J-0200000-06_ELINS_Fill-in.xlsx
XLSX spreadsheet 67 KB Posted
- Solicitation number
- N4008519R1704
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Log_Redacted.pdf | ||
| Amendment_003.pdf | ||
| Amendment_0002.pdf | ||
| SECNAV_Form_5512-1.pdf | ||
| N40085-19-R-1704-00001.pdf | ||
| N40085-19-R-1704.pdf | ||
| SECTION_J-0200000.pdf | ||
| SECTION_J-1502000.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELINs-Base Period-Recurring
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085-19-R-1704 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Period | |||||
| PROVIDE PRICES FOR RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 | |||||
| ELINs A001 through A009 | |||||
| ELIN / Sub ELIN | Description | QTY | Unit of Issue | Unit Price | Total |
| A001 - REGION - PNBC Spec Item 3 | ||||
| A001AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| A001AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| A001AC | Develop and Implement Preventive Maintenance Program for Region HVAC Systems | 12 | Month | $ |
| A001AD | Develop and Implement Preventive Maintenance Program for Region Boilers and Water Treatment Services | 12 | Month | $ |
| A001AE | Inspection, Light-off, Testing, and Certification by NAVFAC Boiler Inspection for Region Boilers. | 12 | Month | $ |
REGION - PNBC UIC- N61003PO Subtotal $
| A002 - REGION - NSA-P Spec Item 3 | ||||
| A002AA | Develop and Implement a Water Testing and Treatment Program for Region - NSA-P HVAC Systems | 12 | Month | $ |
REGION - NSA-P Subtotal REGION -NSA-P UIC- N32445PO Subtotal $
| A003 - NSWC Spec Item 3 | ||||
| A003AA | Perform Emergency Service Call Work for NSWC | 12 | Month | $ |
| A003AB | Perform Routine Service Call Work for NSWC | 12 | Month | $ |
| A003AC | Develop and Implement Preventive Maintenance Program for NSWC HVAC Systems | 12 | Month | $ |
| A003AD | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC HVAC Systems | 12 | Month | $ |
| A003AE | Develop and Implement Preventive Maintenance Program for NSWC Boilers | 12 | Month | $ |
| A003AF | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC Boilers Systems | 12 | Month | $ |
| A003AG | Inspection, Testing, and Certification for NSWC Boilers | 1 | LS | $ |
NSWC UIC - N64498PO Subtotal $
| A004 - DLA PTC Spec Item 3 | ||||
| A004AA | Develop and Implement a Testing and Treatment Program for DLA for Water Softener Equipment | 12 | Month | $ |
DLA - PLC UIC - S07720PO Subtotal $
| A005 - DLA TS Item 3 | ||||
| A005AA | Develop and Implement a Water Testing and Treatment Program for DLA HVAC Systems | 12 | Month | $ |
| A005AB | Develop and Implement Preventative Mainenance Program for DLA Boilers | 12 | Month | $ |
DLA-TS UIC - S04890PO Subtotal $
| A006 - NFPC Spec Item 3 | ||||
| A006AA | Develop and Implement Preventive Maintenance Program for Foundry HVAC Systems | 12 | Month | $ |
| A006AB | Develop and Implement Preventive Maintenance Program for NFPC Boilers and Water Treatment Services | 12 | Month | $ |
| A006AC | Develop and Implement a Water Testing and Treatment Program for NFPC HVAC Systems | 12 | Month | $ |
| A006AD | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for NFPC Boilers | 12 | Month | $ |
NPFC UIC - N61003P1 Subtotal $
A007 - BUMED Spec Item 3
| A007AA | Develop and Implement Preventive Maintenance Program for BUMED (Bldg. 615) HVAC Systems | 12 | Month | $ |
| A007AB | Perform Routine Service Call Work for BUMED HVAC systems | 12 | Month | $ |
| A007AC | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for BUMED Boilers | 12 | Month | $ |
| A007AD | Develop and Implement Preventive Maintenance Program for BUMED Boilers and Water Treatment Services | 12 | Month | $ |
BUMED UIC - N32626PO Subtotal $
| A008 - NWSS Spec Item 3 | ||||
| A008AA | Develop and Implement a Water Testing and Treatment Program for NWSS HVAC Systems | 12 | Month | $ |
NWSS UIC - N00391P1 Subtotal $
| A009 - Building 9 - NSA-P Spec Item 3 | ||||
| A009AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| A009AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| A009AC | Develop and Implement Preventive Maintenance Program for OHRC HVAC Systems - Building 9 | 12 | Month | $ |
| A009AD | Develop and Implement a Water Testing and Treatment Program for OHRC HVAC Systems | 12 | Month |
Building 9 - NSA-P UIC - N32445PO Subtotal $
TOTAL RECURRING WORK PRICE - BASE PERIOD $
SECTION J
EXHIBIT A
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Fence Board Height of 6'
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Barbwire Fence.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Ornamental Steel Fence.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Wood Fence.
