This document is a Decision Memorandum that provides information about a categorical exclusion under the National Environmental Policy Act (NEPA) for the proposed "Air Station MAT Repairs" project at Marine Corps Air Station New River.
The project scope includes removing and replacing damaged concrete, installing moisture barriers, replacing expansion trays and seals, repainting lines, replacing a catch basin, and repairing any disturbed navigation lights. The proposed action qualifies for a categorical exclusion under routine repair and maintenance activities. The Decision Memorandum documents the environmental review for the project and provides guidance on changes to the proposed action or the need for further environmental impact review. The related federal contract opportunity is a solicitation for FY24 MCAS New River MAT Repairs, which is limited to civil/paving MACC contractors under the Naval Facilities Engineering Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 23-0059 Amend 0002.pdf | ||
| 23-059 Amend 0002 Pages from 1130.1 - 32 13 14.13.31.1.D Mix Design 650 PSI - MBI.pdf | ||
| Amend 0001.pdf | ||
| 23-0059 Dwgs.pdf | ||
| 23-0059 SOW.pdf | ||
| 23-0059 Specs.pdf | ||
| 23-0059 RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES MARINE CORPS
MARINE CORPS INSTALLATIONS EAST-MARINE CORPS BASE
PSC BOX 20005
CAMP LEJEUNE NC 28542-0005
From: Director, Environmental Management Division/G-F To: Action Proponent
Subj: DECISION MEMORANDUM, CATEGORICAL EXCLUSION; AIR STATION
MAT REPAIRS, 23M048CN, (NEPA LE23071)
Ref: (a) MCO 5090.2 - V12
(b) 32 C.F.R. 775.6(e)
(c) 32 C.F.R. 775.6(f)
Encl: (1) PWD REIR of 25 Jul 23
(2) Supporting Documents
(3) Applicable Conditions
1. In response to enclosure (1), this Decision Memorandum satisfies reference (a) National Environmental Policy Act (NEPA) requirements applicable to the proposed action.
Pursuant to reference (b) planning considerations, this Decision Memorandum (DM) also documents the decision to categorically exclude (CATEX) the proposed action from the requirements of preparing an Environmental Assessment (EA) or an Environmental Impact Statement (EIS).
2. As outlined in enclosures (1) and (2), the proposed scope of the project is:
Remove damaged areas of concrete and any required substrate, replace with new concrete to required depth and compaction/ density as required. Install moisture barrier under all concrete repairs (if applicable). Replace all expansion trays and seals in the project areas on the runway. Repaint all lines disturbed by project. Replace catch basin beside Military Aircraft Tarmac 7 (MAT) at edge of Combat Aircraft Loading Area (CALA) and clear debris in catch basin downstream. Repair any navigation lights that are disturbed in project area.
3. Pursuant to subparagraph (8) of reference (c), the proposed action qualifies for the following categorical exclusion: " (8) Routine repair and maintenance of buildings, facilities, vessels, aircraft, ranges, and equipment associated with existing operations and activities. (e.g., localized pest management activities, minor erosion control measures, painting, refitting, general building/structural repair, landscaping, or grounds maintenance)." The proposed action will not result in any extraordinary circumstances.
4. In accordance with NEPA, this Decision Memorandum documents the proper level of environmental review for the proposed action to date but may not constitute authority to proceed with implementation of the project. Please see the enclosures for more
05 Sep 2023 information. If the proposed action changes or does not begin within one calendar year after the date of this Decision Memorandum, please coordinate with the Environmental Planning Program Manager at (910-451- 4542) to determine whether this Decision Memorandum continues to apply to the proposed action or whether an updated environmental impact review will be required to find that a CATEX still applies to the proposed action.
Accepted /s/ Robert A. Lowder, P.E.
Receipt Acknowledged Riggs CIV James 05 Sep 23
Enclosure 1: REIR
REQUEST FOR ENVIRONMENTAL IMPACT REVIEW
SECTION I - PROPONENT INFORMATION
Project Title: Air Station MAT Repairs
Short Plain English Description of Action: Repair multiple areas of MATs, and CALA (including some drainage around CALA) Project ID: 23M048CN
Start By Date: 15-Sep-23
End By Date: 25-Jul-25
Activity Sponsor (Unit/Command): PWD
Activity Sponsor POC: James Riggs
Phone: 252-670-2678
Activity Sponsor POC (Alternate): N/A
Phone: N/A
Base Location: New River
Project will result in permanent site improvement?: Yes
New or Modified Real Estate License Will Be Issued By Base?: N/A
Descriptive Information
Purpose and Need of Action: Numerous cracks, and chips in project areas. Some drainage issues also in need of repair.
Scope of Project (Project Narrative): Remove damaged areas of concrete and any required substrate, replace with new concrete to required depth and compaction/ density as required. Install moisture barrier under all concrete repairs (if applicable). Replace all expansion trays and seals in the project areas on the runway. Repaint all lines disturbed by project. Replace catch basin beside Military Aircraft Tarmac 7 (MAT) at edge of Combat Aircraft Loading Area (CALA) and clear debris in catch basin downstream.
