N4215821QS039 Amendment 3 (Final 7-16-21).pdf

PDF 24 KB Posted

Attached to
Overhaul and Inspection of Barge YD 255
Solicitation number
N4215821QS039
Issued by

About this file

This document summarizes an amendment to a solicitation for the overhaul and inspection of Barge YD 255. The amendment provides answers to additional questions received from contractors regarding requirements for interior compartment cleaning and preservation, power tool cleaning levels, and access to a technical drawing. Contractors must contact the specified Navy representative by the stated deadline to receive a CD containing the referenced drawing if they have the appropriate security clearances. All other terms and conditions of the original solicitation remain unchanged. The opportunity remains for the complete overhaul and inspection of Barge YD 255 per the scope of work, including managing hazardous wastes, hull work, deck preservation, cleaning and pumping, as well as providing office space and dry-docking and undocking services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N4215821RC10130

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Provide answ ers to additional questions received.

2) Due to the restricted distribution, the draw ing that is referenced in the SOW may be provided as a CD to DOD contractors only w ho have the appropriate clearances/access. In order to receive the CD, please contact Ms. Victoria Buela, email at victoria.buela@navy.mil for the specif ic instructions on how to receive it by 5pm on 16 July 2021 (Friday). The CD shall be picked up by the authorized contractor personnel betw een 10:00AM to 12:00 noon on 19 July 2021 (Monday) from Ms. Buela.

3) All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Jul-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4215821QS039

X 9B. DATED (SEE ITEM 11)

16-Jun-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jul-2021

CODE

NORFOLK NAVAL SHIPYARD

ATTN: VICTORIA BUELA

SUB PRESERVATION SUPPORT SVCS

C451, BLDG 65, 2ND FLOOR, RM 201

PORTSMOUTH VA 23709-1022

N42158 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4215821QS039

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

ANSWERS TO QUESTIONS

SOLICITATION NUMBER: N4215821QS039

QUESTIONS AND ANSWERS:

BARGE YD 255 QUESTIONS: ANSWERS:

ITEM NO: 631-11-002

TITLE: Interior Compartment

Clean and Preserve

PARA. NO: 3.2

PAGE NO: 1of 3

QUESTION #18:

The government's answer to Question

#14 addressing the insulation covering the Auxiliary Machinery Compartment is insufficient. The amount of labor and material the government directed to be added to the work item will not cover the cost to remove and install all insulation in the compartment. The insulation was not removed on the prior barge contract. The contractor recommends that the government change the requirement for the

Auxiliart MAchinery Space to be a detergent cleaning of the insulation and top coat painting.

Answer to Question #18:

Use the guidelines of Society for

Protective Coatings (SSPC)

Painting Manual, Volume 2, Systems and Specifications. This

Manual is included in the reference

CD provided on 9 July 2021.

ITEM NO: 631-11-002

TITLE: Interior Compartment

Clean and Preserve

PARA. NO: 3.3

PAGE NO: 2 of 3

QUESTION #19:

Question #15 deals with the preparation method to be used in the four compartments below the deck level. The government's response to

Question #15 is, "Paragraph 3.3.1 needs to read; Power tool clean interior compartments located in 1.2 per

2.4". The only direction of the level of power tool cleaning is in paragraph 3.3 where it directs the contractor to complete 009-32, Table 3, Linee 9, Columns A, B and E. This is power tool cleaning to bare metal and painting. Is this the level of paint removal that the government is intending to complete? The contractor recommends completing power tool cleaning to SSPC SP-3 to remove all loose and flaking paint, feather in all spots, spot prime and overcoat the bilges without removing all the paint.

Answer to Question #19:

Use the guidelines of Society for

Protective Coatings (SSPC)

Painting Manual, Volume 2, Systems and Specifications. This

Manual is included in the reference

CD provided on 9 July 2021.

N4215821QS039

Drawing XM-36470 mentioned in Question #5

TITLE: Fuel Tank Level

Indicator (TLI); replace

PARA. NO: 2.6

PAGE NO: 1 of 2

QUESTION #20:

Drawing of XM-36470 mentioned in

Question #5

(TITLE: Fuel Tank Level Indicator

(TLI); replace PARA. NO: 2.6 PAGE

NO: 1 of2)

Answer to Question #20:

If you are a DOD contractor and have the appropriate clearances/access, contact Ms.

Victoria Buela to receive a CD containing one (1) drawing.

(End of Summary of Changes)