This document is an Amendment (Standard Form 30) for Solicitation Number N40085-25-R-9000 for Mechanical Repairs in Building 54 at Camp Lejeune. Amendment 0002 addresses two contractor questions and extends the proposal submission deadline to 15 July 2025 at 1400 hours.
The amendment provides specific clarifications about temporary power requirements for portable HVAC units, including that dedicated temporary circuits must be provided, wall-mounted receptacles shall be installed and later demolished after air handler startup. Additionally, the amendment confirms that refrigerant lines will be routed through the attic, with attic access located in mechanical rooms 1 and 2. The solicitation remains restricted to only Mechanical MACC Contractors listed on the General Requirements cover page, with the opportunity issued by the Department of the Navy Naval Facilities Engineering Command (NAVFAC) Mid-Atlantic Resident Officer in Charge of Construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0001.pdf | ||
| 24-0004 SOW.pdf | ||
| RFP 240004.pdf | ||
| N4008524B0004 Specs.pdf | ||
| N4008524B0004 Dwgs.pdf | ||
| 24-0004 ACM Report.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 2
AMENDMENT NO. 0002 7/8/25 24-0004
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107 A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-25-R-9000
6/5/24
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
24-0004, Mechanical Repairs Bldg 54 Amendment 0002, Answer Requests for information
The time and date for receipt of proposals has been extended to 15 July 2025 at 1400 hours.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
X
N40085-25-R-9000 Amendment 0002
CONTINUATION SHEET
1. QUESTION: Sheet E-103 notes 1-3 call to run power for temp units? Can the units be plugged into an existing receptacle? If not and the power is to be ran as shown, is it to be demoed at the end of the project?
ANSWER: Dedicated temporary circuits shall be provided for the portable HVAC units.
Receptacles shall be wall mounted and demoed after completion of air handler startup.
2. QUESTION: Can As Built drawings be provided for the project? The routing of the refrigerant lines and electrical isn’t clear, we are unsure if the run between a false ceiling or in the attic. Also, are they above hard ceilings or acoustical ceilings? We weren’t able to determine this during our site visit.
ANSWER: The refrigerant lines are routed through the attic. Attic access is located in mechanical rooms 1 and 2.
3. The date and time for receipt of proposals has been extended to 15 July 2025 at 1400 hours.
4. All other terms and conditions remain unchanged.
File details come from the government source that posted it. Updated .