N4523A18R0826-0004.pdf
PDF 71 KB Posted
- Attached to
- Depot Level Preservation IDIQ On-ramping
- Solicitation number
- N4523A18R0826
About this file
SF30 - N4523A18R0826-0004
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N4523A18R0826-0003.pdf | ||
| Pre-proposal_Telecon_Attendees_List-13Mar2018.pdf | ||
| N4523A18R0826_Bidders_Question-Responses-14Mar2018.pdf | ||
| N4523A18R0826-0002.pdf | ||
| N4523A18R0826-0001.pdf | ||
| N4523A18R0826__AMEND_1_released.pdf | ||
| J-3-Notional_Price_Breakdown_Form.xls | XLS spreadsheet | |
| J-2-Notional_Statement_of_Work.pdf | ||
| J-1-DD_FORM_254.pdf | ||
| J-4-RFP_Question-Response_Matrix.xls | XLS spreadsheet | |
| N4523A18R0826.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
MAC Preservation IDIQ On-ramping
Amend Sec I adding clauses FAR 52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989) (NAVSEA VARIATION II) (SEP 2009) and FAR 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999).
Amend Sec C para. 2.1 by deleting reference NAVSEA S-0300-API-1-00-0 NAVSEA Standard Components List for Hull, Mechanical and Electrical Equipment.
Amend Sec C para. 2.1 references are re-numbered, the references listed in 2.1.8 and 2.1.9 are moved up and become 2.1.7 and 2.1.8 and
2.1.9 is no longer used and is deleted.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Mar-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4523A18R0826
X 9B. DATED (SEE ITEM 11)
23-Feb-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Mar-2018
CODE
PUGET SOUND NAVAL SHIPYARD CODE 400
1400 FARRAGUT
CONTRACTING CODE 440
BREMERTON WA 98314
N4523A 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4523A18R0826
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
1. SCOPE
1.1 Background. The Northwest Regional Maintenance Center (NWRMC), Puget Sound Naval Shipyard & Intermediate Maintenance Facility (PSNS & IMF), Industry Management Department, Code 400 intends to utilize this contract to procure preservation of critical and non-critical surfaces and installation of new coating systems which may include single and multiple coat systems, ultra-high solids, epoxy, solvent based, and anti-fouling. As well as associated structural repair requirements necessary to support the preservation process for aircraft carrier, submarine and other vessels during maintenance availabilities at Puget Sound Naval Shipyard and Intermediate Maintenance Facility, Bremerton, WA (Controlled Industrial Area) and at other locations in the region as identified in task orders.
Typical preservation services for aircraft carriers and submarines are as follows: Underwater Hull (including domes, sea chests, rudders, anode shields), Freeboard Surfaces (including ventilation intake/exhaust screens and coamings, flight deck overhang, sponsons, and platforms), Catwalks, Voids, Ventilation Plenums, Aircraft Elevators and Recess Areas, Exterior and Interior Surfaces (overheads, bulkheads and decks). Coating systems may include non-aviation area non-skid product installation (sponsons, platforms, catwalk areas).
Typical preservation services for submarines are as follows: Interior and Exterior Tanks (including Main Ballast, Mud, Potable Water, Sanitary, and Auxiliary), Sail (Interior and Exterior), Pressure and Non-Pressure Hull, Superstructure, Exterior Recesses, Free Flood areas, and Interior and Exterior Surfaces. Coating systems may include single and multiple coat systems, ultra-high solids, epoxy, solvent based, and anti-fouling.
Typical preservation services for other vessels and craft are as follows: Underwater Hull, Freeboard Surfaces, Interior and Exterior Spaces (overhead, bulkhead and deck) and Tanks.
2. APPLICABLE DOCUMENTS
2.1 Specifications and Standards. If, during the performance of this contract, the Contractor believes that the contract contains outdated or different versions of any specifications or standards, the Contractor may request that this contract be updated to include the current version of the applicable specification or standards. Updating shall not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government.
The Contractor shall submit update requests to the Contracting Officer with copies to the Contracting Officer Representative (COR). The Contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval by the Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract. The following specifications, standards and handbooks form a part of this document to the extent specified herein.
