This document outlines a solicitation for an indefinite delivery indefinite quantity (IDIQ) roofing contract to provide services at multiple military bases under the jurisdiction of the Naval Facilities Engineering Command (NAVFAC). The solicitation seeks a contractor to perform roofing demolition, installation, repair, and maintenance services for facilities in Beaufort, South Carolina. The period of performance is for one base year with four optional one-year ordering periods. The contract is a fixed-price IDIQ where task orders will be issued on both a firm-fixed-price and labor-hour basis. The solicitation includes a detailed schedule of estimated quantities and unit prices for line items covering all aspects of roofing work. Responses are due by the date specified in the Standard Form 1449 located on the solicitation website.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

CONTRACT SUMMARY

BASE YEAR
OPTION 1
OPTION 2
OPTION 3
OPTION 4

TOTAL CONTRACT

Line Item Description

DESCRIPTION OF CONTRACT REQUIREMENTS
SCOPE OF WORK:

The following Statement of Work for each Line Item defines the abbreviated scope of work to be performed for the unit cost quoted. All line items shall be inclusive of transportation/delivery charges to the work site, placement at the point of installation, shop and field fabrication, installation and fastening per specifications including all incidental fasteners, brackets, hangers, screws, nails, cleats, adhesives, sealants, etc. as necessary for a complete, weather-tight and usable system.

ELIN STATEMENT OF WORK FOR LINE ITEMS

001DEMOLITION
001AADemolition of standard non-asbestos, multi-ply BUR without gravel

a. Unit of measurement shall be "Square Feet" or SF

b. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, and SC regulations.

001AB Demolition of standard non-asbestos, multi-ply BUR with gravel

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as gravel, deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, and SC regulations.

001AC Demolition of standard non-asbestos, multi-ply perimeter flashing system

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Remove cants, base flashing up to 24" high and all miscellaneous items along the work area such as gravel, deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of metal work is not included in this line item; refer to other line items if sheet metal removal is required.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, and SC regulations.

001AD Demolition of single ply, non-ballasted

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, SC regulations.

001AE Demolition of single ply, with ballast

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as ballast, deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, SC regulations.

001AF Demolition of roof insulation up to 2" thick

a. Unit of measurement shall be: "Square Feet" or SF

b. Includes any incremental thickness of insulation up to 2" thick.

c. Remove existing insulation down to roof deck or as required by task order.

d. Remove all debris from job site and dispose of in an approved landfill.

e. Clean all debris from flutes in metal deck.

f. All work to comply with OSHA, EPA, SC regulations.

g. Remove all fasteners from decking, if applicable.

001AG Demolition of roof insulation up to 4" thick

a. Unit of measurement shall be: "Square Feet" or SF

b. Includes any incremental thickness of insulation up to 4" thick.

c. Remove existing insulation down to roof deck or as required by task order.

d. Remove all debris from job site and dispose of in an approved landfill.

e. Clean all debris from flutes in metal deck.

f. All work to comply with OSHA, EPA, SC regulations.

g. Remove all fasteners from decking, if applicable.

001AH Demolition of regular and/or lightweight concrete fill

a. Unit of measurement shall be: "Cubic Feet" or CF

b. Includes various thicknesses of sloping fill.

c. Remove existing insulation down to structural roof deck or as required by task order.

d. Where used over metal deck, reattach laps, seams and loose metal as needed using self-tapping, coated metal deck fastener.

e. Replace metal decking found damaged or deteriorated as directed by contracting officer.

f. Remove all debris from job site and dispose of in an approved landfill.

g. All work to comply with OSHA, EPA, SC regulations.

001AJ Demolition of asphaltic fill

a. Unit of measurement shall be: "Cubic Feet" or CF

b. Includes various thicknesses of sloping fill.

c. Remove existing insulation down to structural roof deck or as required by task order.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, SC regulations 001AK Abatement and Disposal of non-friable asbestos-containing roofing material (ACRM), multi-ply BUR with loose gravel

a. Unit of measurement shall be: "Square Feet" or SF

b. May be smooth surface BUR or may include embedded gravel; refer to other line items for removal of loose gravel.

c. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as embedded gravel, deteriorated nailers etc. not otherwise covered by a separate demolition line item.

d. Remove all debris, including non-friable ACRM, from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, SC regulations.

f. Certain practices such as burning, sanding or grinding which could crumble, pulverize or reduce the non-friable ACRM to powder are prohibited.

g. All non-authorized work or contractor practices which render the non-friable ACRM to a friable state or which raise the air borne concentration of asbestos fibers above the permissible exposure level (PEL) will subject the contractor to all applicable OSHA, EPA, SC regulations.

001AL Demolition of two-ply modified bitumen roofing - smooth or granular surface

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing down to deck or dry insulation and all miscellaneous items within the work area such as deteriorated nailers etc. not otherwise covered by a separate demolition line item.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove all debris from job site and dispose of in an approved landfill.

e. All work to comply with OSHA, EPA, SC regulations.

