Amendment_0006.pdf
PDF 276 KB Posted
- Attached to
- DESIGN-BID-BUILD P1901 DLA CONSOLIDATED WAREHOUSE, PORTSMOUTH NAVAL SHIPYARD, KITTERY, ME
- Solicitation number
- N4008519R9002
About this file
Amendment_0006.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0010.pdf | ||
| Amendment_0009.pdf | ||
| Amendment_0008.pdf | ||
| Amendment_0007.pdf | ||
| Section_07_81_00_-_Spray-Applied_Fireproofing.pdf | ||
| Amendment_0005.pdf | ||
| Amendment_0004.pdf | ||
| Site_Visit_Sign_In_Sheet_N40085-19-R-9002.pdf | ||
| Amendment_0003.pdf | ||
| Amendment_0002.pdf | ||
| Name_List_Attachment_for_Local_Visitor_Request.xlsx | XLSX spreadsheet | |
| DBIDS_Access_Request_Form_(5500).docx | DOCX document | |
| Base_Access_Pass_Registration_(5512).pdf | ||
| Amendment_0001.pdf | ||
| N4008519R9002.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
P-1901 DLA Consolidated Warehouse, Portsmouth Naval Shipyard, Kittery, ME
The purpose of this amendment is to provide responses to Pre-Proposal Inquiries.
The proposal due date of 04 April 2019 remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Mar-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9002
X 9B. DATED (SEE ITEM 11)
22-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Mar-2019
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
Page Section Para.
85 3/6/2019
RFP ‐
14 of
(1)(i) 1st Par With project acceptability range being 10 years, some points of contact may no longer be available to prepare PPQs with acccuracy. Please consider allowing previously completed PPQs to be utilized.
Offerors may utilize previously submitted PPQs. The RFP only directs offerors to not include them by reference.
86 3/6/2019
RFP ‐
11 of
(1) (i) (d) This Factor 1 Corporate Experience item (d) is requesting projects of similar size ($8M) and scope (warehouse) to have passive Radon Gas mitigation systems. Based on the drawings provided (i.e. P‐102, P‐ 501, and S‐501 detail A4), the radon mitigation for this project does not appear to be complicated. Having past projects demonstrate this appears to be a very niche and small area of the construction details and makes finding past projects with similar work very difficult to locate. Suggest eliminating this Corporate Experience requirement.
The Corporate Experience Solicitation Submittal requirement has been modified. (d) Construction/Installation of passive Radon Gas mitigation systems has been removed from Factor 1
87 3/6/2019
RFP ‐
11 of
(1) (i) (c) This Factor 1 Corporate Experience item (c) is requesting projects of similar size ($8M) and scope (warehouse) to have design and installation of heavy materials storage automated racking systems. This work is very specialized and not common for construction contractors to have a lot of these types of j hi k i l i d bid i
Due to the specialized nature of this project the experience requirement cannot be eliminated.
Question No. Date Received
REFERENCE
QUESTION GOVERNMENT RESPONSE
88 3/6/2019
ATT D ‐
1.2 (e) The government is requesting Contractor and specialty subcontractor to hold pricing on an undesigned specialty automated material handling, storage, and retrieval system for 365‐days from contract award, which is up to 120‐days after proposal submission. This is an incredibly long time to ask contractors to hold their pricing and will result in considerable risk allowances for escalation and unknowns related to the 8‐page specification section 41 associated with this work. Request reducing the 365‐day period to 150‐ days, after which time the contractor should be complete with the design Option 2, if awarded, and government should know if they will be interested in purchasing this option.
It is the government's intent to award CLIN0004 after the design period is complete as part of CLIN0003 which should provide enough time for the manufacture and installation of the ASRS within the contract time frame.
Offerors will be required to comply with the pricing provided in the option CLINs for the full option period.
89 3/6/2019
ATT D ‐
1.2 (e) In addition to the previous two questions, there are LDs associated with option 3 that also complicate this situation. If the government waits up to 365‐days to award option 3, there will only be 217 PoP days remaining. This is not "off the shelf" equipment and will not be enough time to procure, fabricate, deliver, install, and test the automated material handling system. If the government does not change the 365‐ day period, should contractors assume LDs will apply based on their schedules and include these costs at $3950/day as part of Option 3? Alternatively, LDs associated with Option 3 should be eliminated or re‐ evaluated with the award of Option 3. Please advise.
It is the government's intent to award CLIN0004 after the design period is complete as part of CLIN0003 which should provide enough time for the manufacture and installation of the ASRS within the contract time frame.
Any delay to the completion of CLIN0004 work caused by government inaction can be evaluated at the time of CLIN0004 award.
90 3/7/2019
Attach ment F
1.2 CLIN 00004 ‐ 1.2.e General Notes:
The lead time for a complex material handling system is approximately 18‐22 weeks to deliver. The government has up to 365 days to award the option to furnish & install. This would leave less than 60 days allowance for the installation, testing, inspection and owner training prior to red zone activities. We request either the time to award be less than 365 days or provide a contract duration extension option.
It is the government's intent to award CLIN0004 after the design period is complete as part of CLIN0003 which should provide enough time for the manufacture and installation of the ASRS within the contract time frame.
Any delay to the completion of CLIN0004 work caused by government inaction can be evaluated at the time of CLIN0004 award.
91 3/8/2019 To provide the Government with a comprehensive and cost effective proposal for the building and material handling system, we request the proposal due date be extended to April 9, 2019.
