This is Amendment 0003 to Solicitation N40085-27-R-9000, issued by NAVFAC Mid-Atlantic on November 2, 2026, for the Repair Auto Maintenance Facility Building 575 project (Project No. 23-0040). The amendment is a Response to Requests for Information and does not extend the proposal receipt deadline. Offerors must acknowledge receipt of this amendment prior to proposal submission, either by completing items 8 and 15 and returning copies of the amendment, by acknowledging receipt on each copy of the offer, or by separate letter or telegram referencing the solicitation and amendment numbers. Failure to provide timely acknowledgment may result in rejection of the proposal.
The amendment addresses three key clarifications requested by offerors. First, it provides the missing Schedule of Fire Protection System Inspections that specification section 01 45 00 referenced but did not include. This schedule outlines FPQC specialist surveillance requirements across three phases: surveillance during construction, pre-final acceptance inspection, and final acceptance inspection, covering fire suppression systems, special fire suppression systems, passive fire protection systems, and fire alarm systems. Second, the amendment clarifies a conflicting specification regarding flooring systems in section 09 67 23, directing contractors to omit section 09 67 23.16 and follow section 09 67 23.13, which specifies a 5-coat, fuel-resistive, solid color troweled epoxy mortar system rather than the decorative flake broadcast system. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0007.pdf | ||
| Amend 0006.pdf | ||
| Amend 0005.pdf | ||
| Amend 0004.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| Pricing Sheet.pdf | ||
| RFP 230040.pdf | ||
| 23-0040 APPD.pdf | ||
| N4008523B0040 SpecsSigned.pdf | ||
| N4008523B0040 DwgsSigned.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 7
AMENDMENT NO. 0003 11/02/26 23-0040
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-27-R-9000
10/22/26
23-0040, Repair Auto Maintenance Facility Bldg 575 Amendment 0003, Response to Requests for Information
The time and date for receipt of proposals remains unchanged.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See continuation pages.
N40085-27-R-9000 Amendment 0003
CONTINUATION SHEET
1. QUESTION: Specification section 01 45 00, 1.6.4.1.3, states that a "Schedule of Fire Protection System Inspections" is included at the end of this UFGS section. But no such schedule is provided. Please provide this missing schedule.
ANSWER: See attached file.
2. QUESTION: The finish schedule calls for Deco-Flake from Sherwin Williams which is a decorative flake broadcast system installed at around 40 mils thick. The spec calls for a 5-coat, fuel resistive flooring system which is a solid color troweled epoxy mortar system installed at about 250 mils thick (1/4”). These are two completely different systems. Can you confirm which system we should bid on this project. Section 09 67 23.13
ANSWER: OMIT section 09 67 23.16. Follow section 09 67 23.13.
3. All other terms and conditions remain unchanged.
SCHEDULE OF FIRE PROTECTION SYSTEM
INSPECTIONS BY FPQC SPECIALIST
1. INSTRUCTIONS for FPQC Specialist:
Perform surveillance of fire protection system installation during construction and during pre-final and final acceptance inspections. Surveillance includes either visual inspections or observations performed by the FPQC as indicated in the following Schedule of Fire Protection System Inspections.
Check boxes in the schedule indicate the inspections or observations that are applicable to this project, which must be performed and documented by the FPQC.
Surveillance of fire protection system inspections is divided into three phases:
Surveillance During Construction – Includes periodic on-site visits by the FPQC during construction Pre-Final Acceptance Inspection – FPQC must be onsite during pre-final acceptance inspection Final Acceptance inspection – FPQC must be onsite during final acceptance inspection
2. INSPECTION TYPE
VISUAL INSPECTION:
Perform on-site visual inspections as indicated in the Schedule of Fire Protection System Inspections as construction progresses to confirm work conforms with the contract requirements including but not limited to verifying proper installation of equipment and materials in accordance with applicable codes. Where work will be covered up by finished walls and ceilings, inspections must be scheduled and performed when work is still visible.
OBSERVATION:
Observe component and system testing in person on-site as indicated in the Schedule of Fire Protection System Inspections. Confirm testing is completed in accordance with applicable codes and that testing was successful.
DOCUMENTATION:
Document all inspections and observations in the FPQC Report in accordance with UFGS 01 45 00.
Document any deficiencies and all work observed that has been successfully performed in accordance with the contract documents. Record deficiencies in the rework list.
PERFORM SURVEILLANCE DURING CONSTRUCTION
~ FIRE SUPPRESSION SYSTEM ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Verify proper installation of underground service main and service; laterals, thrust blocks, tie-rods and connection to above ground piping.
