SOW Amendment Repair Bldg 1103.docx
DOCX document 14 KB Posted
- Solicitation number
- N4008524R2518
About this file
This document is an amendment to the Scope of Work (SOW) for the repair of Building 1103 at Marine Corps Air Station (MCAS) Beaufort. The key details are:
The amendment requires the contractor to provide a 40-foot shipping container adjacent to the building for MCAS personnel to move and temporarily store items from Building 1103. The contractor must also demolish the existing fuel day tank/pump/stand in the generator room, demolish the exterior storage tank concrete containment, and level the soil across the site, installing silt fencing and hydroseeding the disturbed area. The work is part of the Design-Build/Design-Bid-Build, Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) for General Construction Services at MCAS Beaufort, solicitation number N4008524R2518.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 to Repair Bldg 1103 10 April 2024
Scope of Work
1. Provide one shipping ISO container 8’ x 40’ adjacent to the building for MCAS personnel to move the items stored in 1103 out of the building. PW will need periodic access to the container contents. Provide the container at least two weeks prior to construction start and 2 weeks after Beneficial Occupancy Date.
2. Demolish fuel day tank/pump/stand in generator room. See photo. Drain the tank of fuel, remove hoses cut pipes at floor level and grout pipe closed. Dispose of debris off of Government property.
3. Demolish the exterior storage tank concrete containment including the tank saddle and remove debris from Station property for disposal. Public Works will drain the standing water in the containment with 7 days notice, weather permitting.
4. Provide silt fencing around the existing berm and area that the soil will be redistributed. No soil shall be removed from the site.
5. Level the soil remaining across the site and hydroseed disturbed area. Seed shall be Bahia with Bermuda if seeded in cool season or Bermuda if seeded in the warm season.
End of SOW