Amendment 0001.pdf
PDF 151 KB Posted
- Attached to
- DESIGN-BUILD (DB), P-1254 MOBILE AVIATION MAINTENANCE FACILITY POWER UPGRADES, MCAS BEAUFORT, SC
- Solicitation number
- N40085-19-R-9179
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0003 Attachment.pdf | ||
| Attachment D - Price Proposal Form P-1254.pdf | ||
| 2020_1562038_P1254 Final Volume II.pdf | ||
| AMENDMENT 0002.pdf | ||
| 2020_1562038_P1254 Final Volume I.pdf | ||
| Attachment C - Past Performance Questionnaire.docx | DOCX document | |
| N4008519R9179.pdf | ||
| Attachment B - Construction Design Exp.docx | DOCX document | |
| Attachment A - PPI log.doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5668396
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION NO. N40085-19-R-9179, DESIGN-BUILD (DB), P-1254 MOBILE AVIATION MAINTENANCE FACILITY POWER UPGRADES, MARINE CORPS AIR STATION (MCAS), BEAUFORT, SOUTH CAROLINA
The purpose of this amendment is to provide responses to pre-proposal inquiries (PPI's) for Phase I.
The Phase I proposal due date of 18 February 2020, NLT 2:00 PM EST remains unchanged.
See Continuation Page(s).
1. CONTRACT ID CODE PAGE OF PAGES
1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Jan-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9179
X 9B. DATED (SEE ITEM 11)
16-Jan-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Jan-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9179
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
Contractor
PPI#
Section of RFP or Page Number
Paragraph Reference
Drawing Number
Question RESPONSE AMENDMENT
1 Pg. 5 4 NA What is the expected time gap between the Phase I due date of Feb. 18th and Phase II due date?
The gap between the Phase I due date and Phase II due date is variable based upon the workload of the command.
A Phase II proposal due date will be established once it is issued.
2 Pg. 8 4 NA If we intend to perform all of the design/drawing work in house but will send the drawing set to an outside engineering firm for seal will that company need to be listed as a primary design firm?
Propose according to the RFP.
3 Pg. 14 10 NA Will drawings for this project be posted before the Phase I due date?
Drawings will be published with the issuance of Phase II.
4 NA NA NA When is the project expected to be awarded?
Project is expected to be awarded at the end of fiscal year 20.
5 9 00 21 16 Factor 2 - Experience
Given the Small Business Set-aside Status of this project and the highly specialized nature of the scope of work for this project. We request the government consider Key Sub Contractor Experience allowable in response to Factor 2 - Construction Experience provided the Offeror provides an unequivocal letter of commitment / teaming agreement from the Key Subcontractor in a similar fashion as is already allowed for designers experience.
Propose according to the RFP.
6 9 of 42 (2) (i) (1) The restrictions placed on use of subcontractor projects for construction, combined with the restrictive requirements for a JV/Teaming relationship, limits the amount of competition for qualified small businesses to submit a proposal.
Currently, a company may have completed 500+ MW solar installations with Batteries and still not be able to qualify.
Reliance would like to request that a subcontractor’s experience be permitted in a Teaming/JV relationship as the Offeror. Can the solicitation be amended to reflect that change?
Propose
7 9 of 42 (2) (i) (1) In addition, can there be consideration made to strike the language “Experience of proposed subcontractors will NOT be considered for Construction Experience.
Likewise, the Government will NOT consider the offeror’s experience as a subcontractor” and replace it to state that a Team Member and or Joint Ventures experience WILL be considered for Construction and Design Experience for Factor 2 and Factor 3?
Propose
8 9 of 42 (2) (i) (1) The Solicitation requests that documentation be provided for projects that have been validated and/or certified through the USGBC or other similar organization.
Typically, utility scale renewable generation and/or battery storage systems can provide contribution toward certification but alone do not satisfy requirements for
LEED
certification, etc.
To what extent is and/or will this information be used for the purpose of the Basis of Evaluation?
Propose according to the RFP.
9 SF1442 13 N/A Is a bid bond required for the phase 1 submission? If required, what is the amount of the bid bond?
Bid Guarantee will be required for submission of a Phase II proposal. The amount will be provided in the requisite FAR Clause.
10 Page 11, Factor 3-Past Performance (i)
Paragraph 1 (i)
N/A If we are submitting a design-build project under Factor 2- Experience, do we have to submit 2 separate past performance questionnaires (Factor 3) for the design phase and the construction phase or can we submit one single PPQ for the overall design-build project?
Submit past performance information in the form of PPQ's or CPARS for the construction experience and for design experience separately.
11 Page 9, Factor 2- Experience (1) Construction Experience
Paragraph 1 (1)
N/A Can you consider lowering the final construction cost requirement of $3 M or greater to $1.5 M or greater? Or to $2M or greater?
Propose according to
(End of Summary of Changes)