Please see amendment 0005, which extends the proposal due date to 04 April 2019 at 2:00 EDT.
92 3/8/2019
B‐100
Det. A4 It is not clearly stated if existing soils should be removed to suitable rock elevation for slabs on grade, particulary the 21" slabs. Please clarify if existing soils should be removed to rock for slab areas as well as foundation locations.
Bid per RFP. See 31 23 00.00 20 for Subgrade Preparation requirements.
93 3/13/2019 04 20
2.6.6.7 Spec Section 04 20 00, para. 2.6.6.7 says to “provide rigid board‐type insulation as specified in Section 07 21 13 Board and Block Insulation”. This spec section is not included in the project specifications. Please clarify the product required and size of the insulation being used in the masonry cavity.
Provide 2" rigid insulation board.
94 3/13/2019
A‐501
B3 & C3
Detail B3/A‐501 shows a steel angle beneath the precast cap. Enlarged Detail C3/A‐501 does not show the angle. The angle is also emitted from Structural Detail A1/S‐512. Please clarify if a steel angle is required at this location.
Detail A1/S‐512 is correct, a steel angle is not required.
95 3/13/2019
A‐502
A1 & A2
Detail A1/A‐502 shows two 4” CMU half block, with a CJ between them, being used to get past structural steel columns. Please clarify how this detail should be installed on the next course to tie into the abutting 8” CMU. Will there be a straight joint on each side of the 4” CMU where they meet the 8” CMU ?
Details should be as shown on C1/S‐
503. Continuous CMU break @ column should be filled with rigid insulation.
96 3/13/2019 Please provide elevations for brick shelfs in the foundation walls and indicate locations where steps occur.
Steps in the foundation walls and the elevations at the top of the foundation wall are indicated on the structural drawings.
97 3/13/2019
11 &
07 42
2.1.1 & 2.1.2
The Specification for the insulated metal wall panels call for 0.040 inch aluminum faces. We have checked with several leading manufacturers and they are all limited to a steel faced panel. Please provide a basis of design for the IMP.
Federal acquisition regulations prevent release of a basis of design.
98 3/13/2019 83323 3.3.1 2‐yr warranties are typical for doors and components but this section is requesting 5‐yr warranty. Will a 2yr warranty be acceptable?
Provide 5‐year warranty as specified
99 3/13/2019 Drwgs
41 50 13.00
Can NAVFAC make CAD files available to the bidders for purposes of the Automated Material Handling Systems and Equipment Design?
CAD floor plans can be made available for the use of the ASRS designer
100 3/14/2019
N/A
N/A N/A Will the successful bidder be provided with a tax exempt certificate that can be flowed down to subcontractors?
The Department of the Navy does not fill out tax excemption forms nor does it provide tax exempt numbers, however, the Navy can provide a letter with the contract information to provide to the state revenue office.
101 3/14/2019 N/A
N/A N/A Will the successful bidder be provided with the Navy's ACAD drawings?
CAD drawings can be made available to the sucessful bidder
102 3/15/2019
11 &
07 42
2.1.1 & 2.1.2
We had previously expressed concern on obtaining aluminum faced insulated metal wall panels. We may have found a manufacturer who can produce the panels in limited lengths and profiles. The manufacturer of the existing panels on Building 170A, Metal‐Span, will not produce with aluminum faces so we once again request the Navy to change the specifications to a galvanized steel or galvalume substrate.
An alternative galvanized metal panel is acceptable to replace the aluminum panel as long at it meets the dimensional, finish and profile requirements to match the existing building 170A. Alternate panel information must be submitted to architect for review and approval prior to ordering.
103 3/15/2019 07 22
2.5.1.1 Specification Section 07 22 00, 2.5 MOISTURE
CONTROL, 2.5.1 Vapor Retarder, 2.5.1.1 Asphalt Saturated Felt Base Sheet for Single Layer Application:
Provide in accordance with ASTM D4601/D4601M, weighing not less than 35 pounds per 100 square feet.
A hot asphalt vapor barrier would not be included in any metal roof manufacturer’s warranty. No testing information is available for its use with a metal roof system. After installed this system will be penetrated with fasteners for the remainder of the assembly and then pressure tested. In talking with the roofing manufacturers there is no evidence this would pass a pressure test. Can you please adjust the specification.
The 35 lb felt is installed to act as a vapor retarder and slip sheet under the metal panels. This is not intended to be a hot aphalt application.
104 3/15/2019 07 42
2.1.1 The Specifications call out roll‐form aluminum insulated wall and liner panels to the specified profile, with fy = , .040 thickness as indicated. Material must be plumb and true, and within the tolerances listed: a. Aluminum Sheet conforming to ASTM B209, AA ASD1 and AA ADM. b. Individual panels to have continuous length to cover the entire length of any wall area with no joints or seams and formed without warping, waviness, or ripples that are not part of the panel profile and free of damage to the finish coating system. Panel lengths must span 40'‐0". Module widths must be 30", 36" and 42". Panel thickness to be 3" The longest aluminum panel offered in the industry is 24’‐0”. Plesae clarify how we should bid project.
Provide longest panel lengths available. Panels may contain vertical stack joint per detail D2/A503.
