1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0004 02/08/2023
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-23-R-2528
9B. DATED (SEE ITEM 11)
01/05/2023
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-23-R-2528, DESIGN-BID-BUILD, FFG-62 LAND BASED ENGINEERING SITE (LBES) – EARLY DEMOLITION
PACKAGE, PHILADELPHIA NAVY YARD ANNEX, PHILADELPHIA, PENNSYLVANIA
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil
N40085-23-R-2528
SF 30 BLOCK 14 CONTINUATION PAGE
The purpose of this amendment is to provide the following:
1. Revised Pre-Proposal Inquiry (PPI) Responses
Question # Question Government Response
Drawing No.: G-003 / Note No.: 4. States:
"CONTRACTOR MUST CLEAN HAUL
VEHICLES AND TIRES OF SEDIMENT
PRIOR TO EXITING THE PROJECT SITE.
ANY SEDIMENT DEPOSITED ON PUBLIC
ROADWAYS MUST BE REMOVED
IMMEDIATELY AND RETURNED TO THE
CONSTRUCTION SITE. WASHING THE
ROADWAY OR SWEEPING DEPOSITS INTO
ROADWAY DRAINAGE COURSES IS
PROHIBITED". Can the contractor power wash tires on the inside of building before exiting the
South Overhead Door? Will a DEP Soil Erosion
Control Permit be required with the State of PA.?
Can contractor use a street sweeper for exterior to capture any residual sediment stuck on trucks?
NSWCPD Input: Soil shall be treated as regulated waste unless proven to be clean soil free of contaminants - as such, water used to clean construction vehicle tires must be collected and treated as regulated waste if the soil has not been tested and proven to be clean soil free of contaminants. In lieu of or in combination with water cleaning, mechanical cleaning of tires (e.g., brushing tires) may be considered. Given work is located inside Building 77H, a permit for this particular inquiry is not required. Street sweepers may be used as a reaction to soil that is left on the streets by vehicles but not as a primary control. If streets are soiled after other controls are used, a street sweeper is one option for cleaning up residual soil on the streets. Contractor is not allowed to store motor vehicles such as dump trucks, pick-up trucks, cars, etc. in B77H.
The area of work can be used for storage of materials, dumpsters, cranes, aerial work platforms, etc. Contractor must implement exhaust controls for motorized vehicles operated inside B77H. Use of electric or propane powered machinery is encouraged. As indicated in the specifications, doors must remain closed until they need to be opened for equipment entering or leaving the building and must be constantly monitored by authorized individuals when open; doors may not be kept in the open position unless specifically opened to accommodate vehicle/material/equipment transport through the opening. Exhaust controls and mitigation measures must be included with the Contractors accident prevention plan and must be submitted for review and approval. Controls must be OSHA and EM 385-1-1 compliant. Examples of controls include:
1. Piping exhaust to a temporary opening(s) the B77H envelope. Exhaust and/or ventilation systems must maintain a secure building envelope at all times.
2. Providing muffler scrubbers on vehicles.
3. A program to monitor the atmosphere to ensure readings do not exceed permissible exposure limits.
4. Controls to prevent accumulation of hazardous gases.
The mechanical demolition drawings request removals of piping systems throughout the site, however there is no indication regarding what specifications need to be met for the capping requirements of these piping systems. The drawing only highlights general locations where the piping is to be severed. Please advise if there are any requirements for the piping systems after demolition activities.
There is no intent to extend any of the piping systems after demolition activities are completed. The piping indicated to be capped is to be fully terminated at the points indicated. Refer to Specification Section 02 41 00
'Demolition' for additional information about demolishing piping systems
(specifically paragraph 3.1.15).
Can NSWC provide a test schedule in order to better plan the sequencing and demolition schedule?
Refer to the response to Question 4 to understand how testing operations may impact demolition work activities. A schedule will not be shared at this point in time as it does not extend to the anticipated start date of this project. Schedule details for ongoing testing will be shared (to a limited extent) with the prime contractor routinely throughout the demolition project.
Are there any special requirements for vehicles that are needed to enter the construction zone with respect to security and vetting for both operators and vehicles?
All personnel must be badged as detailed in Specification Section 01 14 00.
Refer to the same specification section for vehicle inspection requirements.
(End of Summary Changes)