This is a Scope of Work (SOW) for ballfield lighting replacement at Naval Air Station Oceana in Virginia Beach, Virginia, prepared by NAVFAC Mid-Atlantic. The project involves replacing approximately 127 pole-mounted metal halide light fixtures with new LED fixtures across four locations: Ballfield 622 (41 fixtures), Ballfield 623 (38 fixtures), Running Track 624 (4 new fixtures), and Ballfield 631 (48 fixtures). The contractor must also remove and replace control enclosures and electrical components at each location with new NEMA 4x enclosures housing control transformers, timed relays, lighting contactors, on/off switches, and photo cells. All timed relays shall feature off-delay function with adjustable timing ranges of 0.1-10.0 hours set to 10 hours, and photo cells must control power to ensure lights remain off during daylight. At Ballfield 623, the contractor must remove an inactive osprey nest in accordance with environmental requirements and reinstall an existing scoreboard controller. At Ballfield 631, broken rigid conduit entering ground must be repaired. The specified LED fixtures are HYLITE AEON PNR Series (APF-500WD-50K-N4-480V or APF-750WD-50K-N4-480V) providing 500W at 91,300 lumens or 750W at 113,860 lumens with 75% energy savings.

The contract completion date is 120 calendar days from award. The contractor must provide supervision, labor, materials, and equipment to deliver a complete, usable finished product with all new equipment equivalent or superior to existing fixtures. Work hours are 0700-1630, Monday through Friday, excluding federal holidays, with advance approval required for outside-hours work. All contractor employees and subcontractors must obtain current Contractor Base Access Passes and Badges and comply with installation security requirements. Prior to construction start, the contractor must submit manufacturer's product data, equipment equivalency documentation, warranties, Accident Prevention Plan, Activity Hazard Analysis, and Quality Control Plan for government approval. The contractor must verify all light fixture and material counts before ordering and coordinate with the Oceana Installation Environmental Office regarding waste lightbulb disposal as universal waste. All work must comply with USACE EM-385-1-1, OSHA CFR Part 1926, and USEPA regulations, with lock-out/tag-out procedures required prior to any electrical work. Key points of contact include FEAD Contracting Officer Tanya Corcoran and Work Package Developer Paul Vaughan.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAS OCEANA BALLFIELDS (W):131675204 (eProjects):1924729

BALLFIELD LIGHTING

NAS OCEANA, VIRGINIA BEACH, VIRGINIA

SCOPE OF WORK 17 April 2026 Page 1 of 22

***UNCLASSIFIED***

NAS OCEANA BALLFIELDS

At the

Naval Air Station Oceana, Virginia Beach, Virginia

PREPARED BY:

NAVFAC MID-ATLANTIC, PWD OCEANA,

Facility Engineering and Acquisition Division (FEAD), Facility Support Contract Branch (FSCB), PRA23 NAS Oceana, 953 Hornet Drive, Building 820, Suite 213

Virginia Beach, Virginia 23460-2197

Work Package Developer: Paul Eli Vaughan

APPROVED BY:

FSC Branch CAT III/IV Team Lead: Frederick Clark

SCOPE OF WORK 17 April 2026 Page 2 of 22

1. POINTS OF CONTACT:

FEAD Contracting Officer: Tanya Corcoran, (757) 433-2668 FEAD Contract Specialist in charge: TBD Work Package Developer: Paul Vaughan, (757) 433-2649 Facility Maintenance Specialist (FMS): William Tuner, (757) 433-2878 Activity POC: Ryan Mason, (757) 433-2049

2. GENERAL:

2.1 The Contractor must provide supervision, labor, material and equipment required to perform all work for the following project: Replace All Ballfield Lights. All work must be done in a manner to provide a complete, usable and finished end product. See paragraph “7. WORK REQUIREMENTS” for an expanded and detailed Scope of Work. The Superintendent, Site Safety, Health Officer and QC Manager must be a direct employee of the Prime Contractor.

2.2 The Contractor must comply with the requirements and specifications of the most current Contract.

2.3 A Pre-Proposal site meeting may be scheduled at the project site to review and discuss the Scope of Work and assess existing field conditions, prior to Award of this Task Order.

2.4 Existing reference drawings may be available upon request. Reference drawings must be used for informational purposes only, and may not accurately reflect current as-built conditions. The Contractor must not solely rely on the reference drawings to determine existing conditions, but must field verify all existing conditions pertinent to the project.

2.5 All work must be performed in accordance with, but not limited to, standard industry practices, applicable local, state and federal codes, laws and regulations, contract specifications, Unified Facilities Criteria (UFC’s) and Unified Facilities Guide Specifications (UFGS’s).

