitation number
- N4523A19R1301
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C_09.0_Solicitation_WaterJet_Amendment_0005.pdf | ||
| Solicitation_Amendment_0004.pdf | ||
| Questions_and_Answers_3.pdf | ||
| C_03.0_Site_Visit_Attendance_Sheet.pdf | ||
| C_09.0_Solicitation_WaterJet_Amendment_0003.pdf | ||
| C_09.0_Solicitation_WaterJet_Amendment_0002.pdf | ||
| WaterJet_Waste_Removal_Question_and_Answer.pdf | ||
| C_04.0_Solicitation_WaterJet.pdf | ||
| A_17.0_QASP.pdf | ||
| C_09.0_Solicitation_WaterJet_Amendment_0001.pdf | ||
| A_13.0_Solicitation_Waterjet.pdf | ||
| A_04.01_PWS.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Waterjet Waste Removal Question and Answer
Question 1: What is the length of hose required to pump each machine?
Answer 1: Shop 11A will require a 50-foot line, Shop 31A will require 160-foot line, and Shop 51R will require a 50-foot line.
Question 2: Will water be provided on-site?
Answer 2: Yes, the Government will provide on-site water.
Question 3: Will site preparations be completed prior to arrival.
Answer 3: All site preparations will be completed before arrival.