105 3/15/2019 07 61 14.00
2.2 & 3.3.1 Paragraph 2.2 Roofing Panels state the individual sheets must be sufficiently long to cover the entire length of any unbroken roof slope when such slope is 30 feet or less. Provide panels that extend over two or more spans when length of run exceeds 30 feet. This contradicts paragraph 3.3.1 Roof Panels: Provide roofing panels in longest practical lengths from ridge to eaves (top to eaves on shed roofs), with no transverse joints except at the junction of ventilators, curbs, skylights, chimneys, and similar openings. Do they want transverse seams or continuous length panels?
Provide roofing panel lengths per paragraph 2.2 requirements.
106 Electrical Drawing E‐501 detail A1 directs three (3) 12 strand single mode fiber to be routed from the Telecom room in the new building to BLDG 170 6th floor telecommunication room. No detail is provided for the location of the 6th floor telecommunication room or routing of these fiber runs. Please provide a detail of the location, elevation and proposed routing for these fiber optic cables to the BLDG 170 6th floor telecommunication room .
The exact routing from the new telecom room to the B170 6th Floor telecom room will be discussed after project award.
107 The response to Amendment 3, question 21, references attached special inspection forms, but it does not appear that these forms were attached.
These forms are attached as a part of this amendment.
108 The response to Amendment 3, question 34, states that the proposed fall protection system shall match the fall protection devices located on existing building 170A.
Please identify the fall protection devices on Building 170A or schedule access to the roof for contractors to investigate. With no further information, contractors cannot determine what type of product to include in their proposals.
Existing fall protection system consists of a horizontal lifeline cable system anchored to the building roof.
109 Please provide a specification for the spray applied fire resistant material, to be applied to steel where shown on drawings.
See attached specification section 07 81 00
110 3/15/2019 41 50 13.00
Please specify what should be included for the Automated Material Handling and Retrieval System for CLIN 0002, Option 1 Eight Foot Height Increase and how should the additonal Design, Procurement/Install be indicated? Should there be a separate CLIN and Option for each of the Material Handling items?
Rack system is intented to store all materials listed at the base bid roof height. If CLIN0002 is to be excercised, rack system height can be increased by 8', if allowed by system capability, to meet storage requirements if needed.
111 3/15/2019
FX‐
8 Note 8 states "Provide 8" pipe with flanged connection for rack sprinkler system 40 feet from system riser. In‐ rack sprinkler system to be provided by automated material handling contractor" Typically sprinkler systems are designed and installed as a whole system by one certified sprinkler system subcontractor. Should this be re‐stated to say, "Sprinkler system installer to coordinate in‐rack sprinkler system requuirements and installation with final rack layout provided by material handling contractor"? NFPA code requires total fire suppression system designer , calculations and installatio to be submitted by one fire suppression design/installation contractor.
Entire building including rack areas should be protected by building fire protection system. UFCs requires a supplimental in rack system so if an integral in rack sprinkler system is not a part of the rack system priced by the contractor then an rack sprinkler system will need to be provided by the contractor to meet IBC, NFPA and UFC requirements.
112 3/15/2019 85113 2.3.9 What is the expected window finish to be? Windows should be a baked on enamel finsih to match the windows on the adjacent building 170A
113 3/15/2019 85113 2.4 Is the intent of the aluminum windows to be fixed?
Spec Section 08 51 13 section 2.4 is describing different types of opereators.
Yes, windows are to be fixed and match the windows in building 170A
114 3/15/2019 85113 2.5 Please clarify exactly what type and brand of aluminum windows they have specified. They call out “Thermal‐ Barrier Windows” but it is unclear if that is a type or brand.
Federal acquisition regulations prevent specifying a brand but the windows should match the windows installed in the adjacent building 170A
115 3/15/2019 87100 3.6 Hardware Set #5 list doors 103b & 103 C but the door schedle does on those doors listed. Please clarify.
Doors 103B and 103C were changed to doors 103I and 104 and should get hardware set 5 as specified in section 08 71 00
116 3/15/2019
A‐ 302A
Sheet A‐302A Detail A5 Section 11 is call for a fire rated ceiling, see partition type I501 on A4/401. This does not exist on A‐401A. Should this read Type L524 on C2/A401A?
Yes, ceiling detail is UL‐L524, detail C4/A‐401
117 3/15/2019
A‐ 306A
Sheet A‐306A Detail 1 Section 37 is call for a fire rated ceiling, see partition type U415on C1/401. This does not exist on A‐401A. Should this read Type U490 on C1/A401A?
Ceiling detail should be U490 as shown on in C1/A‐401
118 3/15/2019 42000 The exterior CMU wall behind the brick veneer is shown in multiple details in the drawings. In most details it is referred to as “CMU Wall”, “8 inch CMU Wall”, or “CMU Backup Wall”. Detail C5/A‐302, it is labeled as “3 Hour Firewall”. Please clarify if the exterior CMU is required to have a 3hr rating.
The standard exterior CMU wall does not need to be rated but the full height CMU wall between the new work and building 170A will need to be grouted soild and constructed using the UL approved techniques as outlined in UL‐U901.
119 3/15/2019 42000 In all details showing the exterior CMU wall behind the brick veneer, it appears to be grouted solid similar to the interior double CMU firewall. None of the details specifically label it as grouted solid. Please clarify if the exterior CMU wall behind the brick needs to be grouted solid, or only grouted at reinforced cells.
Non‐rated exterior walls should be grouted per the structural drawings and details.
120 3/15/2019 85113 What is the standoff distance for Charge Weight I and Charge Weight II
Since the building has less than 11 occumpants, it is not required to comply with UFC 4‐010‐01.