2.1.1 Naval Sea Systems (NAVSEA) Standard Items, Category I and II, Current Fiscal Year/Change Version
2.1.2 Systems and Specifications, SSPC Painting Manual, Volume 2, Current Version
2.1.3 NACE Book of Standards, Current Version
2.1.4 NorthWest Regional Maintenance Center (NWRMC) Local Standard Items:
2.1.5 DOD INST 5220.22M, Department of Defense Industrial Security Manual
2.1.6 MIL-HDBK-881, Work Breakdown Structures for Defense Material Items
2.1.7 NAVSEA S9AA0-AB-GOS-010/GSO, Current Version, General Overhaul Specifications for Overhaul of
Surface Ships
2.1.8 Other references will be identified in individual Task Orders issued.
3. REQUIREMENTS
3.1 General Requirements. The Contractor shall provide all management, labor, staging, containment, material, support services, and equipment necessary to perform preservation and associated structural repair services necessary to support the preservation process detailed in work specifications of task orders issued. The preservation and maintenance services shall be performed on shipboard interior and exterior surfaces in accordance with Navy and industrial specifications and standards, as well as all local, regional, state, and federal laws, rules, regulations, policies, and procedures regarding safety, security, health, and environmental protection. The production schedule requirements are of utmost importance to the Navy and shall be adhered to unless deviation is authorized by the Contracting Office.
3.1.1 Contractor Designated Principal. The Contractor shall assign one lead employee, authorized to obligate the Contractor, to coordinate all aspects of the contract with the designated Government representative and vice versa.
The following additional responsibilities will be required upon award of a delivery order under this contract:
a. Coordinate with the Contracting Officer’s Representative to keep the contracting officer apprised of schedule, technical, material, and financial issues pertaining to the contract.
b. Coordinate work integration and sequencing with Naval Supervisory Activity (NSA) project team and Code 400 Contracting Officer and/or Contracting Officer’s Representative.
c. Participate and coordinate in weekly overall schedule progress reviews with Government representative assigned. Attend project daily (workday) team meetings to ensure a coordinated effort in accomplishment of work.
d. The Contractor shall maintain QP-1 certification in compliance with the requirements of the Systems and Specifications, SSPC Painting Manual, Volume 2, Current Version.
3.1.2 Contractor Safety and Health Manager. The contractor shall assign a Safety and Health Manager for orders issued under this contract. The Safety & Health Manager shall have at least 5 years of experience in marine preservation efforts in a U.S. Navy shipyard environment with two (2) or more years of direct experience with standards and specifications for application of coating systems and shall be able to ensure the requirements of federal, state, local laws, codes, ordinances, and regulations are met. Experience, certifications and education should document the ability to implement and manage robust programs as required by OSHA 29 CFR 1910 and 1915 including competent persons, respirator programs, heavy metal programs, air monitoring and sampling plans including chain of custody to ensure the safety of personnel.
3.1.3 Communications. All communication with other Government organizations / entities shall be via the Contracting Officer or designated Government representative unless otherwise authorized.
3.2 Navy Maintenance Database (NMD). Contractor shall obtain access to NMD to provide electronic communication of work requirements associated to this contract. Access to NMD shall be coordinated through the Contracting Officer’s Representative upon contract award.
Included in the Contractor NMD communications work requirements are Conditions Found Reports (CFR’s) whereby the Contractor will identify needed repairs and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the original work item specifications. The CFR shall be submitted via the NMD system within three working days of identification of the requirement.
At a minimum, the CFR will include the following:
Identify contract number, ship and hull number Serialized by CFR number Identification of the applicable Work Item Specification number Date requirement was discovered Description of the work requirement Specific location of the work Recommendation for corrective action
Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change).
Provide supporting rational for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.
Identification of related changes, if any, to production milestones/key events and contract completion date.
If none, so state.
A Rough Order of Magnitude (ROM) cost estimate (+/- 10%) shall be included as part of the CFR submission in NMD. The Government Maintenance Team will review the CFR deficiency identified, the Contractor’s recommendation for corrective action, estimate for correctness, and further determine if the work is required and potentially affordable.
If the CFR is inadequate or incomplete, it will be rejected back to the Contractor in NMD. To mitigate this, in many cases, the Government and Contractor will meet, discuss the recommendation for corrective action, make ship checks etc. to determine the full scope of work and evaluate costs prior to submittal of the CFR. If the identified CFR is determined to be necessary, a Request for Contract Change (RCC) will be generated.
