This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Geiger Quads G520 DOAS Replacement Project (Project No. 25-0078). The amendment is issued by NAVFAC Mid-Atlantic Resident Officer in Charge of Construction, with Amendment No. 0004 effective on 09/08/25. The solicitation number is N40085-25-R-9027, dated 08/21/25.

The amendment includes a clarification in response to a contractor's question about duct work replacement. The government's answer specifies that only enough duct work should be replaced to reconnect new units, and the new duct must be compatible with existing duct. The time and date for receipt of proposals remains unchanged, and contractors are advised that failure to acknowledge this amendment may constitute grounds for proposal rejection. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-25-R-9027 Amendment 0004

CONTINUATION SHEET

1. QUESTION: Is it the intent of the government to replace all the duct work, or just enough to reconnect to the new units. On page M101 Key Nots 1 & 2 are not clear what is and how much duct work is to be replaced.

ANSWER: Only replace enough duct to reconnect the new units. New duct must be compatible with existing duct.

2. All other terms and conditions remain unchanged.