USCG OPC Homeport Pier Industry Day Slides.pptx
PPTX presentation 10 MB Posted
- Attached to
- Industry Day for USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
- Solicitation number
- N4008526R0001
About this file
This file is a PowerPoint presentation for an Industry Day event for the U.S. Coast Guard Offshore Patrol Cutters (OPC) Homeport Pier project at Naval Station Newport, Rhode Island. The project involves demolishing the existing Navy Pier 1 and constructing a new 80-ft wide by 1000-ft long pier to accommodate four Offshore Patrol Cutters, with supporting utilities including electrical, telecommunications, water, and sewer systems. The planned project milestones include design completion in December/January 2025, with construction contract award targeted for September 2026 and project completion in October 2029.
The acquisition strategy involves a full and open solicitation using a Best Value Source Selection method with evaluation factors including experience, safety, past performance, small business utilization, and management approach. The project will require various environmental permits, including USACE Individual Permit, RIDEM Water Quality Certification, and NOAA Fisheries authorizations. The estimated dredging volume is approximately 12,000 cubic yards, to be completed in one dredge season. The project will include specialized infrastructure such as mooring hardware, fender systems, utility trenches, and electrical shore tie power mounds. The solicitation is being managed by NAVFAC Mid-Atlantic, with the RFP expected to be issued in February 2026 and proposals due in April 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| USCG OPC Homeport Pier Industry Day Sign In Sheet.pdf | ||
| OPC Homeport Build New Pier Industry Day Flyer.pdf | ||
| Attachment 1 - Registration Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG OCR Homeport Initiative OPC Pier NAVSTA Newport; Newport, RI
INDUSTRY DAY
4 December 2025 0900-1200
DRAFT
AGENDA
GROUND RULES
This meeting is informational and for planning purposes only.
This is not a Request For Proposal (RFP). Discussions today will not be evaluated in response to any future requests for proposals.
Do not provide the Government with proprietary information, trade secrets, or any other information deemed source selection sensitive, or information that you do not want disseminated to the public.
Effort that any contractor/entity expends on this effort is at its own time, risk, and expense.
Hold all questions until the end of the presentation.
Everything you see today is a DRAFT and is subject to change.
INDUSTRY DAY GOALS
Notify the Industry of the upcoming solicitation for the USCG OPC Pier project at Naval Station Newport; Newport, RI.
Inform Industry of the scope, timeline, and possible construction challenges for the project.
Solicit private sector input to help shape the project procurement.
WELCOME AND INTRODUCTIONS
Phil Cole, Contracting Officer, NAVFAC Mid-Atlantic Kristy Gerrek, Contract Specialist, NAVFAC Mid-Atlantic Mike Insetta, Project Manager, NAVFAC Mid-Atlantic Chris Jobe, Design Manager, NAVFAC Mid-Atlantic
Capt. Neal Armstrong, USCG FDCC Commanding Officer Frank Cole, Project Manager, USCG Wes Baker, Design Manager, USCG
Ben Baker, Project Manager, Stantec Mike Govoni, Design Manager, Stantec
PROJECT SCOPE PRESENTATION
SITE LOCATION
Pier 12
Pier 10
Pier 6
Pier 1
SITE LOCATION
Pier 12
Pier 10
Pier 6
MISSION REQUIREMENTS AND PROJECT SCOPE
Mission Requirements Demolish Existing USN Pier 1 1586-ft long by 100-ft wide - Condemned Construct New Pier 80-ft wide by 1000-ft long pier Accommodate four (4) Offshore Patrol Cutters (OPCs) Support Utilities Electrical, Telecommunications, Potable and Fire Protection Water, and Sewer Mooring Devices, Deck Fittings, Fenders Construct New Bulkhead at Section S45 South
PROJECT MILESTONES
Pier 12
Pier 10
Pier 6 Design Complete – December/January 2025 Acquisition ~6-8 months Construction Contract Award – September 2026
GENERAL ARRANGEMENT PLAN
GENERAL ARRANGEMENT SECTION
CIVIL
Discussion Topics Site Layout Bioretention Areas Utilities – Sewer, Storm, Water (Backflow Prevention)
CIVIL
Proposed Deck Elevation ~ 13.0 NAVD88 Flood Elevations – VE 16, AE 14
CIVIL – UTILITY DEMOLITION
CIVIL - GENERAL SITE PLAN
CIVIL - UTILITY AND GRADING PLAN