001AM Vacuum non-embedded gravel

a. Unit of measurement shall be: "Square Feet" or SF

b. Line item to be used in conjunction with other line items for overlay systems.

c. Remove all debris from job site.

d. All work to comply with OSHA, EPA, SC regulations.

001AN Spud embedded gravel at tie-ins

a. Unit of measurement shall be: "Square Feet" or SF

b. Using roofing spades, mattock or mechanical device, remove embedded gravel from roof membrane.

c. Includes temporary removal and reuse of existing non-embedded loose gravel in spudded area.

d. Includes asphalt primer on spudded surface.

001AP Remove gravel & debris from gutters, roof drains, mech. equipment, and roof surface

a. Unit of measurement shall be: "Square Feet" or SF

b. Includes removal from all sizes of gutters, drains, and mech. equipment.

c. Remove all debris from job site.

001AQ Demolition of plywood or board sheathing

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove deteriorated plywood or board sheathing as directed by task order; remove all debris from job site.

c. Protect and/or barricade area below work before deck removal starts; take care to ensure against damages to employees and property.

d. Remove all fasteners and inspect roof joist for soundness.

e. Repair joist as directed by contracting officer; refer to other line items for carpentry.

001AR Demolition of 2" or 3" T&G wood decking

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove deteriorated decking as directed by task order; remove all debris from job site.

c. Protect and/or barricade area below work before deck removal starts; take care to ensure against damages to employees and property.

d. Remove all fasteners and inspect roof joist for soundness.

e. Repair joist as directed by contracting officer; refer to other line items for carpentry.

001AS Demolition of standard metal roof deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove deteriorated decking as directed by task order; remove all debris from job site.

c. Protect and/or barricade area below work before deck removal starts; take care to ensure against damages to employees and property.

d. All decking must be replaced and made weather tight daily; refer to other line items for new decking.

001AT Demolition of asphalt shingles and felt

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing and all miscellaneous items within the work area down to deck including felts and, in some instances, multi-layers of shingles.

c. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

d. Remove old nails, tacks and fasteners from deck.

e. Dispose of all debris in approved land fill.

001AU Demolition of wood, vinyl or metal siding

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove deteriorated siding as directed by task order; remove all debris from job site.

c. Remove old nails, tacks and fasteners from sheathing.

d. Furnish material, labor, scaffolding and equipment to perform work per task order.

001AV Demolition of cementitious wall finish

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove deteriorated wall finish as directed by task order; remove all debris from job site.

c. Remove old nails, tacks and fasteners from sheathing.

d. Furnish material, labor, scaffolding and equipment to perform work per task order.

001AW Demolition of cement asbestos board (CAB) siding

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove all debris, including non-friable CAB siding, from job site and dispose of in an approved landfill.

c. All work to comply with OSHA, EPA, SC regulations.

d. Certain practices such as burning, sanding or grinding which could crumble, pulverize or reduce the non-friable CAB siding to powder are prohibited.

e. All non-authorized work or contractor practices which render the non-friable CAB siding to a friable state or which raise the air borne concentration of asbestos fibers above the permissible exposure level (PEL) will subject the contractor to all applicable OSHA, EPA, SC regulations.

f. Remove old nails, tacks and fasteners from sheathing.

g. Furnish material, labor, scaffolding and equipment to perform work per task order.

001AX Removal of masonry units, brick, or block

a. Unit of measurement shall be: "Square Feet" or SF

b. Furnish material, labor, scaffolding and equipment to perform work per task order.

c. Using chisels, grinders etc., remove concrete block, brick, other masonry units and/or joints.

d. Clean all mortar from repair area.

e. Remove all debris and dispose of all debris in approved land fill.

001AY Demolition of wood framing, various sizes

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Remove deteriorated 2" x 4", 6", 8", 10", or 12" framing as directed by task order; remove all debris from site.

001AZ Demolish or raise lightweight, roof-mounted equipment

a. Unit of measurement shall be: "Each" or EA

b. Remove abandoned or raise existing lightweight sheet metal items including but not limited to ventilators, exhaust fans, vent stacks and grills, antennas, etc. as directed by task order; remove all debris from site.

c. Refer to other line items when new curbs are required for equipment to be raised.

d. Refer to other line items if utility disconnection and termination is required.

001BA Demolish or raise heavy, roof-mounted equipment

a. Unit of measurement shall be: "Each" or EA

b. Remove abandoned or raise existing items including but not limited to mechanical units, cooling towers, ventilators, exhaust fans, antennas, etc. which require lifting by crane as directed by task order; remove all debris from site.

c. Refer to other line items when new curbs are required for equipment to be raised.

d. Refer to other line items if utility disconnection and termination is required.