121 3/15/2019 85113 What is the GSA/ISC blast resistance criteria PSI pressure requirement?
Since the building has less than 11 occumpants, it is not required to comply with UFC 4‐010‐01.
122 3/15/2019 85113 What is the GSA/ISC blast resistance criteria PSI‐MSEC impulse or MSEC duration requirement?
Since the building has less than 11 occumpants, it is not required to comply with UFC 4‐010‐01.
123 3/19/2019
LS101
The Life Safety Plan shows four feet of the existing exterior wall of Building 170A to be 1‐Hour rated in two locations. There are no architectural details to add rating to this wall. Please clarify if the existing construction is already rated or what additional work must be undertaken.
Existing walls must be rated by adding a 1hr rated UL‐U415 wall inside of the existing construction, as shown in detail C5/A‐302
124 3/19/2019
A‐ 302A
C5 The exterior CMU wall behind the brick veneer is shown in multiple details in the drawings. In most details it is referred to as “CMU Wall”, “8 inch CMU Wall”, or “CMU Backup Wall”. In Detail C5/A‐302, it is labeled as “3 Hour Firewall”. LS101 does not indicate any of the exterior CMU being rated other than the four foot, 1‐ Hour, sections abutting the existing building. Please clarify if any of the exterior CMU is required to have a 3hr rating.
The standard exterior CMU wall does not need to be rated but the full height CMU wall between the new work and building 170A will need to be grouted soild and constructed using the UL approved techniques as outlined in UL‐U901.
125 3/19/2019 In all details showing the exterior CMU wall behind the brick veneer, it appears to be grouted solid similar to the interior double CMU firewall. None of the details specifically label it as grouted solid. Please clarify if the exterior CMU wall behind the brick needs to be grouted solid, or only grouted at reinforced cells.
Non‐rated exterior walls should be grouted per the structural drawings and details.
126 3/19/2019
03 35 00.00
3.3.3 The Concrete Finishing Specification specifies a
superflat floor for the area that houses the automated storage system, which we interpret as the area called out by keyed note [4] on S‐101. The balance of the specifications and the drawings are not supportive of superflat floor construction. Please provide a complete specification for superflat slab construction.
Floor should achieve superflat finish of level of 60 as defined by ACI 117.
127 3/19/2019
03 30
3.9.2 The specified flat floor finishes of Ff30 and Fl 25 may be appropriate for the eight inch slab areas but are not suitable for the (assumed) superflat slab. Superflat slabs are held to a tighter tolerance and also measured in a Fmin value per a specialized tolerance system.
Please advise.
Floor should achieve superflat finish of level of 60 as defined by ACI 117.
128 3/19/2019
A‐306
C5 Section C5/A‐306 shows the ceiling/roof construction over Vestibule 104 as framed with cold formed metal framing and finished with gypsum board, top and bottom. Section C4/S‐504 shows metal roof deck and a single channel with no other finishing details. Please clarify.
Finish ceiling per architectural details to acieve fire rating.
129 3/19/2019 C5 The existing CMU wall with brick veneer will need to be removed for the construction of Vestibule 104. There are no details for a new header to support the remaining masonry overhead. Please provide detail.
Refer to bond beam lintel schedule sheet S‐503
130 3/19/2019 31 23 00.00
Spec Section 31 23 00.00 22 includes requirements for Archaeological Monitoring. Understanding that this project site is be a contributing resource to the PNS NRHP‐ Eligible district, please confirm it is the contractors responsibly to include any required Archaeological Monitoring required as part of their proposed price for this project.
Confirmed, it is the contractors responsibility to include any required Archaeological Monitoring.
131 3/19/2019 Geotech report 6.9 & 6.10 contemplates the need for Permanent Excavation Support Systems to support the existing structure and slope during construction. No mention or design for this has been included in the rest of the design documents. Please confirm this is intended to be delegated design submittal required to be provided by the contractor.
For information only: This recommendation was based on an earlier design concept. Provide temporary shoring as required to facilitate construction.
132 3/19/2019 Section 01 35 26.00 22 Requires a Site Safety Health Officer. Section 01 35 29.13 22 references both the SSHO and a Safety and Health Manager role. As they have differing qualifications, please confirm that these are 2 separate roles being described.
Yes, these whould be two separate roles.
133 3/19/2019 00 21
Proposal delivery Information indicates that hardcopies of proposals shall be delivered for this bid with the exception of the Attachment D Price Proposal Form which can be submitted via email. Would the government consider allowing the Small Business Subcontracting Plan to be also submitted at the same time as the Attachment D Price Proposal Form via Email? This document needs to coordinate with the Price Proposal which will be actively evolving up until it is submitted. If the Small Business Subcontracting Plan is required to be submitted in the hard copies ahead of time there is potential for this to be out of sync with the Attachment D Price Proposal Form.
The Small Business Subcontract Plan can be submitted electronically with the Price Proposal Form via Email.
134 3/19/2019 01 45 00.00
Section 01 45 00.00 20 ‐ 1.4.5. Contemplates a Underwater QC team requirement. As this contract is not anticipating the need underwater work, please remove this requirement from the contract.
This requirement can be omitted from this project.
135 3/19/2019
CU100
Note 14 Note 14 directs the contractor to lower 2 existing valves and provide a new valve box if necessary. No information is provided related to these existing valves..
Size? Location? Type? Condition?
Existing valve information is unknown.
Assume valve detail which is located on C4/CU500.
