N4523A18R1058_RFC_007.pdf

PDF 41 KB Posted

Attached to
Maintenance, Preservation, and Repair of YT-800
Solicitation number
N4523A18R1058
Issued by

About this file

N4523A18R1058 YT-800 RFC 007

View the file

Other files

File Type Posted
N4523A18R1058_Attachment_J-1__SOW_Errata_2_YT_800_Posted_28JUN2018.pdf PDF
N4523A18R1058_YT-800__Amendment_0003.pdf PDF
N4523A18R1058_YT-800__Amendment_0002.pdf PDF
N4523A18R1058_RFC_009.pdf PDF
N4523A18R1058_RFC_008.pdf PDF
N4523A18R1058__RFC_005.pdf PDF
N4523A18R1058_RFC_002.pdf PDF
N4523A18R1058_YT-800_SOW_Errata_One_12JUNE2018.pdf PDF
N4523A18R1058__RFC_004.pdf PDF
N4523A18R1058_YT-800_SOW_reference_drawing_Errata_One.zip ZIP file
N4523A18R1058_RFC_006.pdf PDF
N4523A18R1058_YT-800__Amendment_0001.pdf PDF
N4523A18R1058__RFC_003.pdf PDF
N4523A18R1058_RFC_001.pdf PDF
N4523A18R1058_Updated_5-way_break_out_13JUNE2018.xlsx XLSX spreadsheet
N4523A18R1058_YT-800_Solicitation.pdf PDF
N4523A18R1058_Attachment_J-1_SOW_YT_800.pdf PDF
N4523A18R1058_Attachment_J-7_GFP.pdf PDF
N4523A18R1058_Attachment_J-5_Corporate_Experience_Data_Sheet.docx DOCX document
N4523A18R1058_Attachment_J-4_Contract_Performance_Data_Sheet.docx DOCX document
N4523A18R1058_Attachment_J-2_YT-800_5-way_break_out.xls.xlsx XLSX spreadsheet
N4523A18R1058_Attachment_J-8_BAVR_Instructions.pdf PDF
N4523A18R1058_Attachment_J-3_Request_for_Clarification_(RFC)_Form.docx DOCX document
N4523A18R1058_YT_800_SOW_Draft.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR SPECIFICATION CLARIFICATION

DATE OF REQUEST: 6/11/18 QUESTION NO: 007

REQUIREMENT: REQUISITION NO.: N4523A18R1058

ITEM NO: 3.2.9, 3.5.4, and 3.11.6 TITLE: Reservation Tasking

ISSUING OFFICE POC (CODE 440.22):

Brittany Chartier: (360) 476-5708 Brittany.chartier@navy.mil

PARA. NO: 3.7.1 PAGE NO: 42 CONTRACTOR:

PLANNER’S NAME: ATTACH. NO: CONTRACTOR POC & PHONE:

CONTRACTOR QUESTION:

Specification Sections 3.2.9, 3.5.4 and 3.11.6 are associated with Reservation Tasking and provide specific labor hours and materials to be accounted for in the contract value.

Specification paragraph 1.26.4 notes “The reservation manhours and material dollar listed in each work item are a part of this contract under the original sonication and award. Therefore, they are subject to the provisions, terms, conditions and classes of this contract.” Paragraph 1.26.5 in part reads “. . . and it is evident that no additional work will be tasked, is subject to a decrease change order. All remaining hour and material balances may be decreased at completion of the applicable work item or after delivery.”

Current J-2 form appears to have the three noted Reservation Tasking items hidden, and do not calculate the value of the labor hours nor materials on the form.

Contractor requests clarification as to how the value of said Reservation Tasking will be accounted for on the J-2 for anticipated or potential deductive change order, if it does not calculate on Contractor completed J-2 form.

DO NOT WRITE BELOW THIS LINE

SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N

TECHNICAL REVIEW: SERIAL NO:

Please see updated Attachment J-2 5-Way breakout 13JUNE2018.

ALL REQUESTS FOR CLARIFICATION MUST BE RECEIVED BY THE ISSUING OFFICE POC NO

LATER THAN THE DATE & TIME IDENTIFIED IN THE REQUEST FOR PROPOSAL.