AMENDMENT 0002.pdf
PDF 42 KB Posted
- Attached to
- DESIGN-BUILD (DB), P-1254 MOBILE AVIATION MAINTENANCE FACILITY POWER UPGRADES, MCAS BEAUFORT, SC
- Solicitation number
- N40085-19-R-9179
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0003 Attachment.pdf | ||
| Attachment D - Price Proposal Form P-1254.pdf | ||
| 2020_1562038_P1254 Final Volume II.pdf | ||
| 2020_1562038_P1254 Final Volume I.pdf | ||
| Amendment 0001.pdf | ||
| Attachment C - Past Performance Questionnaire.docx | DOCX document | |
| N4008519R9179.pdf | ||
| Attachment B - Construction Design Exp.docx | DOCX document | |
| Attachment A - PPI log.doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to issue the Phase II Solicitation, provide Plans and Specifications, and incorporate applicable WD General Decision.
Phase II proposals and responses to Evaluation Notices are due on 28 July 2020 at 2:00 PM (EST).
See Section SF 30 Block 14 Continuation Page
The follow ing documents have been included in this amendment:
P-1254, Mobile Aviation Maintenance Facility Pow er Upgrades, Marine Corps Air Station, Beaufort, SC Final RFP Wage Determination, General Decision Number SC20200008 01/03/2020 Attachemnt D - Price Proposal Form
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9179
X 9B. DATED (SEE ITEM 11)
16-Jan-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Jun-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9179
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
THIS AMENDMENT IS ISSUED TO INITATE PHASE II. ONLY OFFERORS SELECTED SHALL
SUBMIT PROPOSALS FOR PHASE II.
PROPOSAL DUE DATE: Tuesday, 28 July, 2020 at 2:00 p.m. (EST)
PROPOSAL SUBMISSION INSTRUCTIONS: SEE PROPOSAL SUBMISSION INSTRUCTIONS INCLUDED
IN THE ORIGINAL SOLICITATION. The evaluation factors, including both non-price/technical and price submittal requirements are available in the original Request for Proposal document (and any applicable amendments) and have not been reproduced in this amendment.
(See N40085-19-R-9179 for Phase II Evaluation Factors and Submittal Requirements).
PRICE FACTOR submission instructions begin on page six (include all information in the “Additional information to be submitted with Price Proposal Package (PHASE II).
Attachment D - Price Proposal Form is included in this amendment notice.
NON-PRICE FACTORS submission instructions begin on Page 13 (Factor 5).
Proposals shall be sent as an electronic version only via to Brittany Cristelli through DOD SAFE or email at brittany.cristelli@navy.mil.
PRE PROPOSAL INQUIRIES (PPIs): See original solicitation. PPI Form is within the additional documents. PPI cutoff is Tuesday, 14 July 2020 by 2PM EST.
SITE VISIT INFORMATION: No site visit will be conducted. In lieu of a site visit, photos of the site have been provided on pages 366 through 374 of the RFP.
SECTION 00 10 00 - SOLICITATION
CLIN 0001 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
BASE PRICE
FFP
FOB: Destination
PSC CD: Y1MG
NET AMT
CLIN 0002 is added as follows:
OPTION Option 1
FFP
Price for construction and design of 500 Kilowatts AC of Photovoltaic Array (1,470 Panels) including Inverters and Equipment to Connection Point, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001, 0003, 0004, 0005 and 0006.
CLIN 0003 is added as follows:
OPTION Option 2
FFP
Price for construction and design of a 1 Megawatt/1 Megawatt-hour of Lithium Ion Battery Storage, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001, 0002, 0004, 0005 and 0006.
CLIN 0004 is added as follows:
OPTION Option 3
FFP
Price for construction and design of a second 1 Megawatt/1 Megawatt-hour of Lithium Ion Battery Storage, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001, 0002, 0003, 0005 and 0006.
CLIN 0005 is added as follows:
OPTION Option 4
FFP
Price for construction and design of a third 1 Megawatt/1 Megawatt-hour of Lithium Ion Battery Storage, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001, 0002, 0003, 0004 and 0006.
CLIN 0006 is added as follows:
OPTION Option 6
FFP
Price to include Demolition, Disposal and Replacement of Poles and Pole Mounted Luminaires on Facility 1254 Van Pad, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0001, 0002, 0003, 0004 and 0005.
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following Acceptance/Inspection Schedule was added for CLIN 0001:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
N/A N/A N/A Government
The following Acceptance/Inspection Schedule was added for CLIN 0002:
The following Acceptance/Inspection Schedule was added for CLIN 0003:
The following Acceptance/Inspection Schedule was added for CLIN 0004:
The following Acceptance/Inspection Schedule was added for CLIN 0005:
The following Acceptance/Inspection Schedule was added for CLIN 0006:
SECTION 01 00 00 - GENERAL REQUIREMENTS
The following have been added by full text:
WAGE DETERMINATION
"General Decision Number: SC20200008 01/03/2020
Superseded General Decision Number: SC20190008
State: South Carolina
Construction Type: Building
County: Beaufort County in South Carolina.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020
* ELEV0032-002 01/01/2019
Rates Fringes
ELEVATOR MECHANIC................$ 41.36 33.705
PAID HOLIDAYS:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Vetern's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.
b. Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.
SUSC2011-004 08/31/2011
Rates Fringes
CARPENTER, Includes Form Work....$ 15.96 0.00
ELECTRICIAN......................$ 18.33 0.00
LABORER: Common or General......$ 10.61 1.27
LABORER: Pipelayer..............$ 12.50 1.23
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 19.14 2.62
PAINTER: Brush, Roller and Spray............................$ 13.50 0.00
PIPEFITTER.......................$ 19.75 2.80
PLUMBER..........................$ 17.20 2.65
SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 19.15 1.15
TRUCK DRIVER.....................$ 13.50 1.27
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
(End of Summary of Changes)