VISUAL
INSPECTION
Visually inspect materials Visually inspect installation
2. Verify proper orientation of fire hydrants and fire department access
VISUAL
INSPECTION
Visually inspect installation and orientation
3. Verify proper installation of interior and exterior attachments, coatings, and vortex plate prior to filling fire protection water tank
VISUAL
INSPECTION
Visually inspect fire protection water tank installation
4. Hydrostatic/leak test for underground piping
OBSERVE Verify proper test method Confirm test was successful
5. Hydrostatic/leak test for above ground piping prior to ceiling installation
OBSERVE Verify proper test method Confirm test was successful
6. Underground system flush prior to connection to the riser
OBSERVE Verify system was properly flushed
7. Forward flow test for Backflow preventer
OBSERVE Verify proper test method Confirm test was successful
8. Suction pipe flush prior to fire pump startup
OBSERVE Verify system was properly flushed
9. Hydrostatic test fire pump suction and discharge piping
OBSERVE Verify proper test method Confirm test was successful
10. Fire pump startup OBSERVE Confirm successful startup
11. Verify proper installation of sprinkler piping prior to wall or ceiling installation
VISUAL
INSPECTION
Inspect pipe hangars, bracing, sprinkler heads Inspect for sprinkler obstructions;
damaged, painted or covered heads Verify proper location of control valves, drains, vents, backflow, test header Verify proper component mounting heights
12. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur Annotate deficiencies and satisfactory work observed Record rework items in FPQC report
~ SPECIAL FIRE SUPPRESSION SYSTEM ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Verify proper installation of gaseous fire suppression system
VISUAL
INSPECTION
Inspect gas cylinders, initiating controls, shutdowns, aborts, and visual warning
2. Verify proper installation of IR hangar detector
VISUAL
INSPECTION
Inspect detector and nozzle layout Inspect for obstructions, abort stations Inspect riser piping
3. Verify proper installation of elevator fire protection
VISUAL
INSPECTION
Inspect elevator recall functions Inspect two-way communication
4. Verify proper installation of fire suppression in secure spaces
VISUAL
INSPECTION
Inspect location of sprinkler piping and sprinklers
5. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur Document deficiencies and satisfactory work observed in FPQC Report Record deficiencies in rework list
~ PASSIVE FIRE PROTECTION SYSTEMS ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Verify proper construction of fire rated assemblies
VISUAL
INSPECTION
Inspect partitions for proper fire rated construction per design Inspect doors and door hardware for proper fire rating Inspect glass for proper fire rating
2. Verify proper installation of fireproofing
VISUAL
INSPECTION
Inspect for use of proper fireproofing materials Inspect for cracking, spalling or delaminating Inspect for proper application thickness
3. Verify proper installation of firestopping
VISUAL
INSPECTION
Inspect to confirm firestopping system is UL tested or an engineering judgement has been obtained and submitted Inspect for use of proper firestopping materials Inspect penetrations through fire rated walls, partitions and ceilings Inspect construction joints and gaps
4. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur
Document deficiencies and satisfactory work observed in FPQC Report Record deficiencies in rework list
~ FIRE ALARM SYSTEMS ~
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Verify proper installation of fire alarm system after conduit is installed and wiring pulled, but before devices are installed
VISUAL
INSPECTION
Inspect conduit, wiring, conduit fill, wire type Inspect installation heights of back boxes
2. Document inspections and observations in FPQC Report
DOCUMENT Submit report for each day inspections or observations occur Document deficiencies and satisfactory work observed in FPQC Report Record deficiencies in rework list
~ END OF SURVEILLANCE DURING CONSTRUCTION SECTION
PERFORM DURING PRE-FINAL ACCEPTANCE INSPECTION
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Inspect all fire protection systems and all life safety features
VISUAL
INSPECTION
Verify proper installation of fire protection and life safety systems
2. Witness functional testing of all fire protection and life safety systems
OBSERVE Verify proper testing is performed on fire protection and life safety systems
3. Identify deficiencies that require correction
VISUAL
INSPECTION
Document deficiencies in FPQC Report and record in rework list
4. Verify rework items have been corrected
VISUAL
INSPECTION
Record re-inspection results on FPQC Report
5. Document results of pre-final inspection and photograph unsatisfactory conditions
DOCUMENT Document results of pre-final inspection in FPQC Report
6. Certify installation and operation of all fire protection and life safety systems conform to the contract documents
DOCUMENT Provide separate letter certifying conformance with contract requirements
~ END OF PRE-FINAL INSPECTION SECTION
PERFORM DURING FINAL ACCEPTANCE INSPECTION
PERFORM
TASK IF
CHECKED
TASK INSPECTION
TYPE DESCRIPTION
1. Verify proper installation and operation of all fire protection systems and all life safety features
VISUAL
INSPECTION
2. Note any deficiencies identified by Government FPE on deficiency list
DOCUMENT Document deficiencies identified by Government FPE on deficiency list
3. Verify all deficiencies have been corrected
VISUAL
INSPECTION
Inspect rework to confirm all deficiencies have been corrected
4. Certify that all deficiencies have been corrected
DOCUMENT Document inspection results on FPQC Report
~ END OF FINAL ACCEPTANCE INSPECTION SECTION