3.3 Authorized Government Representatives. The contractor shall perform work in accordance with this contract. Should the contractor be instructed by an individual other than the Contracting Officer to perform work that it considers a change to this contract, the contractor shall not perform such work and shall immediately notify the Contracting Officer and/or Contracting Officer’s Representative (COR) in accordance with the notification of changes clause, FAR 52.243-7.
3.4 Specific Requirements. The work specification package, issued for each task order, includes details of work requirements not listed in this contract section.
3.5 Pre-Commencement Conference. Within three (3) working days of receipt of the signed task order, the Government shall advise the contractor of the date for a pre-commencement conference. This conference shall be held at least five (5) working days before the contractor’s preservation team services are scheduled to begin. The primary purpose of this conference is interaction/integration between the contractor’s team and NSA Project Team.
The contractor shall be prepared to discuss the following (not necessarily in order of importance):
1. Space (lay-down area), onboard vessel and/or pier side, needed by the contractor for staging, etc.
2. Noise, dust and grit containment / minimization
3. Abrasive media and paint receipt inspection, storage, staging, handling
4. Employee Safety
5. Accessibility of spaces to ship and shipyard personnel while those spaces are undergoing preservation effort
6. Contractor’s work schedule by space
7. Quality Assurance (QA)
8. Contractor Industrial Hygiene Program; to include worker showers / change-rooms
SECURITY REQUIREMENTS
NAVAL BASE KITSAP (NBK) and/or PSNS & IMF CONTROLLED INDUSTRIAL AREA (CIA) ACCESS:
1.1. Contractor personnel shall comply with all current badging and security procedure requirements for gaining access to Department of Defense (DoD) Installations/Government Sites. Access to Navy Installations or Sites may only be gained by obtaining a badge (either permanent or temporary) from the Visitor Control Center (VCC) in building 981 (Pass & ID). It is the contractor’s responsibility to check for, and obtain changes and updated information from the VCC on a continual basis.
1.2. The following Identification Cards (ID) are authorized by Naval Base Kitsap and Naval Station Everett to be used by visitors 12 years old or greater, while being escorted by a Civil Servant or Military member holding a current CAC Card, effective 2 February 2016:
• Drivers licenses from states other than Washington, Illinois, Minnesota, Missouri and New
Mexico (unless WA, IL, MN, MI and NM licenses are the “Enhanced” version)
• U.S. passport
• U.S. passport card
• DHS trusted traveler cards ( Global Entry, NEXUS, SENTRI, FAST)
• Permanent resident card
• Border crossing card
• DHS-designated enhanced driver’s license
• Federally recognized, tribal-issued photo ID
• HSPD-12 PIV card
• Foreign government-issued passport
• Canadian provincial driver’s license or Indian and Northern Affairs-Canada card
• Transportation Worker Identification Credential (TWIC)
1.2.1. Contractor employees are required to have an individual identification badge as well as one (1) of the four (4) credentials listed below in their possession to gain access to job sites:
1.2.1.1. Common Access Card (CAC):
1.2.1.1.1. Contractors who have a need to access a government computer system may be eligible for a contractor CAC; most contractors are not eligible for a CAC. Contact the Contracting Officer’s Representative (COR) or Contracting Officer’s Security Officer for assistance as needed.
1.2.1.2. Single Day Pass:
1.2.1.2.1. Visiting vendors/contractors requiring infrequent access may obtain daily passes directly from the individual Navy Installation by submitting identification credentials for verification and undergoing a criminal screening/background check. A new pass is required to gain access each day. Passes are issued by Naval Base Kitsap (NBK). The Federal Bureau of Investigation’s (FBI) National Crime Information Center (NCIC) criminal database and FBI Terrorist Watch List will be checked daily prior to entry. In addition, NBK must check the Navy’s Consolidated Law Enforcement Operations Center (CLEOC) database to ensure an unescorted visitor has no objectionable criminal record, is not on the Terrorist Watch List and has not been previously debarred from entry onto any Navy Installation.
1.2.1.3. Defense Biometric Identification System (DBIDS) Program: Commander, Navy Installations Command (CNIC) has established the Defense Biometric Identification System (DBIDS) for access control to CNIC Installations via Entry Control Points (ECP). DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.
