Amendment 0002 26B0010.pdf

PDF 1 MB Posted

Attached to
FRCE: Site Prep for Ultrasonic Degreaser B133
Solicitation number
N4008526B0010
Issued by

About this file

This is Amendment 0002 to Solicitation N4008526B0010 for Site Prep Ultrasonic Degreaser at Building B133, Marine Corps Air Station Cherry Point, NC, issued by FEAD Cherry Point on May 26, 2026. The amendment provides government responses to six pre-proposal inquiries (PPIs) submitted on April 13, 2026, and updates the proposal due date to June 8, 2026 at 12:00 P.M. Offerors must acknowledge receipt of this amendment prior to proposal submission.

The government responses address technical clarifications across multiple specification sections and drawings. Key clarifications include: Schedule 40 black carbon steel pipe is preferred for the chilled water system over Type L copper; a cast-in-place concrete vault is acceptable as an alternative to precast, subject to professional engineer stamping and compliance with 10,000 lb wheel load and buoyancy design criteria; the existing roofing system is Soprema Modified bitumen; clear distances for equipment installation are 90 inches with stairs and 120 inches without stairs; building ceiling height is 294 inches; FRP grating is required for both the elevated platform walking surface and stair treads using 1.5-inch thick I-Bar grating (I-4015 series) with 100 PSF minimum load capacity, mechanically fastened; handrails and top rails must be minimum 1-1/2 inch nominal diameter steel pipe per OSHA 29 CFR 1926; the concrete vault must be watertight to prevent groundwater infiltration and solvent exfiltration, with watertight design delegated to the manufacturer subject to government approval; and stair railings should be identified as Keynote #5 rather than #4. The amendment includes structural floor plan drawings, concrete vault and slab-on-grade section details, and photographs showing the building access path and stair grating configuration.

View the file

Other files

File Type Posted
Amendment 0003 26B0010.pdf PDF
Amendment 0001 26B0010.pdf PDF
N4008526B0010.pdf PDF
7357358 SpecsAsOne.pdf PDF
7357358 DrawingsAsOne.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0002 05/26/2026

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

FEAD CHERRY POINT

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008526B0010 Site Prep Ultrasonic Degreaser, B133, Marine Corps Air Station Cherry Point, NC

This Amendment is being issued to provide responses to the pre-proposal inquires (PPIs).

See Continuation Pages

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

Project 7520568 Repair Leaking Water Tube#2 Boiler Building 152

N4008526B0010

The proposal due date has been updated to June 8, 2026 at 1200 P.M.

PPI

DATE

SUBMITTED QUESTION GOVERNMENT RESPONSE

SECTION PARAGRAPH

1 4/13/2026

23 64 26 Chilled, Chilled-hot and condenser water piping system

2.2 Steel Piping

Steel piping it states water piping shall be steel pipe or copper tubing. Provide steel piping with an ANSI/ASME Class 125 service rating, which for 150 degrees F, the pressure rating is 175 psig. This section further discusses typical installation methods related to steel pipe.

Will type "L" copper pipe and fittings be an acceptable material to install for the chilled water system or is sch. 40 black carbon steel pipe preferred?

sch. 40 black carbon steel pipe is preferred. (RV)

2 4/13/2026

The precast vault is estimated to exceed 9 tons, which would require a specially designed lifting and handling system for safe installation. Its installation would also restrict the existing vehicle traffic lane within Building 133. Given the size and weight of the proposed precast vault, please advise whether a cast-in-place alternative would be acceptable in lieu of a precast unit. A cast-in-place vault could be constructed with appropriate waterstop at the wall-to-slab interface to ensure proper sealing. (See Sheet 2)

Yes, a cast-in-place vault is an acceptable alternative to a precast unit. The design must be stamped by a registered Professional Engineer and submitted. The design must meet all performance criteria, including the 10,000 lb wheel load, and buoyancy resistance (assuming water table at finished floor elevation). Assume equipment operating load of 8000 lbs.(WP).

3 4/13/2026 Drawing Sheet 2 (G- 002)

Note 10

What roofing manufacturer is currently installed on Building 133?

Who was the roofing contractor that installed the existing roofing system?

The roofing system is a Soprema Modified bitumen. The platform and roof penetration are both existing. The roof penetration should follow the roof manufacturer’s requirements in order to make a weathertight seal.

