PPI 2 MIG GOV DN355 answered.xlsx.pdf

PDF 9 KB Posted

Attached to
REPLACE DAHU 16 IN ROOM 211, BLDG 355, DAM NECK ANNEX
Solicitation number
N4008523R2779
Issued by

About this file

This document contains responses to questions regarding a federal solicitation for roof repair work at Building 355 at the Dam Neck Annex. The solicitation number is N4008523R2779 and is issued by the Department of the Navy Naval Facilities Engineering Command. The work requires replacing a DAHU unit in Room 211 and finishing the exposed drywall ceiling to match the existing finish, including painting. The existing roof is not under any manufacturer warranty. Bidders are to use a certified roofing manufacturer installer. The cut-off date for responses is 20 July 2023.

View the file

Other files

File Type Posted
Amendment 0004.pdf PDF
Oceana IDIQ Front End SPECS.pdf PDF
Amendment 0003.pdf PDF
Site Visit DAHU.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
DN-355 A-16.jpg JPG image
DN-355 - Roof - 1.jpg JPG image
2nd FL DN-355 - 2.jpg JPG image
2nd FL DN-355 - 1.jpg JPG image
PPI- MIG GOV 7.6.23 (003) DN-355 Replace DAHU 16 in room 211.pdf PDF
DN-355 - M6.jpg JPG image
DN-355 2nd Fl.jpg JPG image
DN-355 - M7.jpg JPG image
DN-355 - 2nd Fl.jpg JPG image
DN-355 - Roof.jpg JPG image
va167 (1).txt TXT text file
PPI Spreadsheet.xlsx XLSX spreadsheet
BLANK SPONSOR VERIFICATION SPREADSHEET.xls XLS spreadsheet
PROVISION 52.204-24.pdf PDF
SOW (W)15554116 REPLACE DAHU 16 IN ROOM 211 - DN-355.pdf PDF
SECNAV 5512.pdf PDF
BASE ACCESS INSTRUCTION.pdf PDF
GENERAL REQUIREMENTS RM 211 BLDG 355.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page Section Para. Dwg #

1 MIGGov 07/10/23 7 of 18

Work

Requirem ent

7.9

To what level of finish should the drywall ceiling be installed?

Drywall ceiling shall be fully finished, ready for paint and matching existing ceiling finish.

2 MIGGov 07/10/23 Are we to paint the new drywall ceiling? If so, can we receive information on the paint finish type?

Yes, the Contractor shall paint the new finished drywall ceiling. New ceiling paint and finish shall match the existing ceiling finish and paint type/color.

3 MIGGov 07/10/23 8 of 18

Work

Requirem ent

7.22

Is the existing roof still under a roof warranty? If so, can we receive information on which manufacturer and/or roofing subcontractor holds the roof warranty?

The existing roof is not under warranty.

Contractor shall use a Certified Manufacturer

Installer for roofing repairs.

Project Title: REPLACE DAHU 16 IN ROOM 211, BLDG 355, DAM NECK ANNEX

Solicitation / RFP#: N4008523R2779 - PPI Cut Off Date: 20 July 2023

Amend No.

GOVERNMENT RESPONSE

PPI No.

Offeror

Date

Submitted

REFERENCE

QUESTION