STORMWATER TREATMENT
Bio-retention Filter Basin RIDEM approved WQ Treatment Practice WQV Required = 3,267 CF WQV Provided = 11,100 CF
DRAFT DEPTH
CSTO Water Depth Requirements
Mooring Water Depth = 23 ft MLLW Required channel Depth = 27 ft
DREDGING
Dredging – Required beneath existing Pier 1 Water Depths between 32-40 ft MLLW Required minimum berthing depth = 23 ft MLLW Required Channel Depth = 27 ft MLLW
STRUCTURAL
Discussion Topics Cutoff Elevation for Existing Piles Deck Elevation Framing system and trenches Modification of bulkhead to land abutment Fenders and Floating Fenders Special features
DEMOLITION OF EXISTING PILES
Cutoff Elevation for piles at existing pier
If Dredging is not required to meet the minimum berthing depth of 23 ft:
Cut piles 2 feet below mudline
If dredging is required to meet the minimum berthing depth of 23 ft:
Cut piles 3 feet below the minimum dredge depth
DEMOLITION OVERVIEW
Demolish existing pier and all appurtenances Partially demolish existing Bulkhead S45N at Pier Crossing Temporarily remove and reset stone breakwater at bulkhead crossing
SITE DEMOLITON PLAN
TYPICAL EXISTING PIER DEMOLTION SECTION
GENERAL ARRANGEMENT PLAN
Berthing Arrangements 4 OPC with min 100’ clearance in between and to landside 2 NSCs at outboard berths and 2 OPCs at inboard berths
PIER OVERVIEW
Structure Overview 36" concrete filled steel pipe piles Reinforced concrete beam and pile cap framing system Precast concrete deck planks with topping slab Abutment and approach slab span over bulkhead (S45N) to the pier Abutment supported by 30" steel pipe piles Pier ramps up from El. 10' at the landside to El. 13' (NAVD88)
Berthing Arrangements 4 OPC with min 100’ clearance in between and to landside 2 NSCs at outboard berths and 2 OPCs at inboard berths
Ramp limits
DECK PLAN
Two substations: Located on pier deck—inboard at North side and outboard at South side
Trenches: Longitudinal (2) and Transverse (1)
Mechanical and electrical utilities: designed to accommodate joint crossing
Expansion Joints (TOT 3): located at approximately 1/3rd points along the pier
Mechanical and electrical utilities: designed to accommodate joint cross
Four designated areas for 115-ton Cranes to operate for two in-board berths
Ramp with slope 6.7% from land to pier
TYPICAL PIER SECTION
CIP Pile Cap-Beam System (w/ precast concrete plank and CIP topping slab)-transverse section
TYPICAL LONGITUDINAL PIER SECTION
PIER STRUCTURAL SYSTEM
Deck Systems Pile Cap (5’ wide and 4’ tall during construction/6’-5” tall in service) –Beam (3’ wide and 4’ tall during construction/6’-5”tall in service) w/ framing system Precast plank (1’-6” thick) with CIP topping slab (max 11" thick):
Duct banks to be designed at part of pier framing system Utility Trenches Installed longitudinally along the North and South sides of the Pier (clearance: 3’-0”H throughout, and 2’-6”V at pile cap / 3’-6” elsewhere)
Designed as structural components and goes thru bollard on top of pile caps in between bents
Lateral trench near landside to convey utility from south side to the north
MOORING AND BERTHING
Mooring Type IIB w/ Risk Category III: 113 kn wind, 2.4ft wave, and 2kn current 8- Double Braded Polyester Mooring Lines (49 kips single part break strength) for each Cutter Berthing: 0.8 fps app. velocity, 15° app. Angle, Accidental Berthing Factor 0.5 6 floating fenders per Cutter and Total 24
MOORING ARRANGEMENT PLAN
PIER FEATURES
Special Features:
Mooring Hardware Single-Bitt 125-ton bollards (Total 64) with one mooring line/bollard Max. spacing 50’ O.C. and located on top of pile cap with utility trench running below
Fender System Foam-filled floating fenders: 8 feet DIA, 16’ long Polymeric Fender Piles with H-Pile Extensions Reinforced Fiberglass Chocks and Wales Arch Type Rubber Fenders
PIER FEATURES (CONT’)
Special Features (cont.):
Utility Trench at landing (Top EL 10’ feet)
Utility pipes are conveyed from landside to pier side at the south side thru duct banks and utility trench Bent line 0 to be sealed with head wall to sleeve thru
Supported on 30” DIA steel pipe pile and integrated with abutment pile cap
One conflicting tie rod form S45N under abutment pile cap is to be encapsulated in closed-cell foam all around under utility trench
PIER FEATURES
Special Features:
Abutment Top EL. 10.0 ft.