001BB Demolition of slate shingles

a. Unit of measurement shall be: "Square Feet" or SF

b. Protect and/or barricade area below work before removal starts; take care to ensure against damages to employees and property.

c. Remove existing roofing and all miscellaneous items within the work area down to deck including felts.

d. Inspect wood decking for damaged or deterioration; replace as directed by contracting officer; refer to other line items for Carpentry.

e. Removal of items such as sheet metal and insulation within the work area will be accomplished using the pre-priced line items for such removals.

f. Remove old nails, tacks and fasteners from deck.

g. Remove slate debris from decking.

h. Remove all debris from job site and dispose of in an approved landfill.

001BC Demolition of exterior ornamental trim, various sizes

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Protect and/or barricade area below work before removal starts; take care to ensure against damages to employees and property.

c. Inspect molding, soffit, fascia, and supports for damaged or deterioration; remove as directed by contracting officer.

d. Remove all fasteners.

e. Furnish material, labor, scaffolding and equipment to perform work per task order.

f. Remove all debris from site.

001BD Demolition of power ventilator up to 14" x 12" - 12" diameter opening

a. Unit of measurement shall be: "Each" or EA

b. Remove existing power ventilator, curb (if any), flashing, metal counterflashing, and other miscellaneous metal flashings down to substrate and all miscellaneous items within the work area not otherwise covered by a separate demolition line item.

c. Remove all fasteners, hangers, brackets, reglets and associated support devices in the area of the work.

d. Remove all debris from site.

001BE Demolition of wood cornice, various sizes

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Area below work must be protected and/or barricaded before cornice removal starts; care must be taken to ensure against damages to employees and property.

c. Protect and/or barricade area below work before removal starts; take care to ensure against damages to employees and property.

d. Remove all fasteners.

e. Furnish material, labor, scaffolding and equipment to perform work per task order.

f. Remove all debris from site.

001BF Abatement and Disposal of non-friable ACRM asphalt shingles and felt

a. Unit of measurement shall be: "Square Feet" or SF

b. Remove existing roofing down to deck including felts and, in some instances, multi-layers of shingles, and all miscellaneous items within the work area not otherwise covered by a separate demolition line item.

c. Remove all debris, including non-friable ACRM, from job site and dispose of in an approved landfill.

d. All work to comply with OSHA, EPA, SC regulations.

e. Certain practices such as burning, sanding or grinding which could crumble, pulverize or reduce the non-friable ACRM to powder are prohibited.

f. All non-authorized work or contractor practices which render the non-friable ACRM to a friable state or which raise the air borne concentration of asbestos fibers above the permissible exposure level (PEL) will subject the contractor to all applicable OSHA, EPA, SC regulations.

001BG Demolition of gutters, downspouts, metal counterflashing, drip edge, gravel stop or other miscellaneous metal flashings

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Remove existing gutters, downspouts, metal counterflashing, drip edge, gravel stop or other miscellaneous metal flashings down to substrate and all miscellaneous items within the work area not otherwise covered by a separate demolition line item.

c. Remove all fasteners, hangers, brackets, reglets and associated support devices in the area of the work.

d. Remove all debris from site.

001BH Demolition of asbestos sealant/caulking up to 1" width

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Remove existing asbestos containing sealant/caulking joints including all backer material back to substrate.

c. Remove all debris, including non-friable ACRM, from job site and dispose of in an approved landfill.

d. All work to comply with OSHA, EPA, SC regulations.

e. Certain practices such as burning, sanding or grinding which could crumble, pulverize or reduce the non-friable ACRM to powder are prohibited.

f. All non-authorized work or contractor practices which render the non-friable ACRM to a friable state or which raise the air borne concentration of asbestos fibers above the permissible exposure level (PEL) will subject the contractor to all applicable OSHA, EPA, SC regulations.

002ASBESTOS AND LEAD ABATEMENT/REMOVAL
002AAMinmum cost incurred for asbestos abatement for trailer (Provide set up and removal)

a. Unit of measurement shall be: "Each" or EA

b. Include all mobilization and demobilization costs including but not limited to delivery, set up, utility connections, tie down, disconnection, removal, cleanup and site restoration to original site conditions.

002AB Additional cost incurred for the removal and disposal of asbestos containing substances. Regular roofing only. (See synopsis of line items)

a. Unit of measurement shall be: "Square Feet" or SF

b. Work shall be as determined from HAZMAT survey.

002AC Additional cost incurred for the removal and disposal of asbestos containing substance flashing, pitch pockets, etc. (See synopsis of line items)

a. Unit of measurement shall be: "Square Feet" or SF

b. Work shall be as determined from HAZMAT survey.

002AD Removal of lead based paint (Contractor removes loose paint from surface) (The contractor furnishes container and the government disposes)

a. Unit of measurement shall be: "Square Feet" or SF

b. Work shall be as determined from HAZMAT survey.