PROVIDE A UNIT PRICE FOR THE REMOVAL AND DISPOSAL OF FENCE COMPLETE, FENCE POSTS, BARBWIRE, BARBED TAPE.
IN ACCORDANCE WITH SECTION C, C.10.1.l
ELIN A001EW through A001FI
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Chain link Fence.
Including Fabric, Posts, Gates, Rails, Tension Wire, Barbwire/Barbed Tape.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Chain link Fence Gates including tracks (not posts).
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Ornamental Steel Fence. Including Posts and Gates
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Wood Fence. Including Posts and Gates.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Barbwire Fence. Including Posts and all wire.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Including Posts Footing with Braces and Supports as Required.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Post Cut-off Flush.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Driven Post.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Including Posts Footing with Braces and Supports as Required.
Posts Set in Concrete/Asphalt.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Square Foot to Patch and Refinish Concrete or Asphalt Surface.
Surface Depth to Match Surrounding.
Unit Price Each to Remove and Dispose of or Save and Store (for reuse) Barbwire Single Arm Support.
Unit Price Each to remove and Dispose of or Save and Store (for reuse) Barbwire Double (V) Arm Support.
Lump Sum Price for the recycling of removed materials. Based on a Percentage Added to Removal Item Ordered
Lump Sum Price for the Recycling of Removed Materials. Based on a Percentage Added to Removal Item Ordered, ELIN A001EK to A001EW. Figured on a Quantity of 1,000. The Quantity Provided is for Establishing the Percentage Rate Only.
PROVIDE A UNIT PRICE TO PERFORM EXPEDITED SERVICES.
IN ACCORDANCE WITH SECTION C, C.10.2
ELIN A001FJ
Lump Sum Price for Expedited Maintenance and Repair Services. Based on a Percentage Added to Task Order Total. Figured on a Quantity of 1,000. The Quantity Provided is for Establishing the Percentage Rate Only.
SECTION J
EXHIBIT A
PROVIDE A UNIT PRICE FOR THE RENTAL OF TEMPORARY CHAIN LINK FENCE.
IN ACCORDANCE WITH SECTION C, C.10.3
ELIN A001FK THROUGH A001FP
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Temporary Chain link Fence.
6' Fence Height Driven Posts
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, 6' Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, 6' Height, Free-Standing
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
With Barbwire, 7' Fence Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, With Barbwire, 7' Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, With Barbwire, 7' Height, Free-Standing
ELINs-Base Period-Non-Recurrin
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085 - 19-R-1704 |
| EXHIBIT A |
| Line Item 00010 Non-Recurring Work - Base Option Period |
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] -NON-RECURRING WORK PRICE - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 |
| ELINs E700 through E706 |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price | IMAP CAC |
| A700 | Unit Priced Labor Work - MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. MUST BE NEGOTIATED BY KO USING ETO PROCESS. | 600 | HR | $ | 717S | |
| A701 | Material Costs- MUST BE NEGOTIATED BY KO | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Use with ELIN E700. These material costs MUST BE NEGOTIATED BY KO USING ETO PROCESS. | $300,000 | LS | $ | 717S | |
| A702 | Unit Priced Labor Work for Direct Digital Control (DDC) Systems- MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. | |||||
| 1 | HR | $ | 717S | ||||
| A703 | Routine Service Calls for Control Systems | The Contractor shall perform routine Direct Digital Control (DDC) System service call work during regular working hours. Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall be completed within one working day. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| A704 | Emergency Service Calls for Control Systems | The Contractor shall perform Direct Digital Control (DDC) System emergency service call work 24 a day, seven days a week . Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall respond to emergency service call requests within four hours of receipt of call during and outside of regular working hours. The contractor shall remain at thw work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| A705 | Routine Service Calls for HVAC Services | The Contractor shall perform routine HVAC service call work during regular working hours. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within four hours of receipt of call during regular working hours. Service calls shall be completed within five working days. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | EA | $2,500.00 | |||
| A706 | Emergency Service Calls for HVAC Services | The Contractor shall perform HVAC emergency service call work 24 hours a day, seven days a week. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within two hours of receipt of call during and outside of regular working hours. The Contractor shall remain at the work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | 1 | EA | $2,500.00 | 717S |
TOTAL NON-RECURRING WORK PRICE - BASE PERIOD $
ELINS-1st Opt Period-FFP
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085-19-R-1704 |
| EXHIBIT B |
| Line Item 0003 Recurring Work - First Option Period | |||||
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 | |||||
| ELINs B001 through B009 | |||||
| ELIN / Sub ELIN | Description | QTY | Unit of Issue | Unit Price | Total |
| B001 - REGION - PNBC Spec Item 3 | ||||
| B001AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| B001AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| B001AC | Develop and Implement Preventive Maintenance Program for Region HVAC Systems | 12 | Month | $ |
| B001AD | Develop and Implement Preventive Maintenance Program for Region Boilers and Water Treatment Services | 12 | Month | $ |
| B001AE | Inspection, Light-off, Testing, and Certification by NAVFAC Boiler Inspection for Region Boilers. | 12 | Month | $ |
REGION - PNBC UIC- N61003PO Subtotal $
| B002 - REGION - NSA-P Spec Item 3 | ||||
| B002AA | Develop and Implement a Water Testing and Treatment Program for Region - NSA-P HVAC Systems | 12 | Month | $ |
REGION - NSA-P Subtotal REGION -NSA-P UIC- N32445PO Subtotal $
| B003 - NSWC Spec Item 3 | ||||
| B003AA | Perform Emergency Service Call Work for NSWC | 12 | Month | $ |
| B003AB | Perform Routine Service Call Work for NSWC | 12 | Month | $ |
| B003AC | Develop and Implement Preventive Maintenance Program for NSWC HVAC Systems | 12 | Month | $ |
| B003AD | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC HVAC Systems | 12 | Month | $ |
| B003AE | Develop and Implement Preventive Maintenance Program for NSWC Boilers | 12 | Month | $ |
| B003AF | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC Boilers Systems | 12 | Month | $ |
| B003AG | Inspection, Testing, and Certification for NSWC Boilers | 1 | LS | $ |
NSWC UIC - N64498PO Subtotal $
| B004 - DLA PTC Spec Item 3 | ||||
| B004AA | Develop and Implement a Testing and Treatment Program for DLA for Water Softener Equipment | 12 | Month | $ |
DLA - PLC UIC - S07720PO Subtotal $
| B005 - DLA TS Item 3 | ||||
| B005AA | Develop and Implement a Water Testing and Treatment Program for DLA HVAC Systems | 12 | Month | $ |
| B005AB | Develop and Implement Preventative Mainenance Program for DLA Boilers | 12 | Month | $ |
DLA-TS UIC - S04890PO Subtotal $
| B006 - NFPC Spec Item 3 | ||||
| B006AA | Develop and Implement Preventive Maintenance Program for Foundry HVAC Systems | 12 | Month | $ |
| B006AB | Develop and Implement Preventive Maintenance Program for NFPC Boilers and Water Treatment Services | 12 | Month | $ |
| B006AC | Develop and Implement a Water Testing and Treatment Program for NFPC HVAC Systems | 12 | Month | $ |
| B006AD | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for NFPC Boilers | 12 | Month | $ |
NPFC UIC - N61003P1 Subtotal $
B007 - BUMED Spec Item 3
| B007AA | Develop and Implement Preventive Maintenance Program for BUMED (Bldg. 615) HVAC Systems | 12 | Month | $ |
| B007AB | Perform Routine Service Call Work for BUMED HVAC systems | 12 | Month | $ |
| B007AC | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for BUMED Boilers | 12 | Month | $ |
| B007AD | Develop and Implement Preventive Maintenance Program for BUMED Boilers and Water Treatment Services | 12 | Month | $ |
BUMED UIC - N32626PO Subtotal $
| B008 - NWSS Spec Item 3 | ||||
| B008AA | Develop and Implement a Water Testing and Treatment Program for NWSS HVAC Systems | 12 | Month | $ |
NWSS UIC - N00391P1 Subtotal $
| B009 - Building 9 - NSA-P Spec Item 3 | ||||
| B009AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| B009AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| B009AC | Develop and Implement Preventive Maintenance Program for OHRC HVAC Systems - Building 9 | 12 | Month | $ |
| B009AD | Develop and Implement a Water Testing and Treatment Program for OHRC HVAC Systems | 12 | Month | $ |
Building 9 - NSA-P UIC - N32445PO Subtotal $
TOTAL RECURRING WORK PRICE - FIRST OPTION PERIOD $
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Barbwire Fence.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Ornamental Steel Fence.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Reconditioning and Maintenance Service for Wood Fence.
PROVIDE A UNIT PRICE FOR THE REMOVAL AND DISPOSAL OF FENCE COMPLETE, FENCE POSTS, BARBWIRE, BARBED TAPE.
IN ACCORDANCE WITH SECTION C, C.10.1.l
ELIN A001EW through A001FI
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Chain link Fence.
Including Fabric, Posts, Gates, Rails, Tension Wire, Barbwire/Barbed Tape.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Chain link Fence Gates including tracks (not posts).
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Ornamental Steel Fence. Including Posts and Gates
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Wood Fence. Including Posts and Gates.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Removal Service for Barbwire Fence. Including Posts and all wire.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Including Posts Footing with Braces and Supports as Required.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Post Cut-off Flush.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Driven Post.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Each to Provide Removal Service for Fence Posts. Including Posts Footing with Braces and Supports as Required.
Posts Set in Concrete/Asphalt.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Square Foot to Patch and Refinish Concrete or Asphalt Surface.
Surface Depth to Match Surrounding.
Unit Price Each to Remove and Dispose of or Save and Store (for reuse) Barbwire Single Arm Support.
Unit Price Each to remove and Dispose of or Save and Store (for reuse) Barbwire Double (V) Arm Support.
Lump Sum Price for the recycling of removed materials. Based on a Percentage Added to Removal Item Ordered
Lump Sum Price for the Recycling of Removed Materials. Based on a Percentage Added to Removal Item Ordered, ELIN A001EK to A001EW. Figured on a Quantity of 1,000. The Quantity Provided is for Establishing the Percentage Rate Only.
PROVIDE A UNIT PRICE TO PERFORM EXPEDITED SERVICES.
IN ACCORDANCE WITH SECTION C, C.10.2
ELIN A001FJ
Lump Sum Price for Expedited Maintenance and Repair Services. Based on a Percentage Added to Task Order Total. Figured on a Quantity of 1,000. The Quantity Provided is for Establishing the Percentage Rate Only.
SECTION J
EXHIBIT A
PROVIDE A UNIT PRICE FOR THE RENTAL OF TEMPORARY CHAIN LINK FENCE.
IN ACCORDANCE WITH SECTION C, C.10.3
ELIN A001FK THROUGH A001FP
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
6' Fence Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, 6' Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, 6' Height, Free-Standing
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
With Barbwire, 7' Fence Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, With Barbwire, 7' Height
Unit Price Per Linear Foot to Provide Red Wood or Cedar Fence Including Dog Ear Fence Boards, Posts, Rails, Braces and all Hardware.
12' Panel, With Barbwire, 7' Height, Free-Standing
ELINs-1st Opt-Non-Recurring
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085 - 19-R-1704 |
| EXHIBIT B |
| Line Item 00010 Non-Recurring Work - First Option Period |
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] -NON-RECURRING WORK PRICE - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 |
| ELINs E700 through E706 |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price | IMAP CAC |
| B700 | Unit Priced Labor Work - MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. MUST BE NEGOTIATED BY KO USING ETO PROCESS. | 600 | HR | $ | 717S | |
| B701 | Material Costs- MUST BE NEGOTIATED BY KO | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Use with ELIN E700. These material costs MUST BE NEGOTIATED BY KO USING ETO PROCESS. | $300,000 | LS | $ | 717S | |
| B702 | Unit Priced Labor Work for Direct Digital Control (DDC) Systems- MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. | |||||
| 1 | HR | $ | 717S | ||||
| B703 | Routine Service Calls for Control Systems | The Contractor shall perform routine Direct Digital Control (DDC) System service call work during regular working hours. Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall be completed within one working day. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| B704 | Emergency Service Calls for Control Systems | The Contractor shall perform Direct Digital Control (DDC) System emergency service call work 24 a day, seven days a week . Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall respond to emergency service call requests within four hours of receipt of call during and outside of regular working hours. The contractor shall remain at thw work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| B705 | Routine Service Calls for HVAC Services | The Contractor shall perform routine HVAC service call work during regular working hours. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within four hours of receipt of call during regular working hours. Service calls shall be completed within five working days. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | EA | $2,500.00 | |||
