This is a Request for Information (RFI) form template used for the federal contract N40085-26-RFPRFQ-NEW-LONDON-ROICC-0049, specifically for the B434 Roof Replacement project. The form provides a standardized mechanism for contractors to request clarification or additional information regarding contract requirements, drawings, specifications, or other technical details. The RFI form includes fields for identifying the prime contractor and subcontractor/supplier, documenting relevant drawings and specifications, and indicating whether the requested information has cost or schedule implications (increase, decrease, or none).

The form establishes a three-tier review and response process: contractors submit information requests with a required response date, the field office provides a recommendation with date and signature, and the field office then forwards a reply to the prime contractor. The form explicitly states that RFI responses do not authorize contractors to proceed with work and do not constitute a basis for changes in contract amount or time. If contractors believe an RFI response indicates a changed condition, they must provide written notice to the Contracting Officer within 20 calendar days. Distribution of completed RFIs goes to the file, REICC, Project Labor Division/Design Manager, Engineering and Technology/Architect-Engineer, PC number assignment, and the Appropriate Regional Office/Contract Officer. The form serves as a template and does not address specific required products or services.

View the file

Other files

File Type Posted
(A) RFP.pdf PDF
(C) CT Wage Determination.pdf PDF
(B) B434 SOW_Specs.pdf PDF
(N) Drawings B434 Roof.pdf PDF
(D) ECMS.pdf PDF
(I) General Requirements.pdf PDF
(H) Map to B135.pdf PDF
(K) Price Proposal Form.docx DOCX document
(M) NEPA.pdf PDF
(E) CERT-141.pdf PDF
(L) 52.204-24.pdf PDF
(F) Guide to Taxes.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP NUMBER:

N40085-26-RFPRFQ-NEW-LONDON-ROICC-0049

REQUEST FOR INFORMATION RFI NUMBER:

CONTRACT TITLE:

PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:

SUBJECT/TITLE OF RFI:

DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY NUMBER:

COST EFFECT: INCREASE: DECREASE: NONE:

INFORMATION REQUESTED & RECOMMENDED SOLUTION:

Date Response Required By: Date: Signature:

From:

To: Field Office Code

RECOMMENDATION:

Date: Signature:

From: Field Office To: Prime Contractor

REPLY:

Date: Signature:

This reply is given with the expressed understanding that it does not constitute basis for change in the amount or time of subject contract. If you do not concur, DO NOT PROCEED, and notify this office immediately.

Please assign PC # to this change. It is requested that a proposal be forwarded by . THIS DOES NOT

CONSTITUTE AUTHORIZATION TO PROCEED.

copy to: File 2L

Supv Civil Engineer Construction Representative

B434 Roof Replacement

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.

DISTRIBUTION: Original to File via REICC PL/DM ET A/E PC # via AROICC/CONTRACT OFFICER