(J) RFI Form.pdf
PDF 435 KB Posted
- Attached to
- Building 434 Roof Repair
- Solicitation number
- N40085-26-RFPRFQ-NEW-LONDON-ROICC-0049
About this file
This is a Request for Information (RFI) form template used for the federal contract N40085-26-RFPRFQ-NEW-LONDON-ROICC-0049, specifically for the B434 Roof Replacement project. The form provides a standardized mechanism for contractors to request clarification or additional information regarding contract requirements, drawings, specifications, or other technical details. The RFI form includes fields for identifying the prime contractor and subcontractor/supplier, documenting relevant drawings and specifications, and indicating whether the requested information has cost or schedule implications (increase, decrease, or none).
The form establishes a three-tier review and response process: contractors submit information requests with a required response date, the field office provides a recommendation with date and signature, and the field office then forwards a reply to the prime contractor. The form explicitly states that RFI responses do not authorize contractors to proceed with work and do not constitute a basis for changes in contract amount or time. If contractors believe an RFI response indicates a changed condition, they must provide written notice to the Contracting Officer within 20 calendar days. Distribution of completed RFIs goes to the file, REICC, Project Labor Division/Design Manager, Engineering and Technology/Architect-Engineer, PC number assignment, and the Appropriate Regional Office/Contract Officer. The form serves as a template and does not address specific required products or services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| (A) RFP.pdf | ||
| (C) CT Wage Determination.pdf | ||
| (B) B434 SOW_Specs.pdf | ||
| (N) Drawings B434 Roof.pdf | ||
| (D) ECMS.pdf | ||
| (I) General Requirements.pdf | ||
| (H) Map to B135.pdf | ||
| (K) Price Proposal Form.docx | DOCX document | |
| (M) NEPA.pdf | ||
| (E) CERT-141.pdf | ||
| (L) 52.204-24.pdf | ||
| (F) Guide to Taxes.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP NUMBER:
N40085-26-RFPRFQ-NEW-LONDON-ROICC-0049
REQUEST FOR INFORMATION RFI NUMBER:
CONTRACT TITLE:
PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:
SUBJECT/TITLE OF RFI:
DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY NUMBER:
COST EFFECT: INCREASE: DECREASE: NONE:
INFORMATION REQUESTED & RECOMMENDED SOLUTION:
Date Response Required By: Date: Signature:
From:
To: Field Office Code
RECOMMENDATION:
Date: Signature:
From: Field Office To: Prime Contractor
REPLY:
Date: Signature:
This reply is given with the expressed understanding that it does not constitute basis for change in the amount or time of subject contract. If you do not concur, DO NOT PROCEED, and notify this office immediately.
Please assign PC # to this change. It is requested that a proposal be forwarded by . THIS DOES NOT
CONSTITUTE AUTHORIZATION TO PROCEED.
copy to: File 2L
Supv Civil Engineer Construction Representative
B434 Roof Replacement
The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.
DISTRIBUTION: Original to File via REICC PL/DM ET A/E PC # via AROICC/CONTRACT OFFICER
File details come from the government source that posted it. Updated .