N4019219Q7001_AMD_0002.pdf

PDF 402 KB Posted

Attached to
Contractor Operated Civil Engineering Supply Store (COCESS), 36CES, AAFB, Guam
Solicitation number
N4019219Q7001
Issued by

About this file

N4019219Q7001_AMD_0002.pdf

View the file

Other files

File Type Posted
COCESS_APPENDIX__A__ATT02_03_REV_28DEC18.xlsx XLSX spreadsheet
N4019219Q70010003.pdf PDF
COCESS_APPENDIX__A__ATTACHMENT_02_03_REVISED.xlsx XLSX spreadsheet
19Q7001_AMEND_0001.pdf PDF
COCESS_APPENDIX__A__ATTACHMENT_02_03.xlsx XLSX spreadsheet
APPENDIX_A_19Q7001_COCESS_FINAL.pdf PDF
APPENDIX_B_19Q7001_DELIVERABLES_FINAL.pdf PDF
SF1449_19Q7001_FINAL.PDF PDF
N4019219Q7001_19Q7001_PRESOL_COCESS_NECO.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5511822

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. The purpose of this Amendment 0002 to subject solicitation is to accomplish the follow ing:

1. Provide answ ers to requests for information, see continuation page. Both inquiries and answ ers therein are hereby incorporated as solicitation provisions.

2. The quote due date is extended to no later than 2:00 P.M., Chamorro Standard Time, on 28 December 2018.

B. All other provisions and terms of this solicitation remain unchanged.

C. Offerors shall provide signature acknow ledgement of receipt for all solicitation amendments.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4019219Q7001

X 9B. DATED (SEE ITEM 11)

05-Nov-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Dec-2018

CODE

36TH CONTRACTING SQUADRON

LGCB

UNIT 14040, BLDG. 22026

APO AP 96543

N40192 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4019219Q7001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES REVISED

The following have been added by full text:

AMENDMENT 0002

A. The purpose of this Amendment 0002 to subject solicitation is to accomplish the following:

1. Provide answers to requests for information as shown below. Both inquiries and answers therein are hereby incorporated as solicitation provisions:

No. Date Questions Answers 1 11/05/2018 Regarding Appendix A Attachment 02 and

03:

Table 1 – you’ve listed over 600 items that have a CSL number and very generic descriptions. For example, line item 10 – “Switch”. I’m assuming light switch but that switch, depending on the specs, can range from $2 to $45. Only the incumbent can go into MAXIMO and look up the specs for that CSL / switch and hence bid the correct item. That’s obviously extremely unfair to the other bidders but also complicates your job because you will never know whether you are comparing apples to apples among bidders.

Line items 95 to 105 have descriptions of “Plate, Eagle”. They are all obviously unique and different Eagle Plates but, unless you’re the incumbent, it’s impossible to tell what the difference is.

Just a couple of examples, but the same analogy applies to a majority of the items on your list.

60 Day (Task Order 0001) – Same as above for those items that do have CSL #s associated with the item. While this list does have better descriptions and some part numbers, many are still too vague to quote. Line item 71 – Chlorine Regents – which ones? Price of those vary wildly. LI 83 – M/C cable – 250ft? 500 ft. coil? LI 85

– Wirenut Yellow, unit of issue EA – guessing it’s not really each because that’s not how they are generally sold. These come in varying package sizes so how many per each? 25? 50?

Please review Attachment (1), Revised Pre-Priced Line Items List (Appendix A, Attachment 02 and 03) of this Amendment for updated item descriptions.

2 11/06/2018 The issuance of subject solicitation dated 5 November 2018 with a proposal due date twenty-five (25) days later on 30 November 2018 is contrary to the provisions of FAR

5.203 (h) which states:

"In addition to other requirements set forth in this section, for acquisitions covered by the World Trade Organization Government Procurement Agreement or a Free Trade Agreement (see subpart 25.4), the period of time between publication of the synopsis notice and receipt of offers must be no less than 40 days."

Please note pages 17-20, 25 and 30 of subject solicitation which incorporate the Trade Agreements Act and therefore the due date for receipt of proposals “must be no less than” 20 December 2018.

Further, FAR 5.203 (b) provides that:

The contracting officer must establish a solicitation response time that will afford potential offerors a reasonable opportunity to respond to each proposed contract action, (including actions where the notice of proposed contract action and solicitation information is accessible through the GPE), in an amount estimated to be greater than $25,000, but not greater than the simplified acquisition threshold; or each contract action for the acquisition of commercial items in an amount estimated to be greater than $25,000. The contracting officer should consider the circumstances of the individual acquisition, such as the complexity, commerciality, availability, and urgency, when establishing the solicitation response time.

In accordance with the above cited FAR requirements, Noble respectfully request that the proposal due date be changed from 30 November to, no less than, 20 December 2018, to allow preparation of a totally responsive and responsible proposal in response to this complex and expansive requirement. We believe a 20 December response date would permit the time necessary to craft optimal proposals for the Government’s consideration.

The quote due date is extended as stated under item 14.A.2. below to allow contractors ample time to submit quotes.

3 11/11/2018 Regarding the Pre-priced item list for N4019219Q7001 for COCESS.