| B706 | Emergency Service Calls for HVAC Services | The Contractor shall perform HVAC emergency service call work 24 hours a day, seven days a week. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within two hours of receipt of call during and outside of regular working hours. The Contractor shall remain at the work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | 1 | EA | $2,500.00 | 717S |
TOTAL NON-RECURRING WORK PRICE - BASE PERIOD $
ELINS-2nd Opt Period-FFP
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085-19-R-1704 |
| EXHIBIT C |
| Line Item 0005 Recurring Work - Second Option Period | |||||
| PROVIDE PRICES FOR - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 | |||||
| ELINs C001 through C009 | |||||
| ELIN / Sub ELIN | Description | QTY | Unit of Issue | Unit Price | Total |
| C001 - REGION - PNBC Spec Item 3 | ||||
| C001AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| C001AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| C001AC | Develop and Implement Preventive Maintenance Program for Region HVAC Systems | 12 | Month | $ |
| C001AD | Develop and Implement Preventive Maintenance Program for Region Boilers and Water Treatment Services | 12 | Month | $ |
| C001AE | Inspection, Light-off, Testing, and Certification by NAVFAC Boiler Inspection for Region Boilers. | 12 | Month | $ |
REGION - PNBC UIC- N61003PO Subtotal $
| C002 - REGION - NSA-P Spec Item 3 | ||||
| C002AA | Develop and Implement a Water Testing and Treatment Program for Region - NSA-P HVAC Systems | 12 | Month | $ |
REGION - NSA-P Subtotal REGION -NSA-P UIC- N32445PO Subtotal $
| C003 - NSWC Spec Item 3 | ||||
| C003AA | Perform Emergency Service Call Work for NSWC | 12 | Month | $ |
| C003AB | Perform Routine Service Call Work for NSWC | 12 | Month | $ |
| C003AC | Develop and Implement Preventive Maintenance Program for NSWC HVAC Systems | 12 | Month | $ |
| C003AD | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC HVAC Systems | 12 | Month | $ |
| C003AE | Develop and Implement Preventive Maintenance Program for NSWC Boilers | 12 | Month | $ |
| C003AF | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC Boilers Systems | 12 | Month | $ |
| C003AG | Inspection, Testing, and Certification for NSWC Boilers | 1 | LS | $ |
NSWC UIC - N64498PO Subtotal $
| C004 - DLA PTC Spec Item 3 | ||||
| C004AA | Develop and Implement a Testing and Treatment Program for DLA for Water Softener Equipment | 12 | Month | $ |
DLA - PLC UIC - S07720PO Subtotal $
| C005 - DLA TS Item 3 | ||||
| C005AA | Develop and Implement a Water Testing and Treatment Program for DLA HVAC Systems | 12 | Month | $ |
| C005AB | Develop and Implement Preventative Mainenance Program for DLA Boilers | 12 | Month | $ |
DLA-TS UIC - S04890PO Subtotal $
| C006 - NFPC Spec Item 3 | ||||
| C006AA | Develop and Implement Preventive Maintenance Program for Foundry HVAC Systems | 12 | Month | $ |
| C006AB | Develop and Implement Preventive Maintenance Program for NFPC Boilers and Water Treatment Services | 12 | Month | $ |
| C006AC | Develop and Implement a Water Testing and Treatment Program for NFPC HVAC Systems | 12 | Month | $ |
| C006AD | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for NFPC Boilers | 12 | Month | $ |
NPFC UIC - N61003P1 Subtotal $
C007 - BUMED Spec Item 3
| C007AA | Develop and Implement Preventive Maintenance Program for BUMED (Bldg. 615) HVAC Systems | 12 | Month | $ |
| C007AB | Perform Routine Service Call Work for BUMED HVAC systems | 12 | Month | $ |
| C007AC | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for BUMED Boilers | 12 | Month | $ |
| C007AD | Develop and Implement Preventive Maintenance Program for BUMED Boilers and Water Treatment Services | 12 | Month | $ |
BUMED UIC - N32626PO Subtotal $
| C008 - NWSS Spec Item 3 | ||||
| C008AA | Develop and Implement a Water Testing and Treatment Program for NWSS HVAC Systems | 12 | Month | $ |
NWSS UIC - N00391P1 Subtotal $
| C009 - Building 9 - NSA-P Spec Item 3 | ||||
| C009AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| C009AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| C009AC | Develop and Implement Preventive Maintenance Program for OHRC HVAC Systems - Building 9 | 12 | Month | $ |
| C009AD | Develop and Implement a Water Testing and Treatment Program for OHRC HVAC Systems | 12 | Month | $ |
