Amendment0004_24R2737.pdf
PDF 144 KB Posted
- Attached to
- NCIS Office Renovations at CEP-177
- Solicitation number
- N4008524R2737
About this file
This document is an amendment to Solicitation N4008524R2737 for NCIS Office Renovations at CEP-177.
The key details are:
- Revised drawings and specifications have been attached, including Design Revision 02.
- The proposal due date has been extended to Tuesday, August 27, 2024 at 1400 EDT.
- Responses to pre-proposal inquiries have been provided, covering topics such as telecom cabling requirements, outlet details, and a discontinued finish product.
- The overall contract is for NCIS office renovations at facility CEP-177, to be awarded by the Naval Facilities Engineering Command.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0004 08/21/2024
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSY SCOM MID-ATLANTIC
PWD NORFOLK
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3624
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-24-R-2737
9B. DATED (SEE ITEM 11)
07/24/24
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-24-R-2737 NCIS OFFICE RENOVATIONS AT CEP-177
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Ashlee Beggs, ashlee.r.beggs.civ@us.navy.mil ,Tel: 757-341-0564 and Kathryn Arnold kathryn.l.arnold3.civ@us.navy.mil .,Tel 757-341-0554
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
N40085-24-R-2737
SF 30 BLOCK 14 CONTINUATION PAGE
The purpose of this amendment is to provide the following:
1. Provide document 1689103_Design Revision 02_COVER (Attached Separately).
2. Revise document Attachment A - CEP177_1689103_SPECS and Attachment A - 1689103_Design Revision 01_SPECS with document Attachment A - 1689103_Design Revision 02_SPECS (Attached Separately).
3. Revise document Attachment B - CEP177_1689103_DWGS and Attachment B - 1689103_Design Revision 01_DWGS with document Attachment B - 1689103_Design Revision 02_DWGS (Attached Separately).
4. Update the General Requirements to extend the proposal due date.
5. Provide responses to Pre-Proposal Inquires (PPI’s).
1. See “1689103_Design Revision 02_COVER” (Attached Separately).
2. See “Attachment A - 1689103_Design Revision 02_SPECS” (Attached Separately).
3. See “Attachment B - 1689103_Design Revision 02_DWGS” (Attached Separately).
4. Proposal Due Date: Tuesday, 27 August, 2024 at 1400 EDT.
5. Provide responses to Pre-Proposal Inquires (PPI’s).
Question No.
Reference Question Response
Page Section Paragraph
1 27 10 00 Shall the KTR perform work indicated in the T - Drawings?
Refer to Design Revision 1
2 27 10 00 Can the government provide Section 27 10 00 specifications?
Refer to Design Revision 2
3 27 10 00 Regarding Sheet TT601, A1 Telecom Riser Diagram. This diagram has room numbers that do not match the new work room numbers. Can the government provide a riser diagram that is in line with the new requirements?
Refer to Design Revision 1
4 27 10 00 Please provide cable type and colors for classified voice and data cabling.
Refer to Design Revision 1 & 2
5 27 10 00 Shall the KTR provide a separate cabinet/rack for the classified cabling? If so please specify the requirment.
Refer to Design Revision 1
6 27 10 00 Regarding Sheet TT501, detail C1 and B1. Neither detail provide classified outlet detail. Please provide.
Refer to Design Revision 2
7 27 10 00 Regarding Sheet TT501, B1 Quad Data Outlet. Which outlet locations shown on Sheet TT101 have this requirement?
Refer to Design Revision 1 & 2
8 27 10 00 Regarding Sheet TT101. Two of the classified outlets indicate a voice and data requirment. Can the government add this outlet detail on Sheet T501.
Refer to Design Revision 2
9 There is a missing panelboard schedule for Panelboard MP. May this be provived.
Refer to Design Revision 1
10 The accent wall tile (PWT2) that is listed on the finish schedule has been discontinued from the manufactor. Is there a product that can be substituted that the government would accept?
Refer to General Interior Finish Note B on drawing AF601 for clarification.
(End of Summary Changes)