1.2.1.3.1. The Government performs background screening and credentialing.
Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
1.2.1.3.2. Access to Installation. All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS). The Contractor shall provide the Contracting Officer with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS.
Contact the Contracting Officer’s Representative (COR) or Contracting Officer’s Security Officer for assistance as needed. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
1.2.1.3.3. DBIDS Credentials. Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about DBIDS can be found at:
https://www.cnic.navy.mil/om/dbids.html.
1.2.1.3.4. The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.
1.2.1.3.5. The Contractor shall immediately collect employee DBIDS credentials and notify the Contracting Officer in writing:
1.2.1.3.5.1. That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
1.2.1.3.5.2. That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.
1.2.1.3.6. DBIDS Paper Passes. In the event that a visitor, vendor, or Contractor employee elects not to participate in DBIDS, the individual will be issued DBIDS paper pass from the Base Pass and Identification Office in order to access to the installation. The time standard for the validity of a pass to access an installation will be not more than thirty (30) days and may be further restricted based on local policy or by Federal, DOD, Navy, and CNIC guidance. The Government will not be responsible for any cost or lost time associated with obtaining paper passes or added vetting or inspections incurred by non-participants in the DBIDS credentialing process.
1.2.1.4. Transportation Workers Identification Credential (TWIC):
1.2.1.4.1. Trucking and Longshoremen industry, to include Military Sealift
Command (MSC) personnel are authorized to use this credential for unescorted access so long as the holder also has in his/her possession an original Bill Of Lading indicating that the delivery of goods is within the perimeter of the host installation, or in the case of MSC personnel, the holder has in his/her possession, a current Merchant Mariner identification card.
1.3. For contractor individuals that require higher level access requirements such as Nuclear Work Areas
(NWA), Controlled Nuclear Information Areas (CNIA) areas or access to the Main Machinery Rooms of nuclear propelled ships or submarines, the Contractor’s Facility Security Officer ( FSO) shall; (1) submit each individual’s information into the Joint Personnel Adjudication System (JPAS) Visit Request program with Security Management Office (SMO) number 002515, and (2) Submit a completed DD254 (ensuring that block 10b is checked), and that the Naval Nuclear Propulsion Information (NNPI) security clause is listed in either the Security Section of the Statement of Work (SOW) or in the list of effective clauses for review by the Industrial Security Office. Additionally, a separate Visit Request List Form (PSNS&IMF Form 5512) must be submitted to the Contracting Officer’s Security Officer.
1.4. The contractor shall prepare a Visit Request List Form with Cover Letter on Company Letterhead for all prime contractor and subcontractor personnel required to access Navy Vessels in the CIA. The visit request will be submitted via email to the Contracting Officer’s Security Officer at psnsimf.400scrty.fct@navy.mil. The cover letter will be a formal request for badging and access during the contract or delivery period of performance. The letter shall include (1) the purpose of access, (2) dates of validity (period of performance), (3) contract number, and (4) name of subcontractors to be employed. The cover letter shall be signed by the Prime Contractors Facility Security Officer (FSO), and shall be received by the Contacting Officer’s Security Officer NO LESS THAN FIVE (5) FULL WORKING DAYS PRIOR TO THE REQUESTED START DATE (8-10 calendar days prior is recommended). If red badges are required (for contractor personnel to access Restricted Data/Naval Nuclear Propulsion Information-NNPI) there are additional screening and higher level approval requirements, which could take considerably longer. Therefore, personnel identified in the Visit Request List must have a valid requirement to gain access to Restricted Data/NNPI. The prime contractor shall bear full responsibility for the accuracy of the Cover Letter and Visit Request List. Note: Submitting a cover letter and/or list with incomplete information, errors or a blanket list of all company personnel (especially for all red badges) can significantly delay processing requests and result in not being authorized access in time to begin the period of performance. With good cause, as determined by the Contracting Officer or appropriate Security Personnel, access requests may be refused or amended at any time. Updates to the Visit Request List shall be made on an as needed basis. The C400 security office may be contacted at (360) 476-0418 for questions regarding visit request processing.
