AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N4008522R2681 Fire Suppression and Utility Distribution Services at NWS Earle

This amendment is issued to answ er additional inquiries and revise the specifications. See continuation page(s).

The proposal due date and time, 15 November 2022 at 2:00 PM EST remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 62

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Nov-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008522R2681

X 9B. DATED (SEE ITEM 11)

07-Oct-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Nov-2022

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008522R2681

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

This amendment is issued to:

- Incorporate responses to proposal inquires.

- Revise Section C 1502000 – Facility Investment 3.2.14.

All other terms and conditions remain unchanged.

QUESTION GOVERNMENT RESPONSE

1. On Page 67 3.2.14 Replace every other bolt on various pipes and fitting flange joints. The replacement bolts will be color coded to identify which bolts were replaced in which year. This will result in every bolt being replaced every two years. Contractor will inform the Government as to monthly progress in bolt replacement, including the number of joints serviced and the number of joints remaining.

a) Will this include removal of insulation and re-installing insulation? If so, can we reuse the insulation if it is in good condition?

b) Does this include fittings in buildings on Piers?

a.) When insulation and shielding around pipe couplings and bolts is missing, damaged, deteriorated, or cause improper function, it is a requirement to repair or install new. Bolts on valves, shut offs, connections, and similar items have blankets as the insulation and can be observed and if not damaged, deteriorated, or cause improper function, then it could be reused.

b.) The maintenance program includes replacing deteriorated, rusted out, missing, and inoperable fittings that are in the buildings pertaining to sprinkler systems, fire pumps, lift stations, control devices, etc.

See 1.1 and 3.2.14.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

ANNEX 0200000

0200000 – Management and Administration Spec Item Title 2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities

2.4.3 Government-Furnished Vehicles and Equipment

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Deliverables

2.6.7 Service Interruptions

2.6.8 NAVFAC Maximo

2.6.8.1 NAVFAC Maximo Data

2.6.8.2 NAVFAC Maximo Method of Data Entry

2.6.8.3 NAVFAC Maximo Access

2.6.8.4 NAVFAC Maximo Training

2.6.9 Quality Management System (QMS)

2.6.9.1 Quality Management (QM) Plan

2.6.9.2 Quality Inspection and Surveillance

2.6.9.3 Quality Inspection and Surveillance Report

2.6.10 Property Management Plan

2.6.11 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.2.1 Quality Control Personnel

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tagout)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Clean Air Act (CAA)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Recurring Work Preparation of Proposals

2.14.2 Notification to the Government for Work Above the Recurring Work Limitations

2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

0200000 - Management and Administration Spec Item Title Description 2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.

2.2.1.1 Observed

Federal Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.

2.2.2 Wage

Determinations

Wage Determinations are included in J-0200000-02.

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, and 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

Contractor shall attend a Pre-Performance Conference meeting. Contractor shall attend biweekly progress meeting with the Government, (FMFS Branch Manager) and shall provide agenda and meeting minutes. The contractor may be required to attend administrative and coordination meetings as directed by the KO or the FMFS Branch Manager.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors.

Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.

The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

2.3.3.1 Informal

Partnering

The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract

Partnering Administration

Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process. Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract

Partnering Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract.

Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager Site Safety and Health Officer Sub-Contractor Reps

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F before work commences and at other times as requested by the KO.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage.

Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Ensure insurance amounts are current:

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by state law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instruction and reference Invoice Form J-0200000-04 for sample.

Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version (currently 2010). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.

2.4 Government-

Furnished Items

Except for items identified below as Government-Furnished, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services described in this Performance Work Statement (PWS).

Government-Furnished Items will be provided in "AS-IS" condition and their use is at the option of the Contractor. The total or partial breakdown or failure of Government-Furnished Items shall not relieve the Contractor of the responsibility to perform the requirements of this contract.

The Contractor shall provide periodic servicing, maintenance, and repair of the Government-Furnished Items accepted for use at no additional cost to the Government.