With 5 ft. x~5.5 ft. pile cap supported on 6, 30 in. DIA concrete-filled steel pipe piles as foundation
Replaceable approach slab to be supported at grade and on abutment
Special Features (cont.):
Modifications to Existing S45N bulkhead
Steel sheet piles are to be cut down to EL 4.00 for abutment and electrical duck banks to go through bulkhead
Sheet pile will be repaired to EL 5.00 below framing beams/duct banks and EL 7.00 below precast planks
Special Features (cont.):
Modifications to S45N bulkhead (cont.)
Demolished concrete head wall will be restored to EL 7.00
Special Features (cont.):
Air Compressor Enclosure
Supported on concrete footings on 8 H piles
AC enclosure to be installed on braced steel framing with TOS EL 18 ft.
BULKHEAD S45 SOUTH PLAN AND SECTION
Bulkhead Features Replaces Existing Rip Rap Revetment Continuous Steel Sheet Pile Wall Tied back to Steel Sheet Pile Deadman Connects Bulkhead S50 and S45N
GEOTECHNICAL
Geotechnical Site Investigation Performed in 2024 Two (2) land borings: HA24-LB1&2 Seven (7) water borings: HA24-WB01-7 Site Class DE to E for the pier.
Not susceptible to liquefaction
Ground Profile along the Pier Ground Profile at the Bulkhead
Pier Pipe Piles 6-in dia. concrete-filled steel open-ended pipe piles driven to capacity into weathered rock Challenges include dealing with obstructions during pile foundation installation (i.e., fill obstructions, pile obstructions, other dumped material obstructions, natural boulders and cobbles in subsoils) Driven into weathered rock: deeper of the axial capacity and lateral fixity Bid Length: 10’ added to estimated minimum pile lengths to account for variability in the top of weathered rock
Fender Piles Upper 16” dia. with 0.5” thick wall fiberglass section Lower HP10x42 section Driven into glacial till / weathered rock: deeper of the axial capacity and lateral fixity Bid Length: 10’ added to estimated minimum pile lengths to account for variability in the top of weathered rock
Pile Driving Analyzer (PDA) Tests 5 pier piles 3 fender piles
Bulkhead Steel sheet pile wall connected to a continuous steel sheet pile deadman anchor via steel tie rods located approximately 7.5 feet on center.
Both the proposed bulkhead wall and deadman anchor consist of PZ35 steel sheet piles.
The proposed deadman anchors will be located approximately 44 ft behind the sheet pile wall.
The proposed tie rods are planned to be located at approximately El. 3.0 (NAVD 88) which is approximately 1.4 ft above Mean High Water
MECHANICAL UTILITIES
Discussion Topics Potable Water Sanitary Sewer Low Pressure Compressed Air (Option)
MECHANICAL UTILITIES – PIER PARTIAL PLAN LAYOUT (WEST)
MECHANICAL UTILITIES – PIER PARTIAL PLAN LAYOUT (EAST)
MECHANICAL UTILITIES – ELEVATION
Enclosed in Trench:
10" FW
Increased from 4" FW
2" CA
Exposed Outside of Pier
4" SSFM
SSFM relocated from below pier to side of pier.
Heat Trace Requirements:
Fresh Water Sanitary Sewer
MECHANICAL UTILITIES - TRENCH
UTILITY TRENCH – ISOLATION VALVE
UTILITY TRENCH – FIRE HYDRANT
UTILITY TRENCH – SERVICE STATION
10 in. FW W/ Heat Trace & Insulation 10 in. FW Butterfly valve w/ low point drains.
3 in. FW W/ Heat Trace & Insulation 3 in. FW Gate valve.
2 in. CA 2 in. CA Ball valve w/ low point blowdown drain.