003DECKING, FRAMING, SHEATHING, TRIM, AND BLOCKING
003AAPlywood decking, 1/2" CDX

a. Unit of measurement shall be: "Square Feet" or SF

b. Fasteners per roof system mfg. or APA guidelines.

003AB Plywood decking, 5.8" CDX, T&G

a. Unit of measurement shall be: "Square Feet" or SF

b. Fasteners per roof system mfg. or APA guidelines.

003AC Plywood decking, 3/4" CDX, T&G

a. Unit of measurement shall be: "Square Feet" or SF

b. Fasteners per roof system mfg. or APA guidelines.

003AD 2" x 6" T&G wood decking

a. Unit of measurement shall be: "Square Feet" or SF 003AE 1" x 6" or 1" x 8" wood sheathing

a. Unit of measurement shall be: "Square Feet" or SF 003AF 2" x 12" treated wood curbing and nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AG 2" x 4" framing (studs, bracing, blocking, etc.)

a. Unit of measurement shall be: "Lineal Feet" or LF 003AH 2" x 6" framing (joists, rafters, beams, etc.)

a. Unit of measurement shall be: "Lineal Feet" or LF 003AJ 2" x 8" framing (joists, rafters, beams, etc.)

a. Unit of measurement shall be: "Lineal Feet" or LF 003AK 2" x 10" framing (joists, rafters, beams, etc.)

a. Unit of measurement shall be: "Lineal Feet" or LF 003AL 2" x 12" framing (joists, rafters, beams, etc.)

a. Unit of measurement shall be: "Lineal Feet" or LF 003AM 1" x 4" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AN 1" x 6" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AP 1" x 8" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AQ 1" x 10" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AR 2" x 4" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AS 2" x 6" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AT 2" x 8" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AU 2" x 10" treated wood nailer

a. Unit of measurement shall be: "Lineal Feet" or LF 003AV 1" x 6" or 2" x 6" wood fascia

a. Unit of measurement shall be: "Lineal Feet" or LF 003AW 1" x 8" or 2" x 8" wood fascia

a. Unit of measurement shall be: "Lineal Feet" or LF 003AX 1" x 10" or 2" x 10" wood fascia

a. Unit of measurement shall be: "Lineal Feet" or LF 003AY Treated wood cant (4 x 4 cut of diagonal)

a. Unit of measurement shall be: "Lineal Feet" or LF

b. 4x4 treated wood cut on diagonal to form cant strips.

003AZ Plywood decking, 3/4" CDX

a. Unit of measurement shall be: "Square Feet" or SF

b. Fasteners per roof system mfg. or APA guidelines.

003BA Exterior ornamental trim, various sizes

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Protected and/or barricade area below work before trim installation starts; take care must to ensure against damages to employees and property.

c. Install molding, soffit, fascia, and supports per task order.

d. Furnish material, labor, scaffolding and equipment to perform work per task order.

003BB Exterior wood cornice, various sizes

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Protected and/or barricade area below work before trim installation starts; take care must to ensure against damages to employees and property.

c. Install wood cornice and required supports per task order.

d. Furnish material, labor, scaffolding and equipment to perform work per task order.

004WATERPROOFING
004AASaw cut reglet joint in mansonry walls

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Cut joint to full height (3/8" - 1/2") and 1" depth.

004AB Remove and reset clay tile coping

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Cut back all mortar, asphalt mastic and/or caulking from joints.

c. Remove coping and all mortar from top of parapet.

d. Apply mortar mix to top of parapet, set cleaned tile into fresh mortar mix and press into place.

e. Waterproof joints after curing of mortar (48 hours).

004AC Remove and reset 2" to 6" thick stone coping

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Cut back all mortar, asphalt mastic and caulking from joints.

c. Remove coping and all mortar from top of parapet.

d. Apply mortar mix to top of parapet, set cleaned coping stone in place leaving approximately 3/8" joint between stones.

e. Waterproof joints and stones after curing of mortar.

004AD Repair/Replace concrete roof decks

a. Unit of measurement shall be: "Square Feet" or SF

b. Area below work must be protected and/or barricaded before deck removal starts; care must be taken to ensure against damages to employees and property.

c. Remove existing insulation and roofing materials down to concrete roof deck or as required by task order.

d. Using chisels, grinders etc., remove damaged or deteriorated concrete roof deck.

e. Repair/Replace damaged/deteriorated concrete roof deck as directed by contracting officer.

f. Remove all debris from job site and dispose of in an approved landfill.

004AE Repair/Replace concrete roof planks

a. Unit of measurement shall be: "Square Feet" or SF

b. Area below work must be protected and/or barricaded before deck removal starts; care must be taken to ensure against damages to employees and property.

c. Remove existing insulation and roofing materials down to concrete roof planks or as required by task order.

d. Using chisels, grinders etc., remove damaged or deteriorated concrete roof planks.

e. Repair/Replace damaged/deteriorated concrete roof planks as directed by contracting officer.

f. Remove all debris from job site and dispose of in an approved landfill.