Servicing, maintenance, and repair shall be provided in accordance with the manufacturer’s recommendations. The Contractor shall generate work orders in NAVFAC Maximo per Spec Item 2.6.8 for all servicing, maintenance, and repair activities performed on Government-Furnished Items.

At the completion of the contract, all Government-Furnished Items shall be returned to the Government in the same condition as received, except for reasonable wear and tear.

Government-Furnished Items, which becomes worn out due to normal wear and tear, shall be returned to the Government and its replacement shall be the responsibility of the Contractor at no additional cost to the Government. The Contractor shall be responsible for the cost of any repairs or replacement caused by Contractor negligence or abuse.

The Government may inspect Government-Furnished Items at any time and without notice.

2.4.1 Government-

Furnished Property (GFP)

N/A There will be no Government Furnished (GFP) made available to the Contractor upon award. If at a later time the Government finds it is in its best interest to furnish any Property, the Contract will be modified to reflect the items supplied and will include the contract clause as required.

2.4.2 Government-

Furnished Facilities

N/A There will be no Government Furnished Facilities (GFF) made available to the Contractor upon award. If at a later time the Government finds it is in its best interest to furnish GFF, the contract will be modified to reflect the change. The Contractor will be responsible for any damage, loss or theft from or of GFF.

2.4.3 Government-

Furnished Vehicles and Equipment

N/A There will be no Government Furnished Vehicles and Equipment (GFV&E) made available to the Contractor upon award. If at a later time the Government finds it is in its best interest to furnish GFV&E, the contract will be modified to reflect the change. The Contractor will be responsible for any damage, loss or theft from or of GFV&E.

2.4.4 Government-

Furnished Utilities

The Government will make available water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site.

Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).

The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800- 171, track accomplishment, and submit to the Government per Section F.

If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.

2.6.2 Dissemination of

Information If certain information cannot be provided to the public, state what information cannot be provided, when it will be provided, and to whom, e.g., DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours. If a voice mail or recording function is used;

the device must have the capability of either allowing the caller to leave a message or transferring the call to a person at all times.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following workday for inquiries after regular working hours.

The Contractor shall provide work schedules for both Recurring and Non-Recurring Work to the KO and COR. At a minimum, work schedules shall include:

• Description of service(s) to be accomplished

• Location

• Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business. In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor is required to submit 2-week look-ahead work schedule. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO with written notification of any difficulty in scheduling work due to Government controls.

At a minimum, the notification shall include the following:

• The date and time the work was initially coordinated.

• The name and phone number of the Government person with whom the work was initially coordinated.

• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

• The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in Sections C, F, J and within the Directives, Instructions, and References. The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format. Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.7 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, fire department, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.8 NAVFAC

Maximo

The Contractor is required to provide work order, asset, specification, and condition assessment data for NAVFAC’s Maximo. The data is required for the Government’s use in long term asset management and planning.

NAVFAC Maximo is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment.

The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:

Informational Note:

Not all supported commands’ assets are included in NAVFAC Maximo. Not all of the modules available within the Maximo application are utilized by NAVFAC and the modules utilized may not be fully implemented. NAVFAC Maximo does not include a detailed inventory of all assets, components, and equipment that the Contractor is required to service under this contract and may include inaccuracies, omissions, and redundancies.

2.6.8.1 NAVFAC

Maximo Data

Further instructional information detailing the process for submitting the specified information for NAVFAC Maximo Data Reporting is provided in J-0200000-11.

The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into Maximo by the Government and the format may be updated periodically.

As part of the update the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor shall provide up to 10 extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar days’ notice of modifications to the Service Provider, Asset, Specification, or Characteristic Meter Reading Interfaces file format.

2.6.8.2 NAVFAC

Maximo Method of Data Entry

The Contractor shall provide data for NAVFAC Maximo using the methods detailed below:

If the Contractor does not have access to NAVFAC Maximo at contract start, work order and condition assessment data shall be submitted in a pipe delimited flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F. Any failures in processing of the flat-file shall be corrected and resubmitted by the Contractor.

In order to demonstrate the ability to properly format the flat-file, the Contractor shall provide a Sample Pipe Delimited Flat-file prior to contract performance per Section F.