136 3/19/2019 Section 01 35 26.00 22 ‐ 3.2 requires 15 day advanced notice for utility outages.
Section 01 11 00 ‐ 1.6.1 requires 145 day advance notice for utility outages.
Please confirm the correct duration for advance notice on outages and revise specs accordingly.
15 days advanced notice is required for utility outages.
137 3/19/2019 01 11
1.8.1 Section 01 11 00 ‐ 1.8.1 obligates the contractor to
accommodate NMCI contractor access to the project.
This section notes "coordination is required for the following items:" but no items are listed. Please confirm that it is the governments intent that the contractor should assume no coordination is required with the NMCI Contractor.
Paragraph should read: coordination is required for the installation of all NMCI voice and data lines and equipment.
138 3/19/2019 01 35
The NAVFAC PWD Maine outage request form included in the RFP indicates it is to be used for Roads, Rails, Cranes in addition to utilizes. The RFP provides advance notice durations for utility outages but not all outages included on this form. Please confirm that all outages noted on this form will require advance notice. Also please provide the required advance notice if it is different from other utilities.
All outages will require 15 days advanced notice.
139 3/19/2019 01 11
1.2.1 Section 01 11 00 paragraph 1.2.1. remains unedited. Paragraph should read: This work includes the construction of a high bay warehouse building as described in the following specs and detailed in the drawings and incidental related work.
140 3/19/2019 01 30
1.7.2 Section 01 30 00 ‐ 1.7.2 notes that the initial partnering session will be hosted by either the Contracting Officer or the Contractor. Please confirm will the government provide the location for this requirement or should the contractor assume it is their responsibility?
Government will provide location for the initial partnering session.
141 3/19/2019 01 11
1.3 It is understood that B170 is and will remain occupied
during construction. A. What are the available hours of work? B. Are there any special building access protocols?
Specific hours of work will need to be coordinated with DLA but it is intended for the work area required to inside 170A to be clear and available for required work for the duration of construction.
142 3/19/2019 01 11
1.6.1 a. Please confirm that outages are to occur during "off hours" (nights and/or weekends). B. Please confirm the lead time for outages.
Outages are to occur outside of standard working hours and contractor must provide 15 days notice.
143 3/19/2019 01 11
1.9 This paragraph denotes the coordination scope of the
bridge crane on the drawings. Please provide scope and drawing location
Bridge Crane is not part of this project and references can be ignored
144 3/19/2019 01 11
1.10.1 Please provide referenced lubricant Attachment Any manufacturer recommended lubricants used will need to be confirmed with the construction manager during the submittal phase.
145 3/19/2019 01 11
1.11 Please provide referenced list of special inspections Special inspections are included in spec section 01 45 35
146 3/19/2019 01 14 00.00
1.7 This paragraph is contradictory regarding who is
responsible for moving government items out of the way for the addition (northeast corner of B170). If the Contractor is responsible, please provide an itemized list of materials and location to be moved to or an allowance to be carried for conformity of bids.
Government will be responsible for moving items for work in existing building. Space needed by the contractor will need to be coordinated with DLA at project kickoff.
147 3/19/2019 01 14 00.00
1.8 Please confirm that utility outages are limited to nights, weekends, and holidays.
Yes, utility outages should be limited to the times specified.
148 3/19/2019 01 14 00.00
1.13.4/1.17 A. Please confirm that the "optional" laydown areas are inclusive and will be available to the Ktr. B. Can these areas also be used for Ktr parking?
Yes, optional laydown areas will be available for use. Parking in this area will need to be coordinated with the base.
149 3/19/2019 01 14 00.00
1.13.8 A. What are the current laptop camera disabling
protocols? B. What are the current MIFI use protocols?
Laptop camera disabling and MIFI use can be discussed at project kickoff
150 3/19/2019 01 20 00.00
1.3 This paragraph notes that pay requisitions will be based
on a cost loaded schedule (referenced 01 32 17.00 25 denotes the same). Please confirm.
This is correct
151 3/19/2019 01 30
1.4.2 A. Please confirm this project requires a MINIMUM of
three full time and qualified "hats"; a QCM, SSHO, and Superintendent.
This is correct
152 3/19/2019 01 31 23.13
1.1 Is eCMS to be used to manage this project? Yes
153 3/19/2019 01 32 17.00
1.4 This paragraph mentions certain milestones (and
phasing is noted elsewhere) however none are specifically noted. A. Besides the standard, start, completion, and CCD, are there any other milestones to be met? B. Is Phasing to be anticipated?
Standard milestones apply and phasing is not anticipated at this point.
154 3/19/2019 01 32 17.00
1.5 Is P6 software absolutely required or can other
software be used (e.g., MS Project, Suretrak)?
This is correct
155 3/19/2019 01 32 17.00
1.6 Please confirm that a P6 consultant or subcontractor is
prohibited; scheduler must be an employee of the Ktr.
This is correct
156 3/19/2019 01 32 17.00
1.8.3 This paragraph (and other sections) discussed monthly
retention of pay requisitions. Please confirm percentage if applicable.
Retention will be discussed with the contracting officer at the project kickoff
157 3/19/2019 01 33
1.4 This paragraph references the submittal register
attachment but none can be found. Please provide register.
Submittals will be through eCMS and will be set up by the assigned construction manager for NAVFAC.
