Amendment 0004.pdf
PDF 245 KB Posted
- Attached to
- NSN, Q-47 DEMOLISH FISHING PIER
- Solicitation number
- N4008526R0108
About this file
This is Amendment 0004 to a federal solicitation for the demolition of a fishing pier at Naval Station Norfolk, Norfolk, Virginia (Solicitation N4008526R0108). The amendment, effective April 7, 2026, was issued by NAVFACSYSCOM Mid-Atlantic through the Facilities Engineering & Acquisition Division in Norfolk, Virginia, with the point of contact being Hailey McGinness at (757) 341-0596.
The amendment serves two primary purposes: (1) providing an amended Supplementary Instructions to Offerors document with specific updates to Contract Line Item (CLIN) AB regarding the quantification of entangled steel and cables to be manually removed by divers, with clarification that work area perimeter around the pier is acceptable based on crane and barge size rather than limited to a 30-foot perimeter; and (2) providing responses to Pre-Proposal Inquiries (PPIs) #44-47 addressing contractor questions regarding baseline bathymetric survey requirements, clarification on cubic yardage calculations for debris removal, confirmation of government pre-demolition survey data (referenced in Attachment 8C—Bathymetry Survey Data March 2025), and confirmation regarding contractor work area flexibility for equipment placement. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 2. AMENDMENT/MODIFICATION NO.
0004 04/07/2026
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSYSCOM MID-ATLANTIC
ROICC NORFOLK
FACILITIES ENGINEERING & ACQ DIV
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N4008526R0108
9B. DATED (SEE ITEM 11)
03/09/2026
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N4008526R0108; Q-47 DEMOLISH FISHING PIER, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA
See Continuation Page
Contact POC: Hailey McGinness (757) 341-0596; hailey.m.mcginness.civ@us.navy.mil
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:hailey.m.mcginness.civ@us.navy.mil
SECTION SF30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT 0004
The purpose of this amendment is to:
1. Provide amended Supplementary Instructions to Offerors document, refer specifically to CLIN AB. See UPDATED ATTACHMENT H_Supplementary Instructions to Offerors.
2. Provide Response to Pre-Proposal Inquiry (PPI) #44 - 47:
PPI # Date
Submitted
LEAVE
BLANK
Reference Question Responses Page Section Paragraph
44 In response to PPI response #7, if the government is performing a post demolition survey to verify the seafloor is clear of obstruction, please confirm that the government is also performing a pre-demolition survey to establish a baseline and confirm that there is no pre-existing debris for which the contractor could potentially be held responsible.
Refer Attach 8C _Bathymetry survey data March 2025 for Govt.
pre-demolition survey.
45 In response to PPI response #19, how is the contractor supposed to quantify 'entangled steel/cables' to be manually removed by divers in terms of cubic yards? For reference, 200 CY of steel equals1,323 tons of debris to be removed manually by divers. Please clarify.
See amended
ATTACHMENT
H_Supplementary Instructions to Offerors, CLIN AB.
Delete “near piles to be cut” and replace with “(landside)”.
46 In response to PPI response #20, please confirm that the contractor must establish the current seafloor elevation by means of a bathymetric survey.
Refer Attach 8C _Bathymetry survey data March 2025 for Govt.
pre-demolition survey.
47 In response to PPI response #30, please confirm that the contractor work area is not limited to a 30' perimeter around the pier, as our crane barge and material barge are larger.
Limited to size of crane, the barge work area perimeter around pier is acceptable.
All other terms and conditions remain unchanged.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .