Design Build – NAPS Looney Plaza Replacement, NAVAL STATION NEWPORT, NEWPORT, RI.
Solicitation number
N4008526R0014
Issued by

About this file

This Government Pre-Award Inquiry Form is for the NAS JAX EVSE Infrastructure project (Solicitation N4008526R0014), a design-build project at Naval Air Station Jacksonville. The document contains seven questions and corresponding government responses addressing specific project details, including:

The project involves removing and modifying a paver system, with approximately 600 sqft of quartz pavers to be retained along the northern and southern plaza edges. The government clarifies that newly installed processed gravel will not require pre-removal testing, but any disturbed soils beneath will need testing. The scope explicitly excludes structural foundation work and site electrical utility work. Contractors will be permitted to block access to the back doors of building 440 during construction, with the stipulation that they minimize impact on NAPS (Naval Air Patrol Station) operations. The concrete transition at the back doors will be determined during the design phase, and existing curbing may remain or be replaced based on design and Low Impact Development (LID) requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N69450-24-R-PW05

NAS JAX EVSE Infrastructure

GOVERNMENT PRE AWARD INQUIRY FORM

Section Government Responses

How is the concrete transition to be finished at the back doors of building 440?

To be determined by the DOR during design phase

Is existing curbing to remain or be replaced?

Curbing may remain or be replaced as determined by DOR to meet design/LID requirements

Will the contractor be able to block access to the doors at the back of building 440 for the duration of the project?

Contractor can block off access to back door during construction. Contractors shall keep in mind their responsibility to impact NAPS operations as minimally as possible

Solicitation: N4008526R0014, Design Build – NAPS Looney Question

No.

QUESTION

SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

GOVERNMENT PRE AWARD INQUIRY FORM

Section Government Responses No.

QUESTION

Amendment 01 Part 3 Statement of Work, 1.0 Project Description, Base Bid Item #1 states " Remove the quartz and brick paver system (made of loose laid 4" x 8" bricks 3" thick, with infill of pea stone on rubber spacers, completely, in work area. Amendment 01 PPI Question 4 Government Response states "The permeable paver system (interlocking rubber brick and grid system) and quartz pavers will be demolished within theproject area and will replaced with 4" of processed road gravel to create a temporary plaza for NAPS use." Please clarify if which statement is correct.

The paver system will be demolished with the exception of approx 600 sqft of quartz pavers along the northern and southern edge of the plaza

GOVERNMENT PRE AWARD INQUIRY FORM

Section Government Responses No.

QUESTION

If paver system is replaced with 4" of processed road gravel as per Amendendment 01 PPI Question 4 Government Response will it be assumed that all fill to be removed for new concrete placement will be clean and not contaminated, therefore no testing will be required?

Newly installed processed gravel will not have to be tested before removal. Any soils disturbed below the new gravel will need to be tested if they are disturbed

Amendment 01 Part 3 Statement of Work 6.0 Engineering Systems Requirements Lists A10 Foundations. A10 Foundation States "Work is limited to a concrete plaza installation and does not include structural foundations work. Please verify that there are no Engineering System Requirements for A10 Foundations.

There are no structural foundation work as part of this project

GOVERNMENT PRE AWARD INQUIRY FORM

Section Government Responses No.

QUESTION

Amendment 01 Part 3 Statement of Work 6.0 Engineering Systems Requirements Lists G40 Site Electrical Utilities. There is no subsection G40 Site Electrical Utilities. Please verify that there are no Engineering System Requirements for G40 Site Electrical Utilities.

There are no site electrical utility work as part of this project