158 3/19/2019 01 33
In general, LEED is noted in several specifications. A. If this project is to follow, LEED, please provide the credit checklist, etc. B. Please provide the referenced GBI GP guideline/checklist attachments that were to be included but were not. C. Please indicate the GBI GP fees or incorporate an allowance for conformity of bids
This is not a LEED project.
159 3/19/2019 01 45
1.2 A. This paragraph mentions a list of 3rd party
mandated inspectors/inspections, however, the list was not provided. Please provide. B. List any other 3rd party mandated inspections/inspectors (e.g., soils testing, asphalt, concrete, masonry, welds, bolts, steel decks, MEP, fire, ASRS, etc). C. Please clarify the SIOR's daily, weekly, and monthly anticipated duties. E.g., Part 3 appears to denote that the SIOR needs to be present whenever the special inspector/inspection is to take place which is typically not necessary for a qualified/certified inspector. D. For conformity of bids, can the Govt provide an allowance to carry for all 3rd party inspections.
List of special inspections can be found in spec section 01 45 35.
160 3/19/2019 01 57 19.00
3.17 Are noise restrictions applicable to this project? There are no noise restrictions within normal working hour as specified by the base.
161 3/19/2019 01 58
Please clarify which, if any, part of this spec is applicable to this project.
The project sign requirements are applicable to this project
162 3/19/2019 31 23 00.00
1.5 A. Is excess non‐hazardous excess soils to be sampled
and tested by a qualified/certified individual prior to leaving the PNSY?. If so, please detail the referenced Code 106 protocols as none are noted. B. Is the Ktr or B357 responsible for the costs of transporting the excess non‐hazardous soils offsite? C. Is dewatering anticipated or working with tidal flow? If the former, can an allowance be provided for conformity of bids?
A) See Section 31 23 00.00 22 Paragraph 1.5.j. and 3.3.4 Excavated Materials Unsuitable for Backfill. B) See SS 1.5.j. C) Base bid on evaluation of the provided information and noted groundwater conditions.
163 3/19/2019 31 23 00.00
1.7.5 Please confirm if the costs for onsite archaeological
monitory of ALL excavation is to be included in the bid, i.e., he is to be present during all excavation on this project.
Confirmed.
164 3/19/2019 01 78
00.00
Section 01 78 24 00.00 20 outlines the need for eOMSI documentation. This is further confirmed by 01 20
00.00 22 ‐ 1.3.2 which contemplates a $200k value for this effort. Please confirm it is the intent of the government to enforce this requirement. Please note 01 78 24 00.00 20 references other projects beyond the Warehouse project, we assume this is an editing error and not intended to indicate that the contractor shall be responsible for this effort on other projects.
Yes, eOMSI documentation will be required for this project and this specification applies to this project only.
165 3/19/2019
CU100
New Note#5, 7, & 13: A. are there any fees associated with the CATV utility provider? B. Does the Govt have contact information for this provider? C. Due to unknown depth/location, can an allowance be provided for this CATV scope for conformity of bids?
A. Fees with the CATV utility provider are not known. B. Contact information for the CATV provider is in General Note #15 on sheet E‐001.
C. Yes.
166 3/19/2019 32 05
3.3.3/3.3.6 Please clarify/quantify the amount of mowing's and weeks of watering to clearly define when the lawn(s) are established. Or, if the Govt will make this part of their maintenance program, please indicate.
It is the contractor's responsibility to maintain and warranty the landscape for 365 days once accepted by the CM. The landscape must be installed, fully established, and maintained per specifications.
167 3/19/2019
Spec
41 2.2 The Spec para 2.2 calls for an ASRS for lumber, including a total of 564 "Lifts" that identify specific lumber, plywood, sheet metal, etc. types of materials. Drawing E‐102 shows a conceptual layout, but does not appear to include an Automated system for most of these materials. Is it the government's intent for the Contractor to in fact provide Automated systems for these materials that will be oversized and up to 5000‐ pounds each (i.e. no Manual Forklift operations required other than loading and unloading at the end‐ of‐aisle terminals)?
The intent is for the storage of these items to be fully automated except for manual operation at the end of aisle terminals.
168 3/19/2019
Spec
41 2.2 Will a proposal that only includes Manual Forklift operations under Bid Option 3 for the lumber lifts be deemed Unacceptable?
Yes, the purpose of the ASRS is to eliminate the manpower need at the facility.
169 3/19/2019
Spec
41 All Will a proposal that provides Automated Storage and Retreival Systems with significant future rack expansion capacity rank more favorably than one that solely meets the basic requirements of 564 lumber lifts and 590 pallets, but is essentially maxed out within the space provided and cannot be expanded upon? Will the Government have flexibility to open discussions with a contractor that is not low price on the base bid, but has a superior approach on the ASRS aspects of the project?
This project is lowest price technically acceptable so the main criteria for the rack will be if it meets the storage requirements specified.
170 3/19/2019
Spec
01 33
1.4 This paragraph suggests a Submittal Register is
attached, but one cannot be located in the Specification; please provide. If not presently available, can the contractor assume the Submittal Register will be provided to the successful bidder as a working Microsoft Excel file?
Submittals will be through eCMS and will be set up by the assigned construction manager for NAVFAC.
171 3/19/2019
Spec
01 33
All The specification does not identify how many days the contractor should provide the Government for submittal reviews. Please identify where this is located or advise how many business days the contractor is to allow for government reviews when developing our work schedule.
Except as otherwise decided, allow at least 15 working days for QC manager approval, 20 working days for Contracting officer approval and at least 30 days for fire protection engineer review.