005INSULATION
005AA3/4" to 1-1/2" isocyanurate board, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AB 1-9/16" to 2-1/2" isocyanurate board, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AC 2-9/16" to 3" isocyanurate board, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AD 3-1/16" to 4" isocyanurate board, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AE 4-1/16" to 5" isocyanurate board, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AF 3/4" to 1-1/2" isocyanurate board, mechanically fastened on steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AG 1-9/16" to 2-1/2" isocyanurate board, mechanically fastened on steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AH 2-9/16" to 3" isocyanurate board, mechanically fastened on steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AJ 3-1/16" to 4" isocyanurate board, mechanically fastened on steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AK 4-1/16" to 5" isocyanurate board, mechanically fastened on steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Isocyanurate insulation board; R = 6.0/in.

c. Attachment: adhered with cold applied adhesive as required by specifications.

005AL 1/2" glass mat gypsum roof board thermal barrier or cover board, mechanically fastened or adhered

a. Unit of measurement shall be: "Square Feet" or SF

b. Attachment: mechanical fasteners as required by specifications.

005AM 1/2" high density fiberboard cover board, mechanically fastened or adhered

a. Unit of measurement shall be: "Square Feet" or SF

b. Attachment: mechanical fasteners as required by specifications.

005AN Tapered isocyanurate board, 1/8 "/ft

a. Unit of measurement shall be: "Square Feet" or SF 005AP Tapered isocyanurate board, 1/4 "/ft w/o filler

a. Unit of measurement shall be: "Square Feet" or SF 005AQ Tapered isocyanurate board, 3/8 "/ft w/o filler

a. Unit of measurement shall be: "Square Feet" or SF 005AR Tapered isocyanurate board, 1/2 "/ft w/o filler

a. Unit of measurement shall be: "Square Feet" or SF 005AS Mineral fiber cant strip, 1-1/2" x 5" face

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Asphalt impregnated mineral fiber cant.

005AT Tapered edge strip, 1" edge x 12"

a. Unit of measurement shall be: "Square Feet" or SF

b. Mineral aggregate perlite board.

005AU Tapered edge strip, 1-1/2" edge x 12"

a. Unit of measurement shall be: "Square Feet" or SF

b. Mineral aggregate perlite board.

005AV 6" fiberglass blanket, vinyl reinforced faced, R-19 (16" and 24")

a. Unit of measurement shall be: "Square Feet" or SF

b. For use in pre-engineered building systems 005AW 6" fiberglass blanket, unfaced, R-19 (16" and 24")

a. Unit of measurement shall be: "Square Feet" or SF

b. For use in slope-conversion projects with other line items over abandoned, low-slope built-up roofs.

005AX 3/4" to 1-1/2" extruded polystyrene board insulation, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Attachment: adhered with cold applied adhesive 005AY 1-9/16" to 2-1/2" extruded polystyrene board insulation, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: adhered with cold applied adhesive 005AZ 2-9/16" to 3" extruded polystyrene board insulation, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: adhered with cold applied adhesive 005BA 3-1/16" to 4" extruded polystyrene board insulation, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: adhered with cold applied adhesive 005BB 4-1/16" to 5" extruded polystyrene board insulation, adhered over concrete deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: adhered with cold applied adhesive 005BC 3/4" to 1-1/2" extruded polystyrene board insulation, mechanically fastened over steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Attachment: mechanically fastened as required by specifications.

005BD 1-9/16" to 2-1/2" extruded polystyrene board insulation, mechanically fastened over steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: mechanically fastened as required by specifications.

005BE 2-9/16" to 3" extruded polystyrene board insulation, mechanically fastened over steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: mechanically fastened as required by specifications 005BF 3-1/16" to 4" extruded polystyrene board insulation, mechanically fastened over steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: mechanically fastened as required by specifications 005BG 4-1/16" to 5" extruded polystyrene board insulation, mechanically fastened over steel or wood deck

a. Unit of measurement shall be: "Square Feet" or SF

b. Polystyrene insulation board; R = 5.0/in.

c. Tongue-and-groove, closed cell extruded polystyrene insulation board

d. Attachment: mechanically fastened as required by specifications

006SHINGLED ROOF SYSTEMS
006AAShingles, fiberglass, standard 3-tab

a. Unit of measurement shall be: "Square Feet" or SF

b. U.L. and ASTM E108 Class A fire resistance.

c. Self-sealing tabs with U.L. wind resistant label.

d. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Asphalt Shingles and manufacturer's standard details.

e. Refer to other line items for underlayment.