FLAT FILE: The Contractor shall electronically record and report compiled service performance data for exportation of asset and specification data to NAVFAC Maximo. The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F.

The Contractor shall submit work order and condition assessment data in a pipe delimited flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000- 11 per Section F. Any failures in processing of the pipe delimited flat-file shall be corrected and resubmitted by the Contractor. In order to demonstrate the ability to properly format the pipe delimited flat-file, the Contractor shall provide a Sample Pipe Delimited Flat-file prior to contract performance per Section F.

The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F.

2.6.8.3 NAVFAC

Maximo Access

The process for obtaining access and establishing NAVFAC Maximo accounts are detailed in the NAVFAC Maximo System Access Procedures provided in J-0200000-12.

Once accounts have been established, NAVFAC Maximo can be accessed at https://maximo.navfac.navy.mil.

The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access NAVFAC Maximo for Direct Entry of required data.

The Contractor shall submit a list of personnel requiring NAVFAC Maximo accounts per Section F.

2.6.8.4 NAVFAC

Maximo Training

The Government will provide or make available initial training on NAVFAC Maximo to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data. Additional training will be provided by the Government when there are significant changes to the NAVFAC Maximo software or data entry requirements.

Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC Maximo.

2.6.9 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.9.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.9.2 Quality

Inspection and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.9.3 Quality

Inspection and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.10 Property

Management Plan

N/A Not Applicable because section 2.4.1 is not applicable.

2.6.11 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The

Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate who shall be on-site at all times when the Contractor is performing work during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

The Quality Manager or designated alternate shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity.

The Quality Manager or designated alternate may be the same person as the SSHO.

2.7.1.2.1 Quality Control

Personnel

The Contractor shall provide Quality Control personnel whose primary duty and responsibility is to enforce the Contractor’s Quality Management System on this contract.

The Quality Control personnel shall be on-site at all times when the Contractor is performing work during the Government's regular working hours. The Quality Control personnel shall report directly to the Quality Manager and shall not report directly to the Project Manager.

Quality Control personnel shall have fulfilled the following pre-requisite training and experiences before being hired as Quality Control under this contract:

Quality Control personnel shall meet or exceed the qualifications, technical knowledge and experience requirements specified for the personnel performing the work, which they will be inspecting, and have at least three years of experience in enforcing QMS programs on contracts of similar size, scope and complexity.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site

Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he possesses a Certified Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO may be the same person as the project manager but shall have fulfilled the pre-requisite qualification and experience.

The Contractor is required to have a SSHO and QC Manager (may be same person) on site during all Task Order work.

2.7.1.4 Environmental/

Energy Manager

N/A

2.7.2 Employee

Requirements

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.

2.7.2.1 Employee

Certification and Training

The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes.

Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.

2.7.2.2 Employee

Appearance

The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.

2.7.2.3 Employee

Conduct

Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

2.7.2.4 Identification as

Contractor Employee

Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in both verbal communication and electronic or written correspondence.

2.7.2.5 Removal of

Employees The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.

2.7.2.6 Proof of Legal

Residency

No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted per Section F

2.7.3 Service Contract

Reporting (SCR)

The Contractor shall report total dollar amount invoiced and all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.sam.gov.

Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://www.sam.gov.

2.8 Security

Requirements

The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The Contractor shall ensure that all security/entrance clearances are obtained.

The Contractor shall ensure that Contractor personnel do not present a risk to security. By entering the installation, Contractor personnel are subject to installation, state, local and federal regulations and laws, including but not limited to debarment and criminal prosecution.

2.8.1 Employee

Listing

The Contractor shall maintain a current Employee List and submit per Section F. The list shall include employee’s name, supervisor, company, and level of security clearance.

2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration.

2.8.3 Passes and

Badges

All Contractor employees shall obtain the required employee and vehicle passes. The Contractor employees must be able to obtain Common Access Cards (CAC) in accordance with security requirements. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and Badges shall be confiscated by the Contractor immediately and returned within 10 calendar days.

2.8.4 Access to

Installation

All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS).

The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.

2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access…