Building 9 - NSA-P UIC - N32445PO Subtotal $
TOTAL RECURRING WORK PRICE - SECOND OPTION PERIOD $
ELINs-2nd Opt-Non-Recurring
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085 - 19-R-1704 |
| EXHIBIT C |
| Line Item 00010 Non-Recurring Work - Second Option Period |
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] -NON-RECURRING WORK PRICE - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 |
| ELINs E700 through E706 |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price | IMAP CAC |
| C700 | Unit Priced Labor Work - MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. MUST BE NEGOTIATED BY KO USING ETO PROCESS. | 600 | HR | $ | 717S | |
| C701 | Material Costs- MUST BE NEGOTIATED BY KO | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Use with ELIN E700. These material costs MUST BE NEGOTIATED BY KO USING ETO PROCESS. | $300,000 | LS | $ | 717S | |
| C702 | Unit Priced Labor Work for Direct Digital Control (DDC) Systems- MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. | |||||
| 1 | HR | $ | 717S | ||||
| C703 | Routine Service Calls for Control Systems | The Contractor shall perform routine Direct Digital Control (DDC) System service call work during regular working hours. Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall be completed within one working day. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| C704 | Emergency Service Calls for Control Systems | The Contractor shall perform Direct Digital Control (DDC) System emergency service call work 24 a day, seven days a week . Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall respond to emergency service call requests within four hours of receipt of call during and outside of regular working hours. The contractor shall remain at thw work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| C705 | Routine Service Calls for HVAC Services | The Contractor shall perform routine HVAC service call work during regular working hours. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within four hours of receipt of call during regular working hours. Service calls shall be completed within five working days. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | EA | $2,500.00 | |||
| C706 | Emergency Service Calls for HVAC Services | The Contractor shall perform HVAC emergency service call work 24 hours a day, seven days a week. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within two hours of receipt of call during and outside of regular working hours. The Contractor shall remain at the work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | 1 | EA | $2,500.00 | 717S |
TOTAL NON-RECURRING WORK PRICE - BASE PERIOD $
ELINS-3rd Opt Period-FFP
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085-19-R-1704 |
| EXHIBIT D |
| Line Item 0007 Recurring Work - Third Option Period | |||||
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 | |||||
| ELINs D001 through D009 | |||||
| ELIN / Sub ELIN | Description | QTY | Unit of Issue | Unit Price | Total |
| D001 - REGION - PNBC Spec Item 3 | ||||
| D001AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| D001AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| D001AC | Develop and Implement Preventive Maintenance Program for Region HVAC Systems | 12 | Month | $ |
| D001AD | Develop and Implement Preventive Maintenance Program for Region Boilers and Water Treatment Services | 12 | Month | $ |
| D001AE | Inspection, Light-off, Testing, and Certification by NAVFAC Boiler Inspection for Region Boilers. | 12 | Month | $ |
REGION - PNBC UIC- N61003PO Subtotal $
| D002 - REGION - NSA-P Spec Item 3 | ||||
| D002AA | Develop and Implement a Water Testing and Treatment Program for Region - NSA-P HVAC Systems | 12 | Month | $ |
REGION - NSA-P Subtotal REGION -NSA-P UIC- N32445PO Subtotal $
| D003 - NSWC Spec Item 3 | ||||
| D003AA | Perform Emergency Service Call Work for NSWC | 12 | Month | $ |
| D003AB | Perform Routine Service Call Work for NSWC | 12 | Month | $ |
| D003AC | Develop and Implement Preventive Maintenance Program for NSWC HVAC Systems | 12 | Month | $ |
| D003AD | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC HVAC Systems | 12 | Month | $ |
| D003AE | Develop and Implement Preventive Maintenance Program for NSWC Boilers | 12 | Month | $ |
| D003AF | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC Boilers Systems | 12 | Month | $ |
| D003AG | Inspection, Testing, and Certification for NSWC Boilers | 1 | LS | $ |
NSWC UIC - N64498PO Subtotal $
| D004 - DLA PTC Spec Item 3 | ||||
| D004AA | Develop and Implement a Testing and Treatment Program for DLA for Water Softener Equipment | 12 | Month | $ |