Repair any navigation lights that are disturbed in project area.
Identify Other Alternatives Considered: N/A
Information concerning avoidance, specific best management practices, or mitigation necessary to complete the project: N/A
Preferred and Alternative Sites
Preferred Site Description: N/A
End of Form
Enclosure (1)
SECTION II - PRELIMINARY ENVIRONMENTAL SURVEY
a. AIR QUALITY
1. Will your project involve new equipment or modifications to existing equipment associated with the following?: Yes (Select all that apply): b. Painting
Provide proposed construction dates, equipment size, specification, and estimated types.: Will require re-painting of the runway per MCAS NR SOP.
2. Will pollution control equipment be involved (e.g. filter or incinerators)?: No
3. Was this building constructed before 1978?: No
4. Are there going to be any renovations, demolitions and/or building improvements?: Yes
b. LAND QUALITY
1. Number of acres involved? Indicate total project area and total disturbed area.:
Less than 10
2. Does the proposed action involve digging and/or grading?: Yes
3. Will the action require use of earthen fill material?: Yes
4. Will vegetation be cleared?: No
5. Will the project increase impervious area by 10,000ft squared or more?: No
6. Are there wetlands within the project area?: No
7. Will completion of the project result in a change in land use from what is presently shown in the Base Master Plan?: No
c. GROUNDWATER QUALITY
1. Does the project involve use of herbicides, insecticides, or pesticides?: No
2. Does the project involve installation/use of septic tanks, leach beds, or other on-site disposal of sanitary waste?: No
3. Will there be any wells dug or any excavation deeper than 20 feet?: No
4. Will the project generate or use any toxic or hazardous/waste materials?: Yes
5. Will there be an increase of solid waste (temporarily or permanently) caused by implementing the project/action?: Yes
6. Will the project or action be carried out within 100 to 500 feet of a drinking water supply well? If yes, provide distance to nearest drinking water well.: No
7. Does the project require the installation or removal of any petroleum or non-petroleum underground storage tank (UST)?: No
8. Are there any known Installation Restoration Program (Comprehensive Environmental Response, Compensation, and Liability Act - CERCLA or Resource Conservation Recovery Act - RCRA) sites or hazardous waste treatment, storage, and disposal (RCRA) facilities within the proposed project area: Yes
d. SURFACE WATER QUALITY
1. Is the project located on or in a water body or adjacent to or in the 100-year flood plain?: No
2. Will the project involve construction of drainage ditches/underground drains for purposes of lowering water table?: No
3. After construction is complete, will petroleum products including fuel, oil and lubricants be routinely stored or used (temporarily or permanently) at the site? : No
4. Does the project require the installation of any petroleum or non-petroleum above ground storage tank (AST)?: No
e. NATURAL RESOURCES
1. Will trees be removed?: No
Amount to be removed:: N/A
2. Will shrubs, or other low-growing vegetation be cut?: No
3. Will public access for hunting, boating, fishing, etc., be restricted?: No
4. Does the project involve the transfer (purchase, sale, lease, easement or otherwise) of any real estate interest?: No
5. Are there potential effects on any threatened or endangered species?: No
f. CULTURAL RESOURCES
1. Are there any known archaeological sites in the area of your project/action?: No
2. Are there any known historic buildings or districts affected by the project/action?:
No
3. If known, please contact the Base Archaeologist/Cultural Resources Program Manager for assistance at (910) 451-7230.:
g. UTILITIES AND SERVICES
1. Will new/modified utilities be required? Select all that apply.: N/A
If other is selected, please describe below.: N/A
h. SOCIAL ECONOMIC CONSIDERATIONS
1. Will the project cause an increase/decrease in on-base or off-base military population?: No
2. Will there be any changes to traffic flow and patterns on or off base?: No
3. Will the project cause noise or safety issues that could potentially impact off-base persons or property either during construction or from the project itself?: No
4. Will there be any increased demand on a local or state government to provide services?: No
i. GENERAL CONSIDERATIONS
1. Are alternative procedures, practices, or technologies available to minimize environmental impact or utility use?: No
2. Are there likely effects on the human environment that:: a. are highly uncertain?
Explain YES answers here:: N/A
Enclosure 2: Site Map
Figure 1: Specific Location
Figure 2: IR Program Map
Enclosure (2)
Figure 3: NC FRIS Preliminary Flood Plain Map
Enclosure (2)
Enclosure 3: Applicable Conditions
AST/UST (Land use Restrictions):
1. This site is located within a Land Use Restriction (LUR) for groundwater. Any encountered groundwater within this LUR boundary must be containerized and properly disposed of, or sampled prior to dewatering activities.
