25-0082 SOW.pdf
PDF 145 KB Posted
- Attached to
- Building SH50 Replace Water Source Heat Pump
- Solicitation number
- N4008527R9004
About this file
This is a Project Summary document for a federal construction contract (Project 25-0082) involving the mechanical replacement of HVAC systems in Building HP259, distributed to the DoD community only.
The contractor must provide all material, labor, equipment, and supervision to complete a comprehensive mechanical replacement of the HVAC systems serving Building HP259. The scope includes installation of a new 20-ton split system air handling unit (AHU-1) and matching outdoor air-cooled condensing unit (CU-1), ductwork connections, condensate drain lines, refrigerant piping, and associated electrical and control systems. The new 20-ton system must feature an electronically commutated motor (ECM) fan motor and be compatible with R-454B or R-32 refrigerant. Work includes tying the new split system into existing ductwork and electrical systems, demolishing and replacing specified refrigerant lines, condensate lines, and associated controls, and providing new electrical connections with a new disconnect for CU-1 in existing disconnect locations, completely replacing old circuits, breakers, and conduit.
The project has specific operational constraints: all work within the building (excluding the mechanical room) must occur strictly outside standard operating hours (weekdays 0800–1630) to minimize disruption to ongoing operations. All power outages must be scheduled on weekends or outside normal working hours with a minimum of five business days' advanced notice to the Contracting Officer. The building can remain occupied and functional during construction, with all work confined to the mechanical room and outdoor area surrounding it, aside from equipment and contractor access to the site. Supporting documentation includes contract drawings (sheets G001 through E103), specifications, and a submittal register.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25-0063 SOW (4).pdf | ||
| N4008525B0082 Specs.pdf | ||
| N4008525B0063 SpecSigned.pdf | ||
| N4008525B0063 DwgSigned.pdf | ||
| N4008525B0082 Dwgs.pdf | ||
| Pricing Sheet 27R9004.pdf | ||
| Mech MACC RFP 27R9004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION: DoD COMMUNITY ONLY
PROJECT: 25-0082
TITLE: BUILDING BUILDING HP259 MECHANICAL REPLACEMENT
25-0082.PDF (CONTRACT DRAWINGS SHEETS G001 THROUGH E103)
PUBLISH.PDF (SPECS)
REGISTER.PDF (SUBMITTAL REGISTER)
25-0082 PROJECT SUMMARY.PDF (THIS DOCUMENT)
SCOPE OF WORK:
THE CONTRACTOR SHALL PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND
SUPERVISION REQUIRED TO ACCOMPLISH THE FOLLOWING:
COMPLETE MECHANICAL REPLACEMENT OF THE HVAC SYSTEMS SERVING BUILDING
HP259, INCLUDING THE INSTALLATION OF A NEW 20-TON SPLIT SYSTEM AIR HANDLING
UNIT (AHU-1) AND MATCHING OUTDOOR AIR-COOLED CONDENSING UNIT (CU-1),
DUCTWORK CONNECTIONS, CONDENSATE DRAIN LINES, REFRIGERANT PIPING, AND
ASSOCIATED ELECTRICAL AND CONTROL SYSTEMS.
GENERAL DESCRIPTION
REPLACE THE EXISTING SPLIT SYSTEM AIR HANDLING UNIT (AHU-1) AND MATCHING
OUTDOOR CONDENSING UNIT (CU-1) WITH A NEW 20-TON SYSTEM FEATURING AN ECM
FAN MOTOR, COMPATIBLE WITH R-454B OR R-32 REFRIGERANT. TIE THE NEW SPLIT
SYSTEM INTO EXISTING DUCTWORK AND ELECTRICAL SYSTEMS. DEMOLISH AND
REPLACE SPECIFIED REFRIGERANT LINES, CONDENSATE LINES, AND ASSOCIATED
CONTROLS. PROVIDE NEW ELECTRICAL CONNECTIONS, FOR THE AHU-1 AND A NEW
DISCONNECT FOR CU-1 IN EXISTING DISCONNECT LOCATIONS, COMPLETELY REPLACING
OLD CIRCUITS, BREAKERS, AND CONDUIT.
IMPACT STATEMENT:
DUE TO THE DEMOLITION AND INSTALLATION OF THE MAIN 20-TON AIR HANDLER AND
ASSOCIATED CONDENSING UNIT, WORK WITHIN THE BUILDING (EXCLUDING THE
MECHANICAL ROOM) MUST BE PERFORMED STRICTLY OUTSIDE OF STANDARD
OPERATING HOURS (WEEKDAYS 0800–1630) TO MINIMIZE DISRUPTION TO ONGOING
OPERATIONS. ALL POWER OUTAGES MUST BE SCHEDULED ON WEEKENDS OR OUTSIDE
NORMAL WORKING HOURS, REQUIRING A MINIMUM OF FIVE (5) BUSINESS DAYS'
ADVANCED NOTICE TO THE CONTRACTING OFFICER. BUILDING CAN REMAIN OCCUPIED
AND FUNCTIONAL; ALL WORK WILL BE IN THE MECHANICAL ROOM AND IN OUTDOOR
AREA SURROUNDING IT (ASIDE FROM EQUIOPMENT AND CONTRACTOR ACCESS TO THE
SITE).