AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Apr-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9014

X 9B. DATED (SEE ITEM 11)

12-Mar-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Apr-2019

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

The purpose of this amendment is to provide the following information:

I. Pre-Proposal Inquiry (PPI) Responses.

II. Provide specification revision III. Provide clarification on the Cooling Towers IV. Provide FAR 52.228-1 in full text.

V. The proposal due date and time remain unchanged.

I. Pre-Proposal Inquiry Responses: All PPI responses to Design Package #1 and the Solicitation have be provided at this time.

Reference Question

Government Response

PPI # Page/Dwg

Section Paragraph

Is it possible, that before the 100 % drawings are issued, a set of drawings with the changes redlined be issued so the contractors can see what was changed and adjust their takeoff accordingly. These changes could possibly affect several tiers of subcontractors and suppliers.

Bid Per RFP

1 01 11 00 1.2.1 Section 01 11 00 Paragraph 1.2.1, describes the task for base bid and option 1. base bid drawings are issued as 100% and does not have anything on them for the cooling towers as discribed in task 7,8 and 9 is this work going to be included or accomplished in the base bid?

See Amendment

49 100a Caisson construction Specification section 100a (SWBS pg. 49) calls for hull structure shop drawings to be signed and sealed by a professional engineer registered in the State where the project is located. Will NAVFAC accept hull structure shop drawings signed and sealed by a professional engineer from any state if that professional engineer has previous caisson engineering experience?

See Amendment

01 14 00.00

1.5.6 3. On the Special Project RM12- 1896 for eProjects No. 1369059 Specification, under Section 01 14

00.00 22 WORK RESTRICTIONS

item 1.5.6 Working Hours, it is noted:

“Regular working hours must consist of an 8 ½ hour period, between 7 a.m. and 3:30 p.m., Monday through Friday, and 7 a.m. to 11 p.m. on Saturday, excluding Government holidays.”

Under Section 01 14 00.00 22, Saturday, Sunday and Federal Holidays are noted as non-working days:

1.5.9 Utility Cutovers and

Interruptions “Make utility cutovers after normal working hours or Saturdays, Sundays, and Government Holidays unless directed otherwise” and Section 01

32 17.00 20 COST LOADED

NETWORK ANALYSIS

SCHEDULE (NAS) item 1.10.2.5.5 Construction Activities:

"No on-site construction activity may have a duration in excess of 20 working days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, unless otherwise defined in this contract."

Please clarify if Saturdays are are considered a regular work day or is it a restricted work day?

See Amendment

7 a. Price i. Can the Navy provide Section

52.228-1?

See Amendment

Is the construction of the cooling towers included in Design Package 1 or Design Package 2?

See Amendment

Are all of the previously asked questions related to Design Package 1 going to be answered prior to the submission of the Non-Price Proposal?

See Amendment

II. Specification Revision

SECTION 01 14 00.00 22 WORK RESTRICTIONS

1.5.7 Work Outside Regular Hours

Delete the last sentence of the paragraph.

1.5.9 Utility Cutovers and Interruptions

Replace the first sentence of Paragraph 1.5.9.a. with the following:

“Make utility cutovers and interruptions on Saturdays, Sundays, Federal Holidays or after regular working hours as defined in paragraph WORKING HOURS, on Mondays through Fridays, unless directed otherwise.”

SECTION 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

1.10.2.5.5 Construction Activities

Delete “Saturdays,” from the first sentence.

1.10.2.8 Anticipated Weather Lost Work Days

Delete “Saturdays,” from the first sentence of the first paragraph.

1.10.2.9 Anticipated Restricted Delay

Delete “Saturdays,” from the second sentence.

1.10.3 Schedule Software Settings and Restrictions

Replace paragraph 1.10.3.d.(5).(d) with the following:

“(d) Calendar: Calendar must reflect Sunday and all Federal holidays as non-work days. Alternative calendars may be used with Contracting Officer approval.”

SWBS SECTION 100 HULL STRUCTURE

100a. GENERAL

Replace the second sentence of the fifth paragraph with the following:

“Fabrication drawings must be signed and sealed by a professional engineer.”

III. Provide clarification on the Cooling Towers

Cooling tower drawings will be issued via amendment to Bidders in early June. The cooling tower work will be included as part of the Base Bid.

SECTION 00700 - CONTRACT CLAUSES

The following have been modified:

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

(End of Summary of Changes)