25-0014 REVISED SOW 13APR2026.pdf

PDF 59 KB Posted

Attached to
Building FC65 Exhaust System Repairs
Solicitation number
N4008526R9023
Issued by

About this file

This is a Presolicitation/Scope of Work document for DoD contract 25-0014 regarding Building FC65 Exhaust System Repairs at Camp Lejeune, North Carolina.

The project scope encompasses replacement of exhaust systems and associated ductwork serving three dishwashers in Building FC65 (Mess Hall) located on Gonzalez Boulevard West, Camp Lejeune, NC 28547. The primary objective is to prevent condensation from dripping on ceilings. Work includes four distinct tasks: (1) F-12 demolition with ceiling repairs and drop ceiling reinstallation in the female head area; (2) F-7 complete replacement with new stainless-steel ductwork, wall-mounted exhaust fan with backdraft damper, circuit breaker, disconnect switch mounted externally, and BMS integration for monitoring and alarms in dishwasher room 111; (3) F-11 replacement with identical specifications to F-7 in the same location; and (4) F-6 complete replacement with the same new system configuration. All new ductwork must be stainless steel with welded seams and properly sloped. All exhaust fans must operate for an additional five minutes after dishwasher shutdown. New control wiring must connect dishwashers to exhaust fans and to the Building Management System. A temporary wall must be installed in the storage room to separate the work area from operational mess hall facilities. The contractor must follow Combined DIV 01 DBB Specs and BACnet Direct Digital Control Systems for HVAC (CLGS-23-09-23.13, August 2024). All scheduling and access must be coordinated with the Building Manager. After-hours work is required to prevent Mess Hall service interruptions. No environmental considerations are noted.

View the file

Other files

File Type Posted
Amend 0001.pdf PDF
Mech MACC RFP.pdf PDF
N4008525B0014 Dwgs.pdf PDF
N4008525B0014 Specs.pdf PDF
25-0014 SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION: DoD COMMUNITY ONLY

TITLE: 25-0014 Building FC65 Exhaust System Repairs

ATTACHMENTS:

Contractor shall follow Combined DIV 01 DBB SPECS and BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC

(CLGS-23-09-23.13 August 2024)

SCOPE OF WORK:

The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following:

General Description:

The intent of this project is to replace the exhaust system and associated ductwork on all three dishwashers to prevent condensation from dripping on ceilings. FC65 is located on Gonzalez Blvd. West on Camp Lejeune, N.C.

28547.

REQUIREMENTS AND SPECIFICATIONS:

1. F-12 – Demo fan and cap existing ductwork to be abandoned in place. F -12 will no longer be used.

Demo all wiring and conduit, including control wiring back to the BMS. Replace sheetrock ceiling and install new access door in Female Head after overhead work has been completed. Prep and paint with like color paint. Remove drop ceiling in hallway outside female head to access exhaust fan, ductwork, and wiring to be demoed. When overhead work is completed, reinstall drop ceiling and replace as necessary. Install new ceiling tiles.

2. F-7 – Demo F-7 and all associated ductwork located in dishwasher room 111. Cap existing ductwork to be abandoned in place. Demo existing wiring and conduit, including any control wiring. Install properly sized and sloped new stainless-steel ductwork, with welded seams, up to new properly sized wall mounted exhaust fan with backdraft damper. Install new properly sized circuit breaker for new wall mounted exhaust fan. Route properly sized electrical wiring and conduit to new properly sized disconnect for new exhaust fan. New disconnect shall be mounted on the exterior near the new exhaust fan. Route properly sized new wiring and conduit from disconnect to exhaust fan. Install new control wiring and conduit connecting dishwasher to new exhaust fan and exhaust fan to BMS for monitoring and alarms. Ensure new exhaust fan runs an additional 5 minutes after dishwasher shuts off. Seal area where ductwork and conduit exit the building to match existing.

3. F-11— Demo F-11 and all associated ductwork located in dishwasher room 111. Cap existing ductwork to be abandoned in place. Demo existing wiring and conduit, including any control wiring.

Install properly sized and sloped new stainless-steel ductwork, with welded seams, up to new properly sized wall mounted exhaust fan with backdraft damper. Install new properly sized circuit breaker for new wall mounted exhaust fan. Route properly sized electrical wiring and conduit to new properly sized disconnect for new exhaust fan. New disconnect shall be mounted on the exterior near the new exhaust fan. Route properly sized new wiring and conduit from disconnect to exhaust fan. Install new control wiring and conduit connecting dishwasher to new exhaust fan and exhaust fan to BMS for monitoring and alarms. Ensure new exhaust fan runs an additional 5 minutes after dishwasher shuts off. Seal area where ductwork and conduit exit the building to match existing.

4. F-6 – Demo F-6 and all associated ductwork complete. Demo existing wiring and conduit, including any control wiring. Install properly sized and sloped new stainless-steel ductwork, with welded seams, up to new properly sized wall mounted exhaust fan with backdraft damper. Install new properly sized circuit breaker for new wall mounted exhaust fan. Route properly sized electrical wiring and conduit to new properly sized disconnect for new exhaust fan. New disconnect shall be mounted on the exterior near the new exhaust fan. Route properly sized new wiring and conduit from disconnect to exhaust fan. Install new control wiring and conduit connecting dishwasher to new exhaust fan and exhaust fan to BMS for monitoring and alarms. Ensure new exhaust fan runs an additional 5 minutes after dishwasher shuts off. Seal area where ductwork and conduit exit building

DISTRIBUTION: DoD COMMUNITY ONLY to match existing. Temporary wall shall be installed in storage room to separate work area in storage room from the area that mess hall personnel will be continually using.

SPECIAL SCHEDULING AND ACCESS:

All scheduling and access shall be coordinated with the Building Manager.

SPECIAL CONDITIONS:

After hours work will be required to prevent Mess Hall service interruptions.

ENVIROMENTAL:

None