DLA - PLC UIC - S07720PO Subtotal $
| D005 - DLA TS Item 3 | ||||
| D005AA | Develop and Implement a Water Testing and Treatment Program for DLA HVAC Systems | 12 | Month | $ |
| D005AB | Develop and Implement Preventative Mainenance Program for DLA Boilers | 12 | Month | $ |
DLA-TS UIC - S04890PO Subtotal $
| D006 - NFPC Spec Item 3 | ||||
| D006AA | Develop and Implement Preventive Maintenance Program for Foundry HVAC Systems | 12 | Month | $ |
| D006AB | Develop and Implement Preventive Maintenance Program for NFPC Boilers and Water Treatment Services | 12 | Month | $ |
| D006AC | Develop and Implement a Water Testing and Treatment Program for NFPC HVAC Systems | 12 | Month | $ |
| D006AD | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for NFPC Boilers | 12 | Month | $ |
NPFC UIC - N61003P1 Subtotal $
D007 - BUMED Spec Item 3
| D007AA | Develop and Implement Preventive Maintenance Program for BUMED (Bldg. 615) HVAC Systems | 12 | Month | $ |
| D007AB | Perform Routine Service Call Work for BUMED HVAC systems | 12 | Month | $ |
| D007AC | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for BUMED Boilers | 12 | Month | $ |
| D007AD | Develop and Implement Preventive Maintenance Program for BUMED Boilers and Water Treatment Services | 12 | Month | $ |
BUMED UIC - N32626PO Subtotal $
| D008 - NWSS Spec Item 3 | ||||
| D008AA | Develop and Implement a Water Testing and Treatment Program for NWSS HVAC Systems | 12 | Month | $ |
NWSS UIC - N00391P1 Subtotal $
| D009 - Building 9 - NSA-P Spec Item 3 | ||||
| D009AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| D009AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| D009AC | Develop and Implement Preventive Maintenance Program for OHRC HVAC Systems - Building 9 | 12 | Month | $ |
| D009AD | Develop and Implement a Water Testing and Treatment Program for OHRC HVAC Systems | 12 | Month | $ |
Building 9 - NSA-P UIC - N32445PO Subtotal $
TOTAL RECURRING WORK PRICE - THIRD OPTION PERIOD $
ELINs-3rd Opt-Non-Recurring
| ATTACHMENT J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085 - 19-R-1704 |
| EXHIBIT D |
| Line Item 00010 Non-Recurring Work - Third Option Period |
| PROVIDE PRICES FOR -NON-RECURRING WORK PRICE - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 |
| ELINs E700 through E706 |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price | IMAP CAC |
| D700 | Unit Priced Labor Work - MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. MUST BE NEGOTIATED BY KO USING ETO PROCESS. | 600 | HR | $ | 717S | |
| D701 | Material Costs- MUST BE NEGOTIATED BY KO | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Use with ELIN E700. These material costs MUST BE NEGOTIATED BY KO USING ETO PROCESS. | $300,000 | LS | $ | 717S | |
| D702 | Unit Priced Labor Work for Direct Digital Control (DDC) Systems- MUST BE NEGOTIATED BY KO | Provide labor to perform all Unit Priced Labor work subject to the Service Contract Act per the scope and delivery schedule specified in the order. | |||||
| 1 | HR | $ | 717S | ||||
| D703 | Routine Service Calls for Control Systems | The Contractor shall perform routine Direct Digital Control (DDC) System service call work during regular working hours. Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall be completed within one working day. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| D704 | Emergency Service Calls for Control Systems | The Contractor shall perform Direct Digital Control (DDC) System emergency service call work 24 a day, seven days a week . Each service call is limited to combined labor and material cost not to exceed $2,500.00. The total labor rate is based on the labor rate for ELIN E702 time the hours worked. The contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Service calls shall respond to emergency service call requests within four hours of receipt of call during and outside of regular working hours. The contractor shall remain at thw work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, contractor shall submit to the KO a report that includes the following information: call number, date call received, date call completed, description of problem, description of work performed, labor hours expended and material costs incurred. | 1 | EA | $2,500.00 | 717S | |
| D705 | Routine Service Calls for HVAC Services | The Contractor shall perform routine HVAC service call work during regular working hours. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within four hours of receipt of call during regular working hours. Service calls shall be completed within five working days. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | EA | $2,500.00 | |||