172 3/19/2019
A‐401
C2 Detail Some of the details call for 2 layers of 4” insulation and some details call for R‐35 which is 6” +/‐. Which is correct?
Insualtion must meet R‐35 requirement.
173 3/19/2019
Spec
07 22
Para 2.5 2.5 MOISTURE CONTROL, 2.5.1 Vapor Retarder, 2.5.1.1 Asphalt Saturated Felt Base Sheet for Single Layer Application: Provide in accordance with ASTM D4601/D4601M, weighing not less than 35 pounds per 100 square feet. A hot asphalt vapor barrier would not be included in any metal roof manufacturer’s warranty. No testing information is available for its use with a metal roof system. After installed this system will be penetrated with fasteners for the remainder of the assembly and then pressure tested.
In talking with the roofing manufacturers there is no evidence this would pass a pressure test.
The 35 lb felt is installed to act as a vapor retarder and slip sheet under the metal panels. This is not intended to be a hot aphalt application.
174 3/19/2019
Spec
07 42
Para 2.1.1 2.1.1 Aluminum Sheet; Roll‐form aluminum insulated wall and liner panels to the specified profile, with fy = , .040 thickness as indicated. Material must be plumb and true, and within the tolerances listed:; a. Aluminum Sheet conforming to ASTM B209, AA ASD1 and AA ADM. b. Individual panels to have continuous length to cover the entire length of any wall area with no joints or seams and formed without warping, waviness, or ripples that are not part of the panel profile and free of damage to the finish coating system. Panel lengths must span 40'‐0". Module widths must be 30", 36" and 42". Panel thickness to be 3" The longest aluminum panel offered in the industry is 24’‐0”. In addition, there is no such thing as a 5.0 mil Kynar/ Hylar. What finish is desired, Kynar or Vinyl Plastisol and what thickness? Also, hard board backing is not available.
Provide longest panel lengths available. Panels may contain vertical stack joint per detail D2/A503.
Aluminum panels may be subsituted for galvanized or galvalum but the finish, profiles, etc. should match the adjacent building 170A. Alternative panels must be submitted to architect for review and approval prior to order and installation.
175 3/19/2019
Spec
07 61 14.00
Para 2.2 2.2 ROOFING PANELS; Individual sheets must be sufficiently long to cover the entire length of any unbroken roof slope when such slope is 30 feet or less.
Provide panels that extend over two or more spans when length of run exceeds 30 feet. This contradicts
3.3.1 Roof Panels; Provide roofing panels in longest
practical lengths from ridge to eaves (top to eaves on shed roofs), with no transverse joints except at the junction of ventilators, curbs, skylights, chimneys, and similar openings. Does the Navy want transverse seams or continuous length panels?
Provide roofing panel lengths per paragraph 2.2 requirements.
176 3/19/2019
PPI
#51 Follow up
PPI
Government response to PPI 51 related to Detail C4 on A‐504 is "Fixed clip to be located per roofing manufacturer's installation requirements"; if fixed clips are not required by the manufacturer, can this detail be ignored? What takes priority, the requested components called for in the specification (such as warranty), or following the Navy's drawing details?
If fixed clips are not required by a particular roof manufactuer then they can be ignored in the detail.
177 3/19/2019
PPI
#10 Follow up
PPI
The extension provided to April 2 is helpful, but will not be enough time if the answers to all PPIs are not provided by March 22; If provided after this date, please consider extending due date to Wednesday April 10th.
Responses to all PPIs will be issued by March 29th.
178 3/19/2019
PPI
#8 Follow up
PPI
The ASRS equipment will require power and communication conduits. If these are not installed subslab to designated locations prior to placement of the floor slab, the conduits will need to be run overhead, which is problematic, or the floor may need to be cut. If the government delays award of bid option 3 for up to 365 days, it would prevent these conduits from being installed before the floor slab is placed.
Should the Contractor include the costs for installation of these conduits (or similar work) as part of bid option 2 to ensure they are installed per our design, regardless of if the Navy awards bid option 3, or should the contractor assume we need to work with the warehouse facility as a retrofit where coordination of such items is not possible prior to award of bid option 3?
It is the goverments intent to award CLIN0003 for the rack design with enough lead time for the contractor to locate the slab penetrations prior to the installation of the slab. It is NAVFAC's intent for any underslab items required for the racking system to be installed at the time of slab installation.
179 3/19/2019
PPI
#8 Follow up
PPI
The lighting details in the Automated Storage Area as designed by the Navy on E‐102 are fixed pendants that mount with rigid pendant and/or yoke from bottom of roof joists in specific locations of the ceiling/roof to be positioned over the aisles. If the design of the ASRS system changes the layout of these lights because the aisles are in different locations, the lights could potentially need to be relocated. Can the conduit for the lights be installed below the GWB ceiling and/or can the contractor adjust the lighting design to a more flexible one as part of Bid Option 2?
The lighting design is to be coordinated with the ASRS system that the contractor selects per specification 26 00 00.00 20 Paragraph 1.5.1, 26 51 00 Paragraph 1.4, and General Note #2 on sheet E‐ 102.
180 3/19/2019
E‐601
Lights Fixtures A1 and B1, Note 10
These light fixtures have a mounting height of 46'‐0" for the base bid. Will the same quantity and lumen size fixtures be adequate if Bid Option 1 is awarded and the lights are mounted 8'‐0" higher, or will this be addressed as a change order if necessary?