1.5. The Visit Request List will be organized ALPHABETICALLY BY LAST NAME and contain the following information in column form (a spreadsheet template can be obtained by contacting the Contracting Officer’s Security Officer or COR).
• NAME ( LAST, FIRST, MI)
• DOB (Date of Birth)
• POB (City & State)
• SSN (Social Security Number)
• CITIZENSHIP (Country)
• PROFESSION/TRADE
1.6. Contractor employees must be U.S. citizens to access PSNS & IMF owned or controlled spaces unescorted, to include ship's engineering spaces. Foreign Nationals will be issued "Escort Required" white badges only. Additionally, an approved special security plan indicating the proposed visit locations and route to and from the location must be utilized. This requirement adds 3 working days to the visit request process. U.S. citizens working for Foreign Owned or Controlled Companies requiring access, unless they fall under a Defense Security Service (DSS) security clearance, will be issued Green badges only suitable for general CIA access. Access by U.S. citizens working for Foreign Owned or Controlled Companies into more stringently controlled areas such as Nuclear Work Areas (NWA) require a security plan and escorts. Ensure personnel employed by Foreign Owned or Controlled
Companies are clearly identified in Visit Request documents and in communications with the Contracting Officer's Security Officer. Security Clearance information, including confirmation of required red badges, shall be submitted to the Contracting Officer's Security Officer.
1.7. Badges will be picked up at the Naval Base Kitsap Visitor Control Center (VCC) in building 981. Each Contractor employee is REQUIRED to present proof of citizenship for on-site verification (not retention) at the VCC prior to obtaining a badge. This is a requirement for access into the CIA at PSNS&IMF, Bremerton, WA. All contractor employees requesting access shall be U.S. citizens. Acceptable proof of citizenship includes Original Birth Certificate (not a copy) or Current U.S. Passport.
1.8. Lack of a proper ID badge will result in denial of access to the Naval Installation, facility and/or the ship, resulting in a delay at the Contractor’s expense. If Contractor employees are providing a document with no photo, they shall also be required to present a current authorized official issue photo ID listed in paragraph 1.2 above.
1.9. Badges must be displayed on the outermost garment above the waist at all times. The only exception would be while the contractor personnel are engaged in work which could cause a safety hazard if the badge were worn while performing the work.
1.10. Contractor personnel are authorized to retain temporary badges until the badge expiration date or termination of employment. Upon badge expiration date, termination of employment, or completion of contract, the Contractor is required to immediately notify the Contracting Officer’s Security Officer and return all badges.
1.11. Lost or misplaced badges shall be reported immediately to the Contracting Officer’s Security Officer and
COR. If after hours report lost or misplaced badges immediately to the Navy Emergency Services Command (NESCOM) at 360-476-3393.
1.12. Immediately notify the Contracting Officer’s Security Officer and the COR of any access problems or security concerns.
1.13. To grant Contractor Vehicle Access to the PSNS & IMF CIA, a list of vehicles, a copy of each vehicle registration and a justification for access shall be submitted for processing via PSNS & IMF Form 5530/25. Contractors are required to stop at PSNS & IMF Pass & ID Office with proof of valid, current Driver’s License, vehicle registration and proof of insurance, prior to receiving access.
1.14. Contractor owned computers must be inspected by Code 109 prior to bringing them into the CIA and shall have a PSNS&IMF AIS Security Survey for Visitor Computer Equipment Form PSNS&IMF 5239/49 (Rev. 8-07), approved by Code 109, on site at all times.
1.15. Contractor Employees shall adhere to PSNS&IMF NOTICE 5239.6 PORTABLE ELECTRONIC
DEVICE (PED) GUIDANCE.
1.15.1. Lap-top Computers and/or cell phones equipped with cameras are STRICTLY PROHIBITED inside all PSNS & IMF owned or controlled spaces or property (the CIA, DMF & YOKO Enclaves, etc.) and subject to seizure by Installation Police and Shipyard Security Personnel.
1.15.2. ALL portable electronic devices are STRICTLY PROHIBITED onboard submarines (e.g.
phones, mp3 devices, computing devices, recording equipment, removable storage media, etc.).