The attached list contains 62 items that addition information is needed to properly quote these items.

Please see response to question number 1 above.

4 11/14/2018 1. Please clarify if future contractor for the referenced project will pay rent for using AAFB facilities (building 18001).

2. To obtain specifications for the material listed on attachment 02, we did try to visit web sites provided on page 8 of 60 of solicitation but access was denied. Please advise if there are other sources available to be used to identify items and technical standards?

3. We would like to request for extension of bid date with 3 weeks to a month. Extended time will be needed to review all items and price them accordingly.

1. No, as stated in the solicitation (section 3.1), building 18001 is included as Government Furnished Property and the future contractor will not pay rent for using AAFB facilities (building 18001).

2. Please adjust your browser settings in order to access https://www.neco.navy.mil/. If still unable to access the site, as a courtesy, the Government Contracting Office shall send solicitation documents upon request.

3. The quote due date is extended as stated under item 14.A.2. below to allow

5 11/20/2018 1. Will a more detailed list of items be provided? Some item descriptions have various options (i.e. CSL AA001Y: Nil, 8D 2-1/2” comes in galvanized, stainless steel, etc.)

2. What are the operating hours for the store and is there any anticipation to operate outside normal working hours?

1. Please see response to question number 1 above.

2. Per solicitation specification 4.1 the hours of operation are 7:00 A.M.

to 4:00 P.M. (local time). Per solicitation specification 4.1.1, the Contractor shall provide emergency support during other than normal duty hours only upon authorization of the Contracting Officer.

6 11/21/2018 We have noticed that there has not been an Amendment posted to the NECO site regarding the additional information needed to quote the 62 items from the Pre-priced list.

As it is within 10 days of the solicitation due date of 02:00 PM 30 Nov 2018, we are formally requesting an extension on the proposal date of an additional 10 days. This will provide our company the time necessary to research not only the products that need additional data, but also to assimilate any other questions that may be posted from other bidders of N4019219Q7001 COCESS for Andresen

AFB.

The quote due date is extended as stated under item 14.A.2. below to allow

7 12/07/2018 1. Is there an option to purchase existing stock from the existing provider?

2. Does this contract allow the provider to use the Army Post Office/Naval Fleet Post Office?

3. Will the government provide a copy or access to a copy of the current pricing catalog in the 36th CE COCESS?

4. For Attachment 02, CSL AA001Y -Will the government expand the description to describe the nail as boxer, common, smooth shank, roofing, galvanized, etc.? For every nail type?

5. For Attachment 02, CSL AA002B -Will the government expand the description of the switch by material, throw, and voltage?

For every switch type?

6. For Attachment 02, CSL AA004Z -Will the filter by size (L x W x H), material, and purpose? For every filter type?

7. For Attachment 02, CSL AA005R- Will

Wire, #12, for inner material (copper, aluminum, steel), feet on a coil (25, 50, 100 feet), and coating (vinyl, grounded, braided, high volt insulated)?

8. For Attachment 02, CSL A008J -Will the government expand the description of Elbow, 1" for material and joint type (slip, FNPT, MNPT)?

9. For Attachment 02, CSL A009T- Will the government expand the description of Strap, RACO for material and diameter of grip?

10. For Attachment 02, CSL AA0012D- Will the government expand the description of Fixture for material and purpose (electrical, plumbing)?

1. Purchase of the existing stock by the awarded contractor must be negotiated directly with the existing provider.

2. No, the contractor shall utilize its own delivery and storage system for the performance of this contract. As stated in specification item 12.1 Delivery and Storage, 1.12.1. Deliver material to applicable Government warehouse or other delivery point(s) designated by the Government at the time of material ordering. The Contractor shall provide warehousing support at building 18001 for items stored in the warehouse and outside storage areas. This includes receipt of deliveries, physical storage of material and issuing of material to customers. The Contractor shall provide their own warehouse equipment except as stated in paragraph 3.2 of the specifications.

3. No, the Government shall not provide a copy or access to a copy of the current pricing catalog in the 36th CE COCESS as this is proprietary information.

4-17. Please see response to question number 1 above.

11. For Attachment 02, CSL AA014J- Will

Connector? For every Connector line item?

12. For Attachment 02, CSL AA0017H - Will the government expand the description of Conduit? For every Conduit line item?

13. For Attachment 02, CSL AA017R- Will

Faucet? For every Faucet line item?

14. 60 Day Task Order 1- Will the government expand the description for every adapter for fitting type to adapt onto?

15. 60 Day Task Order 1- Will the every Hy-max coupling for material and pressure rating?

16. 60 Day Task Order 1- Will the every item with Unit of Issue of PK to show quantity per pack?

17. 60 Day Task Order 1- Will the every item with Unit of Issue of CL to show feet per coil?

2. The quote due date is extended to no later than 2:00 P.M., Chamorro Standard Time, on 28 December 2018.

B. All other provisions and terms of this solicitation remain unchanged.

C. Offerors shall provide signature acknowledgement of receipt for all solicitation amendments.

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 30-Nov-2018 02:00 PM to 28-Dec-2018 02:00 PM.