4 4/13/2026

During the site visit, it was observed that the path used to enter and exit the building through the roll-up door narrows at the location of the existing vapor degreaser and an adjacent building column. Can the Government provide the measured clear distance between these two fixed structures to assist in determining the method for installing the precast vault and vapor degreaser? Can photographs of this area be provided for clarification?

The stairs can be taken off if needed when moving items through the path.

Distance with stairs: 90 inches Distance without stairs: 120 inches

Pictures provided on Sheet 3.

5 4/13/2026 Please confirm the overall building height. Height to ceiling: 294 inches

6 4/13/2026 Drawing Sheet 11 A-

Detail C3 Stair Detail Keynote #4

Basket Provided with Ultrasonic Cleaning System.” The keynote arrows appear to reference the stair railing.

Please confirm whether this is correct.

If not, should the stair railing instead be identified under Keynote #5?

Stairs should be identified as Keynote #5.

Site Prep UltrDegreaser B133 Amendment 0002 26B0010

Block 14. DESCEIPTION OF AMENDMENT (cont.)

A. This amendment provides responses to the following PPI(s):

7 4/13/2026

06 73 01 Fiberglass Reinforced Plastic Grating

The Submittal Register lists FRP Garting and Clips/Anchorage.

Please confirm whether grating is required only at the stair treads, or if the elevated platform walking surface is also intended to be grating.

Grating is required for both the elevated platform walking surface and the stair treads, refer to A-101 Note #4 (RV).

8 4/13/2026

06 73 01 Fiberglass Reinforced Plastic Grating

The specifications reference performance criteria and testing requirements but do not appear to identify a specific grating thickness, bar depth, or panel configuration.

Please confirm the grating size is required for this project.

Provide 1.5-inch thick I-Bar grating (I-4015 series) as specified in Keynote #4 on Drawing S-101. The grating must meet or exceed 100PSF load requirement (RV).

9 4/13/2026

06 73 01 Fiberglass Reinforced Plastic Grating

Please confirm that grating is to be mechanically fastened (bolted/clipped), and that welded grating is not required.

Grating shall be mechanically fastened using clips and fasteners per the manufacturer's recommendations, as stated in Keynote#4 on Drawing S-101 (RV).

10 4/13/2026

05 12 00 Structural Steel and 05 51 00 Metal Stairs

Addresses steel fabrication but do not appear to identify a standard pipe size for handrails or supporting members below the platform.

Please confirm whether a standard 1.25 inch diameter steel pipe is intended for railings and/or platform support members?

No, a 1.25-inch diameter is not acceptable for handrails/guardrails. Per specification section 05 51 00 paragraph 2.4.11, steel pipe must conform to Grade B Schedule 40. To comply with applicable safety codes (OSHA 29 CFR 1926) handrails and top rails must be a minimum of 1-1/2 inch nominal diameter. Platform support members must be as shown on structural drawings (RV).

11 4/13/2026 Drawing Sheet S-502

Pg. 7 Detail A-

Design Load Requirements-Note 1 indicates that the concrete vault is to be “heavy duty traffic load rated” Please provide the minimum and maximum design load criteria (e.g., vehicle type, wheel load, axle load, H-rating , or other governing standard) that the vault walls and bottom slab are required to withstand.

Delegated vault design must account for lateral earth pressure from a minimum 10,000 lb concentrated wheel load (forklift) and support the operating weight of the equipment (8000 lbs).

Design must also account for Buouancy to resist flotation assuming groundwater table reaches the finished floor elevation (RV).

12 4/13/2026 Drawing Sheet S-502

Pg. 7 Detail A-

Watertight Requirement-Please confirm whether the concrete vault is required to be watertight.

Yes, the concrete vault is required to be watertight, design must prevent groundwater infiltration and solvent exfiltration (RV).

13 4/13/2026 Drawing Sheet S-502

Pg. 7 Detail A-

Watertight Coating or System-If a watertight condition is required: Please clarify whether a specific coating, liner, membrane, or treatment is required by the Government to achieve watertightness, or if watertightness may be achieved by manufacturer’s standard design, subject to Government approval.

A specific, prescriptive watertight coating or system is not mandated by contract and rather delegated to manufacturer design responsibility.

Submittal must prove the system's ability to resist hydrostatic pressure with groundwater table at the finished floor elevation (RV).

Site Prep UltrDegreaser B133 Amendment 0002 26B0010