Amendment 0003 26B0010.pdf
PDF 349 KB Posted
- Attached to
- FRCE: Site Prep for Ultrasonic Degreaser B133
- Solicitation number
- N4008526B0010
About this file
This is Amendment 0003 to a federal solicitation for site preparation work involving an ultrasonic degreaser at Building B133, Marine Corps Air Station Cherry Point, North Carolina. The solicitation is identified as N4008526B0010 and was issued by FEAD Cherry Point (Code N40085) located in Cherry Point, NC 28533. The amendment, effective June 2, 2026, provides government responses to pre-proposal inquiries (PPIs) submitted by potential offerors. The proposal due date remains June 8, 2026 at 12:00 P.M., and offerors must acknowledge receipt of this amendment prior to submission.
The amendment addresses one pre-proposal inquiry (PPI #15) submitted on May 28, 2026 regarding secondary containment requirements for the concrete pit that will house trans-dichloroethylene-based engineered solvents. The government clarified that concrete pit surfaces must be finished with a coating resistant to these engineered solvents, with coating application conforming to manufacturer recommendations. Product data and application instructions must be submitted for government approval. The amendment also references a related project (7520568) concerning repair of a leaking water tube in a boiler located in Building 152. Contractors must acknowledge receipt of this amendment by one of three methods: completing and returning items 8 and 15, acknowledging receipt on each copy of the offer, or submitting a separate letter or telegram referencing the solicitation and amendment numbers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002 26B0010.pdf | ||
| Amendment 0001 26B0010.pdf | ||
| N4008526B0010.pdf | ||
| 7357358 SpecsAsOne.pdf | ||
| 7357358 DrawingsAsOne.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0003 06/02/2026
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
FEAD CHERRY POINT
PSC BOX 8006
CHERRY POINT, NC 28533
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION
9B. DATED (SEE ITEM 11)
AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N4008526B0010 Site Prep Ultrasonic Degreaser, B133, Marine Corps Air Station Cherry Point, NC
This Amendment is being issued to provide responses to the pre-proposal inquires (PPIs).
See Continuation Pages
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
Project 7520568 Repair Leaking Water Tube#2 Boiler Building 152
N4008526B0010
The proposal due date remains June 8, 2026 at 1200 P.M.
Site Prep UltrDegreaser B133 Amendment 0003 26B0010
Block 14. DESCEIPTION OF AMENDMENT (cont.)
A. This amendment provides responses to the following PPI(s):
PPI
DATE
SUBMITTED
REFERENCE
QUESTION GOVERNMENT RESPONSE
PAGE SECTION PARAGRAPH
15 5/28/2026
Secondary containment is addressed in the plans and specs for this project. Due to the chemicals that will be housed in the pit, a secondary containment system will be required to address environmental concerns. For concrete pits, a coating system can be used to satisfy this requirement. Division 09 only addresses coating damage repairs and in-floor coating systems. Can the DOR please clarify which secondary containment system is required?
Concrete pit’s surfaces must be finished with a coating resistant to trans-dichloroethylene-based engineered solvents. Coating application must conform to manufacturer’s recommendations.
Product data and application instruction must be submitted for Government approval