006AB Shingles, fiberglass, twenty-five year architectural

a. Unit of measurement shall be: "Square Feet" or SF

b. U.L. and ASTM E108 Class A fire resistance.

c. Self-sealing tabs with U.L. wind resistant label.

d. Hip and ridge factory pre-cut where applicable.

e. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Asphalt Shingles and manufacturer's standard details.

f. Refer to other line items for underlayment.

006AC Shingles, fiberglass, thirty-year architectural

a. Unit of measurement shall be: "Square Feet" or SF

b. U.L. and ASTM E108 Class A fire resistance.

c. Self-sealing tabs with U.L. wind resistant label.

d. Hip and ridge factory pre-cut where applicable.

e. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Asphalt Shingles and manufacturer's standard details.

f. Refer to other line items for underlayment.

006AD Shingles, fiberglass, forty-year architectural

a. Unit of measurement shall be: "Square Feet" or SF

b. U.L. and ASTM E108 Class A fire resistance.

c. Self-sealing tabs with U.L. wind resistant label.

d. Hip and ridge factory pre-cut where applicable.

e. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Asphalt Shingles and manufacturer's standard details.

f. Refer to other line items for underlayment.

006AE Shingles, slate, Buckingham

a. Unit of measurement shall be: "Square Feet" or SF

b. ASTM C 406 Classification, Grade S1 with expected service life of 75 years

c. 3/16" to 1/4" thick commercial slate with uniform length (20") & width (8-1/2") and nail holes.

d. Slate nails to be used to attach slate to roof

e. Color selected by Contracting Officer from manufacturer's available color selection.

f. Degree of weathering selected by Contracting Officer from manufacturer's available weather exposure color change selection.

g. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Slate Roof Systems and manufacturer's standard details.

h. Refer to other line items for underlayment, flashing, sheet metal or other items as may be required for conditions.

006AF Shingles, slate, Weathering Green, Vermont

a. Unit of measurement shall be: "Square Feet" or SF

b. ASTM C 406 Classification, Grade S1 with expected service life of 75 years

c. 3/16" to 1/4" thick commercial slate with uniform length (20") & width (8-1/2") and nail holes.

d. Slate nails to be used to attach slate to roof

e. Color selected by Contracting Officer from manufacturer's available color selection.

f. Degree of weathering selected by Contracting Officer from manufacturer's available weather exposure color change selection.

g. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Slate Roof Systems and manufacturer's standard details.

h. Refer to other line items for underlayment, flashing, sheet metal or other items as may be required for conditions.

006AG Underlayment, No. 15 felt, per layer

a. Unit of measurement shall be: "Square Feet" or SF 006AH Underlayment, No. 30 felt, per layer

a. Unit of measurement shall be: "Square Feet" or SF 006AJ Ice shield, self-adhered

a. Unit of measurement shall be: "Square Feet" or SF 006AK Roll roofing, single coverage

a. Unit of measurement shall be: "Square Feet" or SF

b. Asphalt roll roofing (glass felt) surfaced with mineral granules, 4" selvage edge.

c. Concealed nail installation per NRCA (latest edition) "Steep Roof", Concealed-Nail Method for Asphalt Roll Roofing Materials.

d. Lap cement, eave & rake edge strips and ridge & hip caps shall be included in line item unit cost.

e. Refer to other line items for underlayment.

006AL Step flashing, mill finish aluminum

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications 006AM Step flashing, prefinished aluminum

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications

c. Pre-coated, baked-on acrylic or polyester coating.

006AN Valley flashing, prefinished aluminum, 24" wide

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications

c. Pre-coated, baked-on acrylic or polyester coating.

d. 'W" style valley with 1" 'V' crimp.

006AP Step flashing, copper

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications 006AQ Valley flashing, copper, 24" wide

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications

c. 'W" style valley with 1" 'V' crimp.

006AR Drip edge, prefinished aluminum

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Thickness and alloy per specifications

c. Pre-coated, baked-on acrylic or polyester coating.

d. "Tee" style drip, 1-1/2" x 2-3/4", with 3/4" lip.

007MODIFIED BITUMEN ROOFING SYSTEMS
007AATwo-ply SBS modified, granulated cap, cold process

a. Unit of measurement shall be: "Square Feet" or SF

b. SBS polymer-modified base sheet and SBS polymer-modified cap sheet set with cold process adhesive over manufacturer approved substrate

c. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Modified Bitumen Roofing Systems and manufacturer's standard details.

d. Refer to other line items for primer, insulation, flashing, sheet metal or other items as may be required for conditions.

007AB Two-ply SBS modified, smooth cap, cold process

a. Unit of measurement shall be: "Square Feet" or SF

b. SBS polymer-modified base sheet and SBS polymer-modified cap sheet set with cold process adhesive over manufacturer approved substrate

c. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Modified Bitumen Roofing Systems and manufacturer's standard details.

d. Refer to other line items for primer, insulation, flashing, sheet metal or other items as may be required for conditions.