Dry-Barrel Fire Hydrant 6 in. Inlet
(2) 2-½ in. Hose Connections
Combination Heated Enclosure Dual Sanitary In-line Pumps 4 in. Sanitary Emergency backup connection** San. Pump VFD controls enclosure
(4) CA Quick Connect Outlet w/ Ball valves
(1) FW w/ water meter and bypass.
(2) Reduced Pressure Zone (RPZ)
MECHANICAL UTILITY CONNECTIONS
SERVICE STATIONS:
Compressed Air (Low Pressure):
(1) 2 in. CA riser
(4) ¾ in. CA outlets
Sanitary (Forced Main):
(1) 4 in. FMSS w/ Camlock connection
(1) In-line Sanitary Pump Duplex w/ VFD
(1) 4 in. FMSS Emergency backup connection
Potable (Fresh) Water:
(1) 3 in. FW riser
(2) 1 ½ in. FW outlets w/ RPZ
Utility Enclosure 316L SS Insulated Panel Electrically Heated 120 mph wind rated 100 lb/sf rated Freeze Protection Monitoring
SANITARY PUMP
Duplex Direct Inline Pump Wet well not required Inlet/Outlet connections adjustable Pump operation in Primary / Secondary Pump Pressor Sensor Control:
Activates once fluid/sewage detected Measures inlet fluid height.
Communicate with control panel to maintain inlet pressure.
VFD modulates to maintain inlet pressure and optimize operation based on system backpressure and inlet pressure.
Pump shutdown when fluid is not detected.
Control Enclosure NEMA 4X with VFDs and HMI Interface
COMPRESSED AIR ENCLOSURE
PACKAGED COMPRESSED AIR ENCLOSURE (BID OPTION)
Prefabricated Enclosure with Equipment Industrial Grade Air with -40°F dp. (ISO Class 2.2.1) Physical: 33'L x 10'Wx 10'-6"H, 34,000 lbs.
Access Panels for Equipment Maintenance ( 4 Panels ) Equipment:
(2) Rotary Screw Compressors (236 scfm), 50HP (N+1 Redundancy)
(2) Vertical storage wet/dry tanks (400 gal.)
(2) Heatless Desiccant Dryers (260 scfm) w/ filter package (N+1 Redundancy)
(1) Oil-water separator Single point connection (480V disconnect)
FIRE PROTECTION & LIFE SAFETY
Fire Lane Fire Water Distribution
FIRE LANE
Down middle of the pier Total Width = 20-ft.
15-ft. unobstructed 2.5-ft. dual-use (cranes) buffer on each side Vertical clearance ≥ 13.5-ft.
Turning radius requirements Inside ≥ 25 ft.
Outside ≥ 50 ft.
Angle of approach ≤ 8°
FIRE PROTECTION WATER SUPPLY
Combined Fresh Water Supply System Fire hydrants spaced at maximum 300-ft. intervals along both side of pier 10-in. looped main Standard fire hydrants with two 2½-in. and one 4½-in. outlet Sized to deliver 2,000 GPM at 20 PSI residual pressure
ELECTRICAL
Overall Scope Electrical Utilities Locations
ELECTRICAL – OVERALL SCOPE
Landside:
15kV Feeders, Communications, Alarms & Metering Feeders in ductbank from site to Pier. Connections of feeders to existing systems.
15kV Pad-Mounted Switches on elevated structure 15kV Circuit Breaker in Substation 1
Pier:
(2) Elevated pre-engineered electrical equipment enclosures with 2000KVA secondary unit substations, distribution panels, communications enclosures and miscellaneous equipment. Enclosures located on top of utility vaults.
(4) Electrical Shore Tie Power Mounds, each with shore (ungrounded) power, industrial (grounded) power, and communications receptacles.
