RFC3_Response.doc

DOC document 35 KB Posted

Attached to
Maintenance, Repair and Preservation of Edgecumbe Barge
Solicitation number
N4523A18R1065
Issued by

About this file

Request for Clarification #3 Response

View the file

Other files

File Type Posted
RFC6_Response.doc DOC document
RFC4_Response.doc DOC document
RFC5_Response.doc DOC document
RFC1_Pictures.zipx ZIPX file
RFC1_Response.doc DOC document
RFC2_Pictures.zipx ZIPX file
RFC2_Response.doc DOC document
RFC3_Picture.zipx ZIPX file
Exhibit_A_-_CDRLs_and_DIDs_Combined_Edgecumbe_Barge.pdf PDF
Attachment_J-1_Statement_of_Work_Edgecumbe_Barge_dated_1MAY2018.docx DOCX document
N4523A18R1065_SolicitationDrawings.zip ZIP file
Attachment_J-3_Request_for_Clarification_Form_Edgecumbe_Barge.doc DOC document
Attachment_J-4_Contract_Performance_Data_Sheet_Edgecumbe_Barge.docx DOCX document
Attachment_J-5_Corporate_Experience_Data_Sheet_Edgecumbe_Barge.docx DOCX document
N4523A18R1065_Edgecumbe_Barge.pdf PDF
Edgecumbe_Barge_Draft_SOW.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR CLARIFICATION

N4523A18R1065 Attachment J-3

DATE OF REQUEST:
QUESTION NO: 003

REQUIREMENT: Edgecumbe Barge

REQUISITION NO.: N4523A18R1065

ITEM NO: 3.2.2

TITLE: Rubber Fenders

PSNS&IMF CONTRACTS POC & PHONE:

See POCs listed on RFP.

PARA. NO: 3.2.2
PAGE NO: 27
CONTRACTOR:
PLANNER’S NAME:
ATTACH. NO:
CONTRACTOR POC & PHONE:

CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)

Specification 3.2.2 provides Contractor direction to hand tool clean hull surfaces from the edge of the existing rubber fenders and outward 2 inches. Specification does not provide drawing reference.

Solicitation package does not provide drawings in support of rubber fender hand prep.

Contactor requests fender layout drawings.

DO NOT WRITE BELOW THIS LINE

SPEC CHG: N
DWG/REF CHG. N
RQMTS CHG: N
MAT'L CHG: N
TECHNICAL REVIEW: Baxter
SERIAL NO: 003

See the attached picture for reference.

ALL RFCs MUST BE RECEIVED NO LATER THAN 2:00 P.M. (PST), 25 July 2018.

File details come from the government source that posted it.