2.6 Supervision: Have a Supervisor fluent in English on the job site during working hours at all times.

The Supervisor must be a United States Citizen or a Documented Legal Resident of the United States of America.

3. SPECIAL SCHEDULING REQUIREMENTS/WORK PROCEDURES:

3.1 The project Contract Completion Date (CCD) must be 120 calendar days from Award of this Task

Order.

3.2 Existing and adjacent spaces to remain in operation during construction must be protected from damage, dust, and debris at all times. Damage to any existing spaces, finishes, items, furniture and equipment, as a result of the Contractor’s operations, must be replaced in-kind by the Contractor at no expense to the Government.

3.3 FOD PREVENTION: The Contractor must take any/all measures to prevent the spread of Foreign

Object Debris (FOD) adjacent to, or onto runway/taxiway pavements or within active hangar bay areas. The Contractor must take the necessary precautions to fully contain FOD producing operations to the limits of construction as approved by the Contracting Officer and Activity. The Contractor must keep construction work areas clean to prevent the spread of FOD.

SCOPE OF WORK 17 April 2026 Page 3 of 22

3.4 UTILITIES LOCATION AND VERIFICATION (Exterior): Prior to digging, the appropriate digging permit must be obtained. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department, prior to any digging. Any markings made during the utility investigation must be maintained throughout the contract. The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 2 feet of a known utility must not be performed by means of mechanical equipment; hand digging must be used. If construction is parallel to an existing utility expose the utility by hand digging every 100 feet if parallel within 5 feet of the excavation.

3.5 In the event that hazardous waste is generated or mobilized, the hazardous waste program manager must be contacted for the appropriate guidance. In addition, any movement of soil/fill material outside of project boundaries, meaning both soil brought onsite and soil from the site relocated to other areas, must be coordinated with the hazardous waste program manager to ensure environmental compliance.

3.6 Pre-Outage Coordination Meeting:

Apply for outages at least 15 days in advance to the Contracting Officer. As a minimum, the request must include the location of outage, areas being affected, duration of outage and any necessary sketches. Any/all outage requests must be approved by the Contracting Officer prior to starting the work. Once approved, and prior to beginning work on the system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist. All expenses incurred for outages shall be the responsibility of the Contractor.

3.7 Control of Hazardous Energy (Lock-out/Tag-out):

Provide and operate a Hazardous Energy Control Program (HECP) in accordance with EM 385-1-1 Section 12, 29 CFR 1910.333, 29 CFR 1915.89, and paragraph HAZARDOUS ENERGY CONTROL

PROGRAM (HECP).

3.8 In general terms, demolition work and the use of word “demolish”, must include the removal and effective management and disposal of existing construction and or structures. Contractor must take care to prevent damage to existing utilities and construction that are not scheduled for demolition. If damage occurs, the Contractor must make repairs, or replacement with new, to the satisfaction of the Contracting Officer and at no cost to the Government. Selling of demolished or salvaged materials and equipment on government properties is prohibited.

3.9 Work Hours: The Contractor’s normal working hours must be between 0700 to 1630, Monday through Friday, excluding Federal Holidays. Advance approval is required for contractor personnel to work outside of normal working hours.

3.10 Passes and Badges: All Contractor employees, including subcontractors, and subcontractors’ employees, suppliers, and suppliers’ employees must be required to comply with the Installation Security Requirements regarding personnel, vehicle, equipment, security passes/badges and access to the jobsite. Nothing in the contract must be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station. All Contractor employees/subcontractors must have current and valid government issued Contractor Base Access Passes and Badges, in order to perform work under this contract.

SCOPE OF WORK 17 April 2026 Page 4 of 22

Responsibility for Escorts: The Contractor must be responsible for coordinating escorts with the Building Activity/Tenant at all times. The Contracting Officer and other NAVFAC personnel “must not” be responsible for the coordination of escorts for Contractor personnel.

3.11 The Contractor must provide detour signage for redirection of occupants during the entirety of construction.

3.12 To minimize downtime for the area, construction activities may not start until the Contractor provides confirmation of receipt of all new products and materials necessary to complete the work, prior to start of construction.

4. SAFETY:

SAFETY STATEMENT: The contractor shall comply with the most current edition of the USACE EM-385-1-1, OSHA CFR Part 1926; along with all other federal, state, and local laws and regulations. Where differences occur within, the most stringent shall apply.

4.1 Contractor must utilize all safety equipment when operating aerial man lifts, as well as proper signage, barriers to ensure safety of ground workers and pedestrians.