2. NAVAL BASE KITSAP, BANGOR OPERATIONAL AREA (OA) / INDIAN ISLAND &
WATERFRONT RESTRICTED AREAS ACCESS:
2.1. PSNS & IMF CIA “Green” badges shall not provide access to the NBK Bangor Operational Area (OA).
PSNS & IMF CIA higher level badges (i.e. Red badges) shall provide access to the OA, but will not provide access to the Bangor Waterfront Restricted Areas.
2.2. Contractor employees that require access to the OA & Waterfront Restricted Area are required to obtain a CAC, DBIDS pass and card or a single day pass per paragraph 1.2.1.1 through 1.2.1.4.1 above.
2.3. The contractor shall prepare and submit a Visit Request via the Badge Authorization and Visit Request
(BAVR) at https://bavr.cnic.navy.mil for each contractor employee. A Common Access Card (CAC) is required to access the BAVR website. If you are not eligible for, or have not yet been issued a CAC, your command/government sponsor can fill out the request for you (with the pertinent personal information available), or you can contact the VCC for guidance and assistance. The Visit Request application must be received a minimum of five (5) full working days prior to the job start date (8-10 calendar days prior is recommended). Ensure that you completed all sections including PSNS & IMF sponsor (Contracting Officer’s Security Officer) and contract number into BAVR.
2.4. The contractor shall prepare and submit a Visit Request Form for each contractor employee to Commander, Navy Region Northwest (CNRNW) Pass & ID Office Bangor to receive a CNRNW badge.
2.5. For Vehicle Access, contractors shall provide a valid, current Driver's License, vehicle registration, and proof of insurance to the Pass & ID Office of the Naval Installation.
2.6. Cell phones equipped with cameras are PROHIBITED in the Waterfront Restricted Areas.
3. NAVAL BASE KITSAP, KEYPORT (NAVAL UNDERSEA WARFARE CENTER DIVISION,
KEYPORT) ACCESS:
3.1. If contractor employees are required access to NUWC Keyport, they will be required to obtain a CAC, DBIDS pass and card or a single day pass per paragraph 1.2.1.1 through 1.2.1.4.1 above.
3.2. All other visit requests requiring access to buildings the Contractor’s Facility Security Officer (FSO) shall; (1) submit each individual’s information into the Joint Personnel Adjudication System (JPAS) Visit Request program with Security Management Office (SMO) number 002536, and (2) Submit a completed DD254 (ensuring that block 10b is checked), and that the Naval Nuclear Propulsion Information (NNPI) security clause is listed in either the Security Section of the Statement of Work (SOW) or in the list of effective clauses for review by the Industrial Security Office. Additionally, a separate Visit Request List Form (PSNS&IMF Form 5512) must be submitted to the Contracting Officer’s Security Officer.
3.3. For specific security requirements see NUWC Keyport’s OPSEC Guide for Defense Contractors at http://www.navsea.navy.mil/Portals/103/Documents/NUWC_Keyport/OPSEC%20%20Guide%20for%2 0Defense%20Contractors_2016.pdf. A copy of the guide can also be obtained by contacting the Contracting Officer’s Security Officer or COR.
4. NAVAL STATION EVERETT ACCESS:
4.1. If contractor employees are required access to Naval Station Everett, they will be required to obtain a
CAC, DBIDS pass and card or a single day pass per paragraph 1.2.1.1 through 1.2.1.4.1 above.
4.2. For Pier Access to vessels, the contractor shall prepare and submit a Visit Request via the BAVR as identified in paragraph 2.3 above.
SECTION I - CONTRACT CLAUSES
The following have been added by full text:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
(NAVSEA VARIATION II) (SEP 2009)
(a) The Government may extend the term of this contract by written notice(s) to the Contractor within the periods specified below. If more than one option exists the Government has the right to unilaterally exercise any such option whether or not it has exercised other options.
FISCAL YEAR ITEM LATEST OPTION EXERCISE DATE
Per individual delivery order
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any option(s) under this clause, shall not exceed five
(5) years, however, in accordance with paragraph (g) of the requirement of this contract entitled "LEVEL OF EFFORT" (NAVSEA 5252.216-9122), if the total manhours delineated in paragraph (a) of the LEVEL OF EFFORT requirement, have not been expended within the period specified above, the Government may require the Contractor to continue to perform the work until the total number of manhours specified in paragraph (a) of the aforementioned requirement have been expended.
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days.
(End of clause)
(End of Summary of Changes)