High Mast Lighting Poles Industrial Power to mechanical and civil utility equipment and systems Grounding & Lightning Protection Cathodic Protection
ELECTRICAL – SITE PLAN – OVERALL
ELECTRICAL – PIER LAYOUT PLAN - WEST
ELECTRICAL – PIER LAYOUT PLAN - EAST
ENVIRONMENTAL
Required Permits and Approvals Dredging and Dredge Management In-Water Work Environmental Considerations Landside Work Environmental Considerations Eelgrass Mitigation and Planning
ENVIRONMENTAL – PERMITS AND APPROVALS
Required Permits and Approvals Government-Obtained Permits USACE Individual Permit (Sections 404/10) RIDEM Water Quality Certification (Section 401) RIDEM Dredging RICRMC Coastal Consistency Determination RISHPO Memorandum of Agreement NOAA Fisheries Letter of Authorization
Contractor-Obtained Permits RIPDES General Permit RIDEM Remediation General Permit
ENVIRONMENTAL – PERMIT APPLICATIONS/CONSULTATIONS
KEY UPDATES
NOAA Fisheries will be issuing two one-year IHAs to Project rather than a single LOA Conceptual approval given from upland landfill for dredged material disposal (requirement of RIDEM permitting) Agency consultations under ESA and EFH ongoing. Recent inquires for additional details on proposed dredging activities.
Section 106 consultation ongoing. Planned mitigation for adverse affects may include display at NAVSTA Newport museum, onsite near Pier 1, or digital content on SHPO website.
Eelgrass impacts and planned mitigation to be discussed later
DREDGING AND DREDGE MANAGEMENT -
ENVIRONMENTAL CONSIDERATIONS
KEY INFORMATION
Estimate of ~12,000 cy of material (with 2’ overdredge) To be completed during one dredge season (October 15 to January 31) Turbidity curtains in place and monitoring during dredging (and all in-water work).
Material has been conceptually approved for upland disposal at RIRRC landfill, but re-testing expected Preferred approach is decanting on barge/scow and transport to dedicated upland management area for further handling and offsite disposal Barge based handling is alternative approach if upland space is limited
IN-WATER ENVIRONMENTAL CONSIDERATIONS
KEY INFORMATION
Turbidity curtains in place for all in-water work Avoidance of dredging/spudding over ancient submerged landform features (from May 2025 study) Marine mammal observers (PSOs) required for in-water sound producing activities.
Water quality protective measures for Project vessels and barges/scows
LANDSIDE ENVIRONMENTAL CONSIDERATIONS
KEY INFORMATION
Additional PCB testing on existing Pier 1 planned (Winter 2025) Erosion and sediment controls required Land Use Controls in place (CERCLA Site 19) Excavated soils to be characterized, transported, and disposed offsite. No reuse onsite Contractor to handle construction waters, in accordance with RIDEM remediation permit or dispose offsite (including testing and treatment as needed) PFAS expected. Contractor to test for and detail management considerations Coordinate handling and disposal with NAVSTA
EELGRASS MITIGATION AND PLANNING
KEY INFORMATION
0.07-acre (2,918 sf) footprint near S45S Bulkhead Contractor allowed spud construction barges in area for S45S Bulkhead construction but no additional impacts Project will provide mitigation payment into Massachusetts In-Lieu Fee Program Exact mitigation cost amount is still TBD Construction documents will require Contractor to make payment to regulatory agency
Rendering / BIM Model
PROJECT SCHEDULE
| TASK | PLANNED DATE | ||||
| Issue RFP | February 2026 | ||||
| Site Visit | March 2026 | ||||
| Proposals Due | April 2026 | ||||
| Contract Award | September 2026 | ||||
| Construction Complete | October 2029 (1000 cal days) |
ACQUISITION STRATEGY
Full and Open Solicitation
Best Value Source Selection (BVSS) with Tradeoffs
- Experience Factor
- Safety Factor
- Past Performance Factor
- Small Business Utilization Factor
- Management Approach and Schedule Factor Project Labor Agreement To Be Determined
ANY QUESTIONS?
Any additional questions can be submitted in writing to: philip.j.cole.civ@us.navy.mil image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.png image7.jpeg image8.png image9.png image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.jpeg image15.png image16.png image17.png image18.png image19.png image20.png image21.jpeg image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.png image52.png image53.png image54.png image55.jpeg image56.png image57.png image58.png image59.png image60.png image61.png image62.png image63.png image64.png image65.png image66.png image67.png image68.png image69.png image70.png image71.png image72.jpeg image73.png image74.png image75.png image76.png image77.png image78.png image79.png image80.png image81.png image82.png image83.png image84.png image85.png image86.jpeg image87.png image88.png image89.png image90.png image91.jpeg image92.png image93.emf image94.png image95.jpeg image96.jpeg image97.jpeg image98.jpeg image99.png image1.jpeg