4.2 Contractor shall comply with base fire safety rules when the use of flammable cutting tools are necessary.

5. HAZARDOUS MATERIALS (HAZMAT) DISCLOSURE STATEMENT(S):

HAZMAT STATEMENT: Contractor shall comply with all USEPA and OSHA laws and regulations, along with all other federal, state and local laws and regulations. Where differences occur, the most stringent shall apply.

5.1 For repair, remodeling, or minor construction and demolition, the contractor may be required to work in areas that have, but not limited to, flooring, walls, ceilings, insulation, roofing materials and paints etc., that may contain hazardous materials requiring abatement and/or management according to applicable laws and regulations. If during the performance of the work the contractor encounters hazardous substances not known prior to issuance of this Task Order; the contractor must immediately stop work and inform the Contracting Officer.

6. SUBMITTALS:

6.1 The Contractor must submit the following for government approval, prior to the start of any construction activities:

6.1.1 Manufacturer’s Product Data: Submit manufacturer’s written detailed product data cut sheets, with instructions for installation, adjustment, cleaning and maintenance instructions.

6.1.2 Contractor shall provide documentation in writing that the new units are equivalent (or superior) in every respect. Written documentation shall contain efficiency of new unit, complete serial numbers and model numbers of proposed equipment.

SCOPE OF WORK 17 April 2026 Page 5 of 22

6.1.3 Manufacturer Warranties: Contractor shall submit to the Government all warranties against defects of equipment, material and workmanship.

6.1.4 Accident Prevention Plan (APP):

6.1.5 Activity Hazard Analysis (AHA):

6.1.6 Quality Control Plan:

7. WORK REQUIREMENTS:

The Contractor shall provide supervision, labor, material, and equipment as required to perform the following work. Work shall be done in a manner to provide a complete, usable, and finished end product.

Unless otherwise stated, all materials, components, and equipment procured and installed by the Contractor shall be equivalent (or superior) in every function and feature to what exists.

All materials, components, and equipment shall be installed in strict adherence to manufacturer’s specifications.

Waste lightbulbs (including LEDs) must be managed as universal waste in Virginia, and must be properly disposed. Contact the Oceana Installation Environmental Office (433- 3438) prior to work start to ensure appropriate waste management. Universal waste must be disposed of at an authorized, permitted facility. All disposal of universal waste must be manifested and signed by a representative from NAVFAC MIDLANT Environmental Services.

7.1.1 Prior to performing any work, the Contractor shall properly secure and de-energize all electrical power utilizing OSHA approved Lock Out/ Tag Out procedures as outlined in paragraph 3.7 above.

7.1.2 The Contractor shall demolish all pole mounted metal halide light fixtures at Ballfields 622, 623, and 631 (approximately 127 lights) providing new LED lights and controls. Details for each field are provided below. (See paragraph 8.1 Location Map).

7.1.3 Ballfield 622 the Contractor shall:

7.1.4 Remove and demolish (approximately 41) pole mounted metal halide light fixtures.

7.1.5 Provide and install (approximately 41) new LED light fixtures and mounting hardware in existing locations. (See paragraph 8.4 Light Specifications).

7.1.6 Remove and demolish control enclosure and all electrical components.(See paragraph 8.2 photographs)

7.1.7 Provide and install new NEMA 4x control enclosure in existing location.

SCOPE OF WORK 17 April 2026 Page 6 of 22

7.1.8 Provide and install new control components (control transformer, timed relay, lighting contactor, on/off switch and photo cell) in new NEMA 4x control enclosure.

7.1.9 Timed relay function shall be off delay with adjustable timing range of 0.1-10.0 HRS. (See paragraph 8.3 control diagram). Set range to 10 hours.

7.1.10 The photo cell shall control power source to on/off switch ensuring lights are off during day.

7.1.11 The Contractor must verify all light fixture and material counts before ordering.

7.2 Ballfield 623 the Contractor shall:

7.2.1 Remove and demolish existing Osprey nest in accordance with environmental requirements. “An inactive Osprey Nest is defined as a nest without any eggs or dependents (flightless) young and includes nest under construction. Inactive nest may be removed or relocated at any time without authorization or consultation”.

7.2.2 Remove and demolish (approximately 38) pole mounted metal halide light fixtures.

7.2.3 Provide and install (approximately 38) new LED light fixtures and mounting hardware in existing locations. (See paragraph 8.4 Light Specifications)

7.2.4 Remove and demolish existing 277/480 volt panel and control components.(See paragraph 8.2 photographs)

7.2.5 Provide and install new NEMA 4x enclosure to house new 277/480 volt panel and control components (control transformer, timed relay, lighting contactor, on/off switch and photo cell) in existing location.