The lighting design is to be coordinated with the ASRS system that the contractor selects per specification 26 00 00.00 20 Paragraph 1.5.1, 26 51 00 Paragraph 1.4, and General Note #2 on sheet E‐ 102.
181 3/19/2019 Sheet B300 indicates the scale is 1”=20’ however our calculated area of the building on this sheet at 1”=20’ is 13,000 sf. Please confirm correct scale.
Scale is 1:30. See ammendment for revised.
182 3/19/2019 Sheet CD100 Keynote 13 and CD101 Keynote 6 indicates that Chapel Street needs to be closed and associated work performed after hours or on weekends, however Sheet CG100 identifying the stormwater work to be completed does not reference the work needing to be performed after hours or on weekends. Please confirm specifically what activities must be performed after hours or on weekends.
CD100 Keynote 13 specifies any work that affects Chapel Street, such as the stormwater work needs to be performed after hours or on weekends.
183 3/19/2019 Reference Sheet L100 General Sheet Note 1 – are the 44 trees to be mitigated shown on sheet L100, or are they in addition to those shown?
A total of 44 trees are required.
Planting to occur within the project limits as shown on the plans and elsewhere on the installation to be determined and coordinated with the EV Department per plans and specifications.
184 3/19/2019 Reference Sheet L100 General Sheet Note 3 – which states that 16 mitigation trees are inside the project limits, whereas 18 are located elsewhere on the installation. That is a total of only 34 trees, where as General Sheet Note 1 requires 44 trees. Please clarify.
44 trees total are required.
185 3/19/2019 Reference drawing CE100, specifically the sediment pond immediately north of the building footprint, construction entrance and diversion berm. Once excavation of the building commences, these features will be within the footprint of the excavation and sideslopes. It will not be possible to manage these features during excavation. Please clarify.
The sediment pond, construction entrance and diversion berm are for the initial stages. Once excavation commences, then they will be removed as shown in CE101.
186 3/20/2019 Drawing E‐502 calls for main electrical service (secondary) conductors to be sized at 350‐KCM copper wire, which I rated for 310‐amps. The main circuit breaker for the electrical service is rated at 400‐amps.
The minimum code‐required size wire for a 400‐amp electrical service is 500‐KCM copper wire. Should this wire size be increased accordingly?
Conductor shall be increased to 500 kcmil.
187 3/21/2019 One‐line diagram on Drawing E‐501 calls for main circuit breaker in SB‐01 (which is the main for the building) to have a 400‐amp trip; however E‐601 Panel Schedule calls for this main breaker to have a 600‐amp trip.
Which is correct?
The trip setting shall be 400A with the ability to be increased to 600A if needed in the future.
188 3/22/2019 Electric Unit Heater EUH‐1 and Exhaust Fan EF‐104 appear on mechanical drawings but no wiring is indicated on the electrical drawings for these units.
Should wiring and electrical connections be added to the electrical drawings for these units?
See Enlarged Power Plan detail C1/E‐ 401 for this equipment.
189 3/22/2019 Specifications include section 321313.06 Portland Cement Concrete Paving. Please confirm what locations this specification applies to.
Site Facilities such as concrete pads used for transformers and bench.
190 3/22/2019 Sec. 03 35 00.00 10 Para. 3.3.3 Superflat Finish Paragraph 3.3.3 in spec section 03 35 00.00 10 references a superflat finish for the floor under the automated storage rack. Please confirm if the superflat finish references a floor flatness level of 60 per ACI 117.
Yes, this is correct.
191 3/24/2019 The one‐line diagram for the fire alarm system on Drawing FA601 shows a line interconnecting the new fire alarm panel to the existing fire alarm panel in Building 170 and presumably an existing connection between the fire alarm panel in Building 170 to the existing FACP in Building 170A. Since the distance to the FACP in Building 170 is unknown and since there appears to be an existing connection between 170 and 170A, is it acceptable to run interconnecting conduit and wire between the FACP in the new building and the FACP in Building 170A in lieu of running all the way back to the FACP in Building 170 (distance unknown)?
It is acceptable to connect to the Building 170A panel. Sequence of operation requriements must still be met.
192 3/27/2019 We are still receiving additional questions from subcontractors related to various aspects of the project.
Some have been submitted and are pending response.
Please consider extending the proposal due date to at least April 10th.
Proposal date has been extended to April 4th
193 3/27/2019 PPI 42 Navy's previous response to PPI 42 clarified the product to be used as mineral wool. Please also advise on how much of the cavity between the two CMU walls requires filling. A number of details throughout the drawing package showing the double CMU wall does not include the insulation, but A‐303 includes insulation layer for full wall height in details A5 and C5, as does C5 on A‐304 and C5 on A‐306. However on A‐503, details A3 and B3 only show a partial depth layer of batt insulation, without a dimension. Please clarify if the cavity between the two CMU block walls at the exterior of existing B170A need to be completely filled with batt insulation, or if only partially filled please provide guidance on to what extent.
Cavity between CMU walls at building 170A will need to be completely filled with mineral wool batt insualtion.
194 3/27/2019 Our assessment of construction schedule indicates the project will take approximately 700 calendar days to complete without any bid options and 800 calendar days with all bid options awarded. This assumes the Navy waits the full 365 days to make award of Option 3.
Will the Navy consider extending the Period of Performance accordingly?
It is the government's intent to award CLIN0004…
This is the start of the file's text. The full file is on GovTribe.