1800000 - Environmental

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

Annex/ Spec Item

Form Attachment

Number Deliverable

Title Date (s) of Submission

Distribution

Frequency Original/ Copies

Number of Copies (including original)

1800000/2.2.1 N/A Training Plan 15 days after award/

Annually

COR 1 Annually

1800000/2.2.1 N/A Training Documentation

15 days after award/

Annually

COR 1 Once

1800000/3.1 N/A Sampling Plan 15 days after award/

Annually

COR/

Installation

Environmental Office

2 Annually

1800000/3.1.1 N/A Sampling Schedule

15 days after award/

Annually

COR 1 Annually

1800000/3.1.1 N/A Sample Collection Logs

7 days after sampling

COR/Installation Environmental

Office

2 As Required

1800000/3.1.2 N/A Field Testing Reports

7 days after testing

COR/

Installation

Environmental Office

2 As Required

1800000/3.1.3 N/A Laboratory Analysis Reports

Immediately upon

Receipt

COR/

Installation

Environmental Office

2 As Required

1800000/3.1.3 N/A Laboratory Analysis Reports Summary

By the 15th of the following month

COR/

Installation

Environmental Office

2 As Required

1800000/3.2 N/A Service Order Monthly Summary Report

Within 5 calendar days after the end of the month.

COR/Installation Environmental

Office/Asbestos Program Manager

3 Monthly

1800000/3.2.1

N/A Urgent Service Orders, Water Sampling

Lab reports due immediately upon receipt

COR/Installation Environmental

Office

3 As Required

1800000/3.2.2 N/A Urgent Service Orders, HM Inspection, Sampling, & Testing- Asbestos

5 days after inspecting, sampling, & testing

COR/Asbestos Program Manager

3 As Required

DELIVERABLES

Annex/ Spec Item

Form Attachment

Number Deliverable

Title Date (s) of Submission

Distribution

Frequency Original/ Copies

Number of Copies (including original)

1800000/3.2.3 N/A Onsite Service Orders – Asbestos

5 days after inspecting, sampling & testing

COR/Asbestos Program Manager

3 As Required

1800000/3.2.4 N/A Urgent Service Orders, HM Inspection, Sampling, & Testing-Heavy Metals

5 days after inspecting, sampling, & testing

COR/Asbestos Program Manager

3 As Required

1800000/3.2.5 N/A Onsite Service Orders – Heavy Metals

5 days after inspecting, sampling & testing

COR/Installation Environmental

Office/Asbestos Program Manager

3 As Required