7.2.6 Timed relay function shall be off delay with adjustable timing range of 0.1-10.0 HRS. (See

7.2.7 The photo cell shall control power source to on/off switch ensuring lights are off during day.

7.2.8 Existing score board controller must be reinstalled to side of new NEMA 4x enclosure.

7.2.9 The Contractor must verify all light fixture and material counts before ordering.

7.3 Running Track 624 the Contractor shall:

7.3.1 Provide and install new LED lights on 2 light poles that were not accounted for on previous

Contract.(approximately 4 LED lights) (See paragraph 8.2 photographs) (See paragraph 8.4 Lighting Specifications)

7.3.2 Provide and install photo cell in control enclosure ( 2 locations) to control power source for on/off switch ensuring lights are off during day.(See paragraph 8.2 photographs)

7.3.3 The Contractor must verify all light fixture and material counts before ordering.

SCOPE OF WORK 17 April 2026 Page 7 of 22

7.4 Ballfield 631 the Contractor shall:

7.4.1 Remove and demolish (approximately 48) pole mounted metal halide light fixtures.

7.4.2 Provide and install (approximately 48) new LED light fixtures and mounting hardware in existing locations. (See paragraph 8.4 Light Specifications).

7.4.3 Remove and demolish existing 277/480 volt panel and control components.(See paragraph 8.2 photographs)

7.4.4 Provide and install new NEMA 4x enclosure to house new 277/480 volt panel and control components (control transformer, timed relay, lighting contactor, on/off switch and photo cell) in existing location.

7.4.5 Timed relay function shall be off delay with adjustable timing range of 0.1-10.0 HRS. (See

7.4.6 The photo cell shall control power source to on/off switch ensuring lights are off during day.

7.4.7 Repair broken ridged conduit entering ground from this panel location.(See paragraph 8.2 photographs)

7.4.8 The Contractor must verify all light fixture and material counts before ordering.

7.5 All information here-in is for reference only. The Contractor must FIELD VERIFY all existing conditions, prior to fabrication and placing orders for any new items/equipment within this

SOW.

7.6 The Contractor must dispose of all existing demolished/removed materials off base and will completely clean up job site after work is performed. Maintain daily site clean-up at the end of every workday during the entirety of the construction period, to prevent any hazard potential. Disposal must be in accordance with all existing Local, State, Federal and NAVFAC MIDLANT EV rules and regulations.

7.7 The Contractor shall ensure all new equipment information and equipment inventory forms are delivered to the PWD Oceana.

SCOPE OF WORK 17 April 2026 Page 8 of 22

8. ATTACHMENTS (following the Scope of Work):

8.1 Location Map.

SCOPE OF WORK 17 April 2026 Page 9 of 22

8.2 Photographs.

Control Enclosure

SCOPE OF WORK 17 April 2026 Page 10 of 22

Control Components

SCOPE OF WORK 17 April 2026 Page 11 of 22

Panel and Controls

SCOPE OF WORK 17 April 2026 Page 12 of 22

623 and 631 Panels

SCOPE OF WORK 17 April 2026 Page 13 of 22

Add 3 New Lights

Replace All Lights

SCOPE OF WORK 17 April 2026 Page 14 of 22

Add 1 New Light

SCOPE OF WORK 17 April 2026 Page 15 of 22

Photo Cell Location #1

SCOPE OF WORK 17 April 2026 Page 16 of 22

Photo Cell Location #2

SCOPE OF WORK 17 April 2026 Page 17 of 22

Panel and Controls

SCOPE OF WORK 17 April 2026 Page 18 of 22

Broken Conduit

SCOPE OF WORK 17 April 2026 Page 19 of 22

8.3 Control Diagram.

SCOPE OF WORK 17 April 2026 Page 20 of 22

8.4 Light Specifications.

SCOPE OF WORK 17 April 2026 Page 21 of 22

SCOPE OF WORK 17 April 2026 Page 22 of 22

**End of SCOPE OF WORK**

***UNCLASSIFIED***
NAS OCEANA BALLFIELDS
BALLFIELD LIGHTING
At the
Naval Air Station Oceana,
Virginia Beach, Virginia
PREPARED BY:
Work Package Developer: Paul Eli Vaughan
FEAD Contracting Officer: Tanya Corcoran, (757) 433-2668
FEAD Contract Specialist in charge: TBD
2026-04-17T09:25:36-0400
CLARK.FREDERICK.A.1043499242

File details come from the government source that posted it. Updated .