This document is a Standard Form 30 Amendment to a Naval Facilities Engineering Command (NAVFAC) Solicitation N4008525R0056 for an Indefinite-Delivery/Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for large general construction projects in the Hampton Roads Area of Responsibility (HR AOR), Virginia. The specific project involves restoring restroom and locker rooms in NMCP Building 002.

The amendment, dated 08/12/2025, requires contractors to acknowledge receipt of the amendment when submitting proposals. Failure to acknowledge the amendment may result in proposal rejection. The amendment primarily publishes revised Attachment A & B Statement of Work (SOW) specifications, with all other terms and conditions remaining unchanged. The contract is issued by NAVFAC Mid Atlantic, PWD Norfolk Naval Shipyard, Facilities Engineering & Acquisition Division, located in Portsmouth, VA.

View the file

Other files

File Type Posted
25R0056 AMD0006.pdf PDF
25R0056-AMD0005.pdf PDF
25R0056 AMD0004.pdf PDF
25D0056 AMD0003.pdf PDF
25R00056 AMD0002.pdf PDF
Attachment A SOW Specifications.pdf PDF
Attachment B SOW Documentation.pdf PDF
Attachment A SOW Specifications.pdf PDF
Solicitation 25R0056 General Requirements.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC SOLICITATION:

N4008525R0056

AMENDMENT NO. 0001

IMPORTANT

This amendment must be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal. If your proposal has been submitted prior to the receipt of this amendment, acknowledgment should be made by email, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgment must be received prior to the proposal due date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable)

0001 08/12/2025

6. ISSUED BY Code PRM22 7. ADMINISTERED BY (If other than item 6.) Code

NAVFAC MID ATLANTIC

PWD NORFOLK NAVAL SHIPYARD

FACILITES ENGINEERING & ACQ DIV

BLDG 492

PORTSMOUTH VA 23709

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N4008525R0056

9B. DATED (SEE ITEM 11)

11 August 2025

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended . Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

INDEFINITE-DELIVERY/INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION

CONTRACT (MACC) FOR LARGE GENERAL CONSTRUCTION PROJECTS PRIMARILY IN THE

HAMPTON ROADS AREA OF RESPONSIBILITY (HR AOR), VIRGINIA

NMCP Building 002 Restore Restroom Locker Rooms

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SF30 BLOCK 14 CONTINUATION PAGE

This Amendment is issued to:

1. Publish revised Attachment A & B SOW specifications.

2. All remaining terms and conditions remain unchanged.