007AC 15 year installer's warranty for two-ply SBS modified bitumen roof

a. Unit of measurement shall be: "Each" or EA.

b. Extend required five-year installer warranty for a total of 15 years from date of acceptance.

008PVC MEMBRANE ROOFING
008AASingle-ply PVC membrane roofing, mechanically fastened

a. Unit of measurement shall be: "Square Feet" or SF

b. Fully adhered system; bonding adhesive and lap seam sealant shall be compatible with substrate and membrane and furnished by membrane manufacturer.

c. Refer to other line items for insulation, surfacing, flashing, sheet metal or other items as may be required for conditions.

d. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for PVC Single Ply Roofing Systems and manufacturer's standard details.

008AB Single-ply PVC membrane roofing, fully adhered

a. Unit of measurement shall be: "Square Feet" or SF

b. Fastener pattern shall comply with NRCA (latest edition) Specification Guide and fastener type shall comply with NRCA (latest edition) "General Guide to Fasteners".

c. Lap seam sealant shall be compatible with substrate and membrane and furnished by membrane manufacturer.

d. Refer to other line items for insulation, surfacing, flashing, sheet metal or other items as may be required for conditions.

e. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for PVC Single Ply Roofing Systems and manufacturer's standard details.

008AC 15 year installer's warranty for single ply PVC membrane roofing, mechanically fastened

a. Unit of measurement shall be: "Each" or EA.

b. Extend required five-year installer warranty for a total of 15 years from date of acceptance.

008AD 15 year installer's warranty for single ply PVC membrane roofing, fully adhered

a. Unit of measurement shall be: "Each" or EA.

b. Extend required five-year installer warranty for a total of 15 years from date of acceptance.

TOTAL COST FOR CONTRACT LINE ITEM 008

009SURFACING AND RESTORATION
009AAPower wash horizontal surfaces

a. Unit of measurement shall be: "Square Feet" or SF 009AB Power wash vertical surfaces

a. Unit of measurement shall be: "Square Feet" or SF 009AC Seam reinforcement - 6" wide (polyester fabric and urethane coating for single-ply and modified bitumen aluminum coating only)

a. Unit of measurement shall be: "Lineal Feet" or LF 009AD Aluminum coating for modified bitumen roofing only

a. Unit of measurement shall be: "Square Feet" or SF

b. Fibrated aluminum base coat, ASTM D 2824

c. Fibrated aluminum finish coat, ASTM D 2824, Energy Star Certified 009AE Emulsion and poly fabric base coat for modified bitumen white coating only

a. Unit of measurement shall be: "Square Feet" or SF

b. Water based neoprene rubber modified asphalt emulsion with polyester reinforcing mat base coat

c. Waterbased acrylic latex polymer finish coat, Energy Star Certified 009AF Urethane coating system for single ply roofing only

a. Unit of measurement shall be: "Square Feet" or SF

b. Single component aromatic urethane base coat

c. Single component aliphatic urethane white finish coat

010FLASHINGS
010AATwo-ply SBS modified bitumen sheet, metal clad

a. Unit of measurement shall be: "Square Feet" or SF

b. Refer to other line items for primer, wood nailers, sheet metal and surface coating, if required.

c. Installation and details shall be in accordance with NRCA (latest edition) "Construction Details" as applicable for Built-Up, EPDM Single Ply, Modified Bitumen, or Steep Roofing Systems and manufacturer's standard details.

010AB 30" x 30", 4 lb. lead roof drain flashing at existing roof drain including removals

a. Unit of measurement shall be: "Each" or EA

b. Remove existing roof drain strainer, clamping ring, lead, stripping plies, deteriorated roof membrane and wet insulation within approximate 4' x 4' work area.

c. Prime area; set new lead flashing in elastomeric mastic; strip lead flashing with glass fabric and elastomeric mastic; prime surface of lead sheet; reinstall clamping ring and strainer.

d. Refer to other line items for removal of embedded gravel at tie-in at existing roof surface, membrane ply stripping, replacement of deteriorated roof membrane and insulation and miscellaneous roof drain repair items.

010AC 4 lb. lead plumbing stack flashing at existing stack including removals

a. Unit of measurement shall be: "Each" or EA

b. Remove existing lead, stripping plays, deteriorated roof membrane and wet insulation within approximate 2' x 2' work area.

c. Prime area; set new lead flashing in elastomeric mastic; strip lead flashing with glass fabric and elastomeric mastic; prime surface of lead sheet.

d. Refer to other line items for removal of embedded gravel at tie-in at existing roof surface, membrane ply stripping, replacement of deteriorated roof membrane and insulation and miscellaneous repair items.

