This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Naval War College (NWC) Lower Campus Exterior Repairs Phase 1 at Naval Station Newport, Rhode Island. Amendment 0002 extends the proposal due date from 28 August 2025 to 04 September 2025 and includes updates to the Wage Determination (RI20250001 08/22/2025) and original drawings for Luce Hall and Pringle Hall. The amendment also provides responses to Pre-Proposal Inquiry (PPI) questions, addressing topics such as roof access, laydown areas, contractor parking, and project start date. The work is expected to begin in spring 2026, with all submittals to be completed prior to the start of work to prevent delays. The contract is administered by NAVFACSYSCOM Mid-Atlantic Contracting Core, with the solicitation number N4008525R0038.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

N40085

SOLICITATION NO.: N4008525R0038, Naval War College (NWC) Lower Campus Exterior Repairs Phase 1, Naval Station Newport, Newport, Rhode Island

Contract POC: Leslie McGehee, leslie.m.mcgehee.civ@us.navy.mil, 757-341-1624

See Continuation Page(s)

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

See Item 6

J

N4008525R0038

1 3

08/25/2025

07/24/2025

N4008525R0038

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 – BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

This Amendment 0002 is issued to incorporate the following:

1. Provide a proposal due date extension from 28 August 2025 to 04 September 2025

2. Provide the updated Wage Determination, RI20250001 08/22/2025 (attached separately)

3. Provide the Original Drawings for Luce Hall and Pringle Hall (attached separately)

4. Provide Pre-Proposal Inquiry (PPI) responses

1. Provide a proposal due date extension from 28 August 2025 to 04 September 2025

2. Please see the separately attached updated Wage Determination labeled, General Decision Number

RI20250001 08-22-2025

3. Please see the separately attached Original Drawings for Luce Hall and Pringle Hall labeled, 25R0038 -

Original Drawings Luce Hall & Pringle Hall

4. Please see PPI responses below:

No.

Reference

Question Response Page Section Paragraph

General question- Roof access

Mahan Hall; Will we be allowed to use roof hatches at Mahan (need interior access) to get to the low roof areas to allow us to access the areas to be repointed?

Please see the response to PPI #1

General question- Roof access Luce

Hall; Is there any roof access hatches that will allow us to access the hexagon skylight for the caulking work?

There are no roof hatches or roof tie offs at

Luce Hall.

N4008525R0038

General question- Roof access and tie off locations Luce Hall;

Chimney repair and skylight work, where would there be an accessible tie off location on this roof that does not involve walking on slate roof?

Should we carry a certain dollar amount for very minimal slate repair and if so what would that dollar amount be?

There are no tie offs on the roof of Luce

Hall

General question- Laydown area;

Where will the laydown area be located?

Please see the response to PPI #2

General question- Contractor parking; Where will workers be allowed to park?

TBD - parking in the direct vicinity is limited, CTR Parking will most likely be in Hampshire Field.

General question- Start date;

because the repointing work needs to occur in temps that are consistently above 55 degrees consistently, we are assuming that this work will be allowed to start in spring of 2026, please confirm.

From past experience, we believe it will not be possible to get the award, then submittals and submittal approvals within a two month or three month period so we will miss the season this year.

Work is expected to start in the spring of

2026, all submittals are expected to be completed / accepted prior to the start of work to prevent any delays

General question- how many wythes thick is the chimney that is to be repaired at Luce Hall?

Please reference the original drawings for

Luce Hall and Pringle Hall (attached separately), there are three wythes of brick.

Based on field observations, the brick chimney at Luce Hall is approximately 1'-

4" thick. Verify chimney thickness in the field.

Please see attachment labeled:

25R0038 - Original Drawings Luce Hall &

Pringle Hall

General question- how thick are the granite facade blocks?

Based on field observations and a review of original construction drawings for

Pringle Hall, the granite is nominally 4-inches thick.