This document is a Standard Form 30 Amendment to Solicitation N40085-25-R-1001 for the Pier 11 Power Upgrade project at Naval Station Norfolk, Virginia. Amendment 0002 extends the proposal due date to Wednesday, August 27, 2025 at 1400 EDT and includes several key changes: updates to the Scope of Work and Drawings, revised General Requirements, a Site Visit Log, and responses to Pre-Proposal Inquiries (PPIs). The amendment specifically addresses design revisions, drawing updates for NAVFAC Drawing Nos. 4523395-4523466, and clarifies technical details such as cable replacement, electrical manholes, and existing infrastructure configurations. The project is administered by NAVFACSYSCOM MID-ATLANTIC and involves power infrastructure upgrades for CVN-78 Class Ships.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0002 08/20/25

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

NAVFACSYSCOM MID-ATLANTIC

PWD NORFOLK

FACILITIES ENGINEERING & ACQ DIV

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N40085-25-R-1001

9B. DATED (SEE ITEM 11)

08/06/2025

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008525R1001, PIER 11 POWER UPGRADE FOR CVN-78 CLASS SHIPS, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contact POC: Natalya Kuti (757) 341-0563; natalya.kuti.civ@us.navy.mil

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SECTION SF30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

AMENDMENT 0002

The purpose of this amendment is to:

1. Provide changes to Scope of Work and Drawings

2. Provide Updated General Requirements Amend.2

3. Provide Site Visit Log

4. Extend Proposal Due Date

5. Provide Responses to Pre-Proposal Inquiries (PPIs)

All other terms and conditions remain unchanged.

1. Provide Changes to Scope of Work and Drawings

See Attachment A 1749392 Executable Scope of Work

Changes include the following:

a. Change of email address for Project Manager Frances Papper

b. Design Revision 01

Change to New Work -Work Requirement, section 6.3.2.

Drawing Revisions

The following drawings are revised as of August 20th, 2025 and accompany this Design Revision:

NAVFAC Dwg. No. Title 4523395-4523466 Pier 11 Replacement

2. Provide Updated General Requirements

See Attachment Pier 11 Amend.2 Power Upgrade General Requirements REV2. Updates are in red font.

3. Provide Site Visit Log

See Attachment J – Site Visit Log

4. Extend Proposal Due Date

The proposal Due Date is extended from Monday, 25 August 2025 to Wednesday, 27August 2025 at 1400 EDT.

5. Provide Responses to PPIs #1

(End of Summary of Changes)

Page Section Paragraph Response

08/15/25 N/A N/A N/A E-102A shows a continuation to drawing E-101 but E-101 isn’t provided. Please provide E-101 Refer to Design Revision 01

08/15/25 N/A N/A N/A Please verify what cables are to be replaced down the pier? Refer to Executable Scope 6.3 g. There are no cables being replaced.

08/15/25 N/A N/A N/A Is the current one-line to remain or does the feeder from sw. 348 go direct to sw. 328? Refer to Executable Scope 6.3 g. Att 8.7 is a Partial Record Drawing

08/15/25 N/A N/A N/A Manhole 19 has a detailed butterfly but isn’t depicted anywhere else on the drawings

Manhole 19 is not a part of the project and is included as a sample in the Electrical Manhole and Inspections Report (EMIR) which is Att. 7.6 and is provided only as a example of what the EMIR should include for manhole #467.

08/15/25 N/A N/A N/A Manhole 19 has a detailed butterfly but isn’t depicted anywhere else on the drawings.

Please provide location.

Manhole 19 is not a part of the project and is included as a sample in the Electrical Manhole and Inspections Report (EMIR) which is Att. 7.6 and is provided only as a example of what the EMIR should include for manhole #467.

08/15/25 N/A N/A N/A Are the ducts from manhole 467 existing to the new SF6 pad?

Refer to Design Revision 01

08/15/25 N/A N/A N/A

KTR requesting proposal due date extension of 14 calendar days from the date of the amandment answering PPIs. Will the government grant this request? Proposal Due Date is extended until

Wednesday, August 27, 2025

08/18/25 SOW 6.2

It is unlikely we will be able to demo the concrete fill in the conduit at the existing Pad, likely resulting in a partial or full demo of the exsiting pad. Please advise how we should proceed around this obstacle. Bid as shown in Executable Scope 6.2 a

Date Submitted Question

Reference

LEAVE

BLANK

Pre-Proposal Inquiry Submission Form N4008525R0110 Pier 11 Power Upgrade for CVN-78 Class Ships

Project Location: NAVAL STATION NORFOLK, NORFOLK, VIRGINIA

File details come from the government source that posted it. Updated .