| D706 | Emergency Service Calls for HVAC Services | The Contractor shall perform HVAC emergency service call work 24 hours a day, seven days a week. Each service call is limited to a combined labor and material cost not to exceed $2,500.00. The Contractor shall, per Annex 2, notify the KO upon identification that the service call will exceed the $2,500.00 threshold. Contractor shall respond to service call requests within two hours of receipt of call during and outside of regular working hours. The Contractor shall remain at the work site until the emergency has been arrested. If follow up work is required to complete the repair, the call will be reclassified as routine and the corresponding completion time will then apply. Such follow up work will be considered part of the original service call. Within three working days of completion, Contractor shall submit to the KO a report that includes the following information: Call number, date call received, date call completed, description of problem, description of work performed, labor hours expanded and material costs incurred. | 1 | EA | $2,500.00 | 717S |
TOTAL NON-RECURRING WORK PRICE - BASE PERIOD $
ELINS- 4th Opt Period-FFP
| ATTACHMEN+A1:F78T J-0200000-06 |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT # N40085-19-R-1704 |
| EXHIBIT E |
| Line Item 0009 Recurring Work - Fourth Option Period | |||||
| PROVIDE PRICES FOR [SUB-ANNEX TITLE] - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 | |||||
| ELINs E001 through E009 | |||||
| ELIN / Sub ELIN | Description | QTY | Unit of Issue | Unit Price | Total |
| E001 - REGION - PNBC Spec Item 3 | ||||
| E001AA | Perform Emergency Service Call Work for Region | 12 | Month | $ |
| E001AB | Perform Routine Service Call Work for Region | 12 | Month | $ |
| E001AC | Develop and Implement Preventive Maintenance Program for Region HVAC Systems | 12 | Month | $ |
| E001AD | Develop and Implement Preventive Maintenance Program for Region Boilers and Water Treatment Services | 12 | Month | $ |
| E001AE | Inspection, Light-off, Testing, and Certification by NAVFAC Boiler Inspection for Region Boilers. | 12 | Month | $ |
REGION - PNBC UIC- N61003PO Subtotal $
| E002 - REGION - NSA-P Spec Item 3 | ||||
| E002AA | Develop and Implement a Water Testing and Treatment Program for Region - NSA-P HVAC Systems | 12 | Month | $ |
REGION - NSA-P Subtotal REGION -NSA-P UIC- N32445PO Subtotal $
| E003 - NSWC Spec Item 3 | ||||
| E003AA | Perform Emergency Service Call Work for NSWC | 12 | Month | $ |
| E003AB | Perform Routine Service Call Work for NSWC | 12 | Month | $ |
| E003AC | Develop and Implement Preventive Maintenance Program for NSWC HVAC Systems | 12 | Month | $ |
| E003AD | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC HVAC Systems | 12 | Month | $ |
| E003AE | Develop and Implement Preventive Maintenance Program for NSWC Boilers | 12 | Month | $ |
| E003AF | Develop and Implement a Water Testing and Treatment Program for NSWC - NSWC Boilers Systems | 12 | Month | $ |
| E003AG | Inspection, Testing, and Certification for NSWC Boilers | 1 | LS | $ |
NSWC UIC - N64498PO Subtotal $
| E004 - DLA PTC Spec Item 3 | ||||
| E004AA | Develop and Implement a Testing and Treatment Program for DLA for Water Softener Equipment | 12 | Month | $ |
DLA - PLC UIC - S07720PO Subtotal $
| E005 - DLA TS Item 3 | ||||
| E005AA | Develop and Implement a Water Testing and Treatment Program for DLA HVAC Systems | 12 | Month | $ |
| E005AB | Develop and Implement Preventative Mainenance Program for DLA Boilers | 12 | Month | $ |
DLA-TS UIC - S04890PO Subtotal $
| E006 - NFPC Spec Item 3 | ||||
| E006AA | Develop and Implement Preventive Maintenance Program for Foundry HVAC Systems | 12 | Month | $ |
| E006AB | Develop and Implement Preventive Maintenance Program for NFPC Boilers and Water Treatment Services | 12 | Month | $ |
| E006AC | Develop and Implement a Water Testing and Treatment Program for NFPC HVAC Systems | 12 | Month | $ |
| E006AD | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for NFPC Boilers | 12 | Month | $ |
NPFC UIC - N61003P1 Subtotal $
E007 - BUMED Spec Item 3
| E007AA | Develop and Implement Preventive Maintenance Program for BUMED (Bldg. 615) HVAC Systems | 12 | Month | $ |
| E007AB | Perform Routine Service Call Work for BUMED HVAC systems | 12 | Month | $ |
| E007AC | Inspection, Light-Off, Testing, and Certification By NAVFAC Boiler Inspection for BUMED Boilers | 12 | Month | $ |
| E007AD | Develop and Implement Preventive Maintenance Program for BUMED Boilers and Water Treatment Services | 12 | Month | $ |
BUMED UIC - N32626PO Subtotal $
| E008 - NWSS Spec Item 3 |