010AD Expansion joint with flexible bellows and metal flanges, cover width to 16"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Schuller "Expand-O-Flash", Type EJ, CF, CF-EJ or TL.

c. Neoprene bellows with 26 ga. galvanized metal flange.

d. Furnish with manufacturer's standard adhesives, splices, nails, sealant and prefabricated corners, tees and other shapes as required by conditions.

e. Refer to other line items for wood curbs, nailers and cants, removal of embedded gravel at tie-ins, membrane ply stripping and sheet metal.

010AE Expansion joint with flexible bellows and metal flanges, cover width over 16" to 24"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Schuller "Expand-O-Flash", Type EJ, CF, CF-EJ or TL.

c. Neoprene bellows with 26 ga. galvanized metal flange.

d. Furnish with manufacturer's standard adhesives, splices, nails, sealant and prefabricated corners, tees and other shapes as required by conditions.

e. Refer to other line items for wood curbs, nailers and cants, removal of embedded gravel at tie-ins, membrane ply stripping and sheet metal.

010AF Expansion joint with .040 aluminum cover, cover width to 16"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. .040 mill finish aluminum cover with continuous bayonet type joint

c. Refer to other line items for wood curbs, nailers and cants, removal of embedded gravel at tie-ins, membrane ply stripping and sheet metal.

010AG Expansion joint with .040 aluminum cover, cover width over 16" to 24"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. .040 mill finish aluminum cover with continuous bayonet type joint

c. Refer to other line items for wood curbs, nailers and cants, removal of embedded gravel at tie-ins, membrane ply stripping and sheet metal.

010AH Aluminum termination bar, 1/4" x 1"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Extruded aluminum termination bar, .10" x 1.35" with lap sealant reservoir channel on top and drip channel on bottom.

c. Threaded or drive-pin fasteners as recommended by membrane system manufacturer, installed 8" o.c.

010AI Remove old mastic & refill pitch pan with two-part pourable sealer, average approximate size 8" x 8" x 6" thick

a. Unit of measurement shall be: "Each" or EA

b. Refill with Tremco "POLYroof" or Karnak "AR", single-component, asbestos-free, elastomeric mastic.

011SHEET METAL
011AAPrefinished aluminum downspout, .019", 2" x 3"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

c. Corrugated conductor pipe including matching elbows, pipe bands and outlet tubes.

011AB Prefinished aluminum downspout, .019", 3" x 4"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

c. Corrugated conductor pipe including matching elbows, pipe bands and outlet tubes.

011AC Prefinished sheet metal downspout, 26 ga., 3" x 4"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Galvanized with fluoropolymer coating.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Plain or corrugated conductor pipe with flat-lock seams including matching elbows, pipe bands and outlet tubes.

011AE Prefinished sheet metal downspout, 26 ga., 4" x 5"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Galvanized with fluoropolymer coating.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Plain or corrugated conductor pipe with flat-lock seams including matching elbows, pipe bands and outlet tubes.

011AF Copper downspout, 16 oz, 4" dia.

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Copper Sheet and Strip.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Corrugated conductor pipe with flat-lock seams including matching elbows, bands and outlet tubes.

011AG Copper downspout, 16 oz, 4" x 5"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Copper Sheet and Strip.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Corrugated conductor pipe with flat-lock seams including matching elbows, bands and outlet tubes.

011AH Prefinished aluminum gutter, .027", 5"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Nominal 5", 'K' or 'OGEE' style including matching end caps, mitered corners and hanger system.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Provide other SMACNA styles to match existing gutters where required.

011AJ Prefinished aluminum gutter, .032", 6"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Nominal 5", 'K' or 'OGEE' style including matching end caps, mitered corners and hanger system.

c. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

d. Provide other SMACNA styles to match existing gutters where required.

011AK Prefinished sheet metal gutter, 24 ga, 6"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Galvanized with fluoropolymer coating.

c. Nominal 6", 'A' or 'F' style including matching end caps, mitered corners and hanger system.

d. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

e. Provide other SMACNA styles to match existing gutters where required 011AL Prefinished sheet metal gutter, 22 to 18 ga, 21" to 35" girth

a. Unit of measurement shall be: "Square Feet" or SF

b. Galvanized with fluoropolymer coating.

c. Typical 'A' style including matching end caps, mitered corners and hanger system.

d. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

e. Provide other SMACNA styles to match existing gutters and conditions where required.

011AM Copper gutter, 16 oz, 5"

a. Unit of measurement shall be: "Lineal Feet" or LF

b. Copper Sheet and Strip.

c. Nominal 5", 'K' or 'OGEE' style including matching end caps, mitered corners and hanger system.

d. Fabrication, installation and details shall be in accordance with Sheet Metal and Air Conditioning Contractor's National Association, Architectural Sheet Metal Manual (latest edition) as applicable.

e. Provide other SMACNA styles to match…

This is the start of the file's text. The full file is on GovTribe.