Contact:
IR Program, 910-451-9641/9610 AST/UST Program,910-451-5878
AST/UST/IR/MRP (Soil):
1. If contaminants are suspected through odors or visual observation during construction activities, immediately stop work, call 911, and contact EQB at 910-451-9641 for further instructions.
2. Existing monitoring wells are present in this area and should be protected. If they are damaged or will need to be demolished, the wells should be properly abandoned in accordance with State regulations (NCAC 15A 2C) by a State-licensed well driller.
Replacement wells will need to be installed in accordance with State regulations (NCAC 15A 2C) by a State-licensed well driller. If an unmarked well is discovered and inadvertently damaged, immediately contact EQB at 910-451-9641 for further instructions.
3. 3R UXO Safety Awareness Training is recommended for all construction workers as a precaution given that Camp Lejeune has been an active military base since the 1940s. 3R Safety Awareness Training is available online at the following link:
http://www.lejeune.marines.mil/Offices-Staff/Environmental-Mgmt/Training-Video/. Should a munitions-related item be found during construction, follow appropriate notifications as detailed in the 3R training. Any munitions related item found during project construction should additionally be reported to EMD within 10 days (T.Richard, 910-451-9641) to determine if additional evaluation and precautions are necessary (Explosives Safety Submission, UXO Tech Support, etc). Additional UXO safety resources available at: Construction - DENIX (osd.mil) https://www.denix.osd.mil/uxo/for-work-crews/construction/index.html
4. This project is partially within the Aquifer Use Control Boundary associated with IR sites 86 and 54, Operable Units (OU) 15 and 6, as well as active UST Rapid Refueler remediation site and UST site AS845 Notice of Residual Petroleum. All work conducted in an identified EPA NPL OU or RCRA SWMU must adhere to the provisions detailed in 29 CF R
1910.120 Occupational Safety and Health Standards, Hazardous Materials, Hazardous waste operations and emergency response.
***5. There is known shallow groundwater contamination (volatile organic compounds) in the vicinity of the project area associated with Installation Restoration (IR) Site 86.
Any construction activities that require digging into the groundwater will require additional safety precautions (such as 40 hour HAZWOPER training) and waste management for groundwater and saturated soils in accordance with the most current Waste Management Plan.
Enclosure (3)
***6. The project site is impacted by PFAS (per- and polyfluoroalkyl substances) in groundwater. The contractor is responsible for worker safety and education for working within areas impacted by PFAS and eliminating migration/spread of PFAS from leaving the site to the greatest extent practicable. Due to potential AFFF usage in the Airfield vicinity, all concrete must be reused on-site or disposed of at a RCRA D landfill. It is recommended that soil be left in place or at a minimum on site. Any soils removed from the site must be tested and manifested to a permitted Subtitle C or D landfill. Any dewatering activities should either assume PFAS impacts and associated proper containment and disposal, or testing to confirm presence/absence of PFAS above screening criteria. Groundwater extracted below 70ppt PFOA/PFOS combined or separate per DON 201 7, and 2020 update, Interim PFAS Guidance does not require special handling, treatment or disposal.?Groundwater extracted above the DON Guidance policy level of 70ppt PFOA/PFOS must be handled, treated and disposed per DON policy. Equipment, such as borings augers or sheet piling that comes in contact with potentially contaminated soil and groundwater should be decontaminated to prevent the spread of contamination offsite. See EMD's PFAS construction guidance for more information.
***7. There is known soil contamination (petroleum) in the vicinity of the project area associated with Installation Restoration (IR) Site 54. Any construction activities will require additional safety precautions (such as 40 hour HAZWOPER training) and waste management for soils in accordance with the most current Waste Management Plan. In addition, notification to the State and U.S. EPA is required a minimum 60 days prior to start of construction to ensure compliance with existing land use restrictions. The notification shall be done by the Installation's Environmental Management Division and coordinated via the construction contractor.
Contact:
IR Program, 910-451-9641/9610 AST/UST Program,910-451-5878
Air Quality:
1. Ensure that any fugitive dust emissions generated by construction and demolition are appropriately controlled.
Contact:
Air Quality Program, 910-451-9421/5836
ECB (Stormwater):
1. This project is a renovation. At the junction, please annotate all new SW features installed. Drop Inlets, pipes, etc. Utilize all local sedimentation and erosion plans on site.
Contact:
Stormwater Manager, 910-450-5806 (Stormwater Requirements) Public Works Design Branch, 910-451-2212 (Permit Application) Supervisor, 910-451-9657
Note 1: In accordance with MCIEAST-MCB CAMLEJO 11013.4, projects that include construction, intrusive work, or real estate actions will require site approval from G-F. Please contact Asset Management Branch (AMB) at 910-451-0982.
Note 2: The following sections reviewed the REIR, replied to it and have no concerns:
T&E, RTAM, Wildlife, Wetlands, MCAS New River, MCAS NR Safety, Water Quality and Cultural Resources.