N4008518B0043 Specs 1of2.pdf

PDF 7 MB Posted

Attached to
Repair BEQ HP504
Solicitation number
N40085-21-R-2505
Issued by

View the file

Other files

File Type Posted
NEW RFP 180043.pdf PDF
N4008518B0043 Dwgs.pdf PDF
18-0043 Pb and ACM fr CL combined.pdf PDF
18-0043 APPD.pdf PDF
18-0043 Lead Base Paint Inspection Report.pdf PDF
N4008518B0043 Specs 2of2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT N40085-18-B-0043

NAVFAC SPECIFICATION

NO. 05-18-0043

Repair BEQ HP504

AT THE

MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA

DESIGN BY:

CEMS Engineering | Architecture Summerville, SC Wilmington, NC

A/E Contract: N40085-15-D-0858

SPECIFICATION PREPARED BY:

Chris A. Mooring, PE Eric C. Wieters, PE

Paul C. Mahaffey, PE Robert S. Perkins, PE

Mark J. Smith, AIA Date: July 30, 2020

SPECIFICATION APPROVED BY:

T. H. Burton, P.E., Director Design Branch, Public Works Division

J. W. Carson, Captain, CEC, U.S. Navy for Commander, Naval Facilities Engineering Command

05180043

29610

N

O

RT

H CAROL IN

A

P

RO

FESS I ONA L

SEAL

E

N G

I N E E

R

R O

B E

R T

S C O T T P

E

R K

I N

S

7/

/2

7/30/20

7/30/20

045662

N

O

RT

H CAROL IN

A

P

RO

FESS I ONA

L

SEAL

E

N G

I N E E

R

E R

I C C. W I E T E

R

S

7/30/20

Eric C. Wieters, PE

32273

N

O

RT

H CAROL IN

A

P

RO

FESS I ONA

L

SEAL

E

N G

I N E E

R

P A

U

L

C . M A H A F

F E

Y

032190

N

O

RT

H CAROL IN

A

P

RO

FESS I ONA

L

SEAL

E

N G

I N E E

R

M A R K A. L A Z O

7/30/207/30/20

THIS PAGE INTENTIONALLY LEFT BLANK

Repair BEQ HP504 18-0043

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 12 00 CUTTING AND PATCHING

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 31 50 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY

01 32 16 CONSTRUCTION PROGRESS DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 10 QUALITY CONTROL

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 60 00 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION

01 78 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 30.00 22 GIS DATA DELIVERABLES

01 91 13 GENERAL COMMISSIONING REQUIREMENTS

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION

02 82 16 02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

DI VI SI ON 03 - CONCRETE

03 01 30.71 CONCRETE REHABILITATION

03 30 50 CAST-IN-PLACE CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

DI VI SI ON 05 - METALS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 STEEL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 11 13 BITUMINOUS DAMPPROOFING

07 21 13 BOARD AND BLOCK INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 21 16 MINERAL FIBER BLANKET INSULATION

07 21 23 LOOSE FILL THERMAL INSULATION

07 61 00 SHEET METAL AND CLADDING

07 61 15.00 20 ALUMINUM STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 31 00 ACCESS DOORS AND PANELS

08 58 01 BLAST MITIGATION OPERABLE ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 90 00 PAINTS AND COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.20 INTERIOR SIGNAGE

10 28 13 TOILET ACCESSORIES

10 52 20 FIRE EXTINGUISHERS AND CABINETS

DI VI SI ON 11 - EQUI PMENT

11 24 24 HORIZONTAL LIFELINE ROOFTOP FALL PROTECTION SAFETY SYSTEMS

DI VI SI ON 12 - FURNI SHI NGS

12 21 00 WINDOW BLINDS

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 INSULATION OF MECHANICAL SYSTEMS

23 09 23.13 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC

23 73 33 HEATING, VENTILATING, AND COOLING SYSTEM

DI VI SI ON 26 - ELECTRI CAL

26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS

PROJECT TABLE OF CONTENTS Page 2

26 06 00 GROUNDING AND BONDING

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

DI VI SI ON 33 - UTI LI TI ES

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

33 40 00 STORM DRAINAGE UTILITIES

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

PROJECT TABLE OF CONTENTS Page 4

LIST OF DRAWINGS

Contract drawings are as follows:

NAVFAC SHEET

DWG NO. NO. TITLE

60023816 G-001 COVER SHEET

60023817 LS101 BUILDING CODE ANALYSIS

60023818 LS102 LIFE SAFETY PLAN

60023819 H-101 ABATEMENT PLANS

60023820 H-102 ABATEMENT ROOF PLAN

60023821 C-001 LEGEND AND GENERAL NOTES

60023822 VF101 EXISTING TOPOGRAPHIC SURVEY

60023823 CD101 DEMOLITION / EROSION CONTROL PLAN - AREA 'A'

60023824 CD102 DEMOLITION / EROSION CONTROL PLAN - AREA 'B'

60023825 CS101 SITE PLAN - AREA 'A'

60023826 CS102 SITE PLAN - AREA 'B'

60023827 CP101 PLANTING PLAN - AREA 'A'

60023828 CP102 PLANTING PLAN - AREA 'B'

60023829 C-501 EROSION CONTROL DETAILS

60023830 C-502 CIVIL DETAILS

60023831 C-503 CIVIL DETAILS

60023832 S-001 GENERAL NOTES AND DESIGN LOADS

60023833 SD101 DEMOLITION PLANS

60023834 SD401 ENLARGED DEMOLITION PLAN

60023835 S-101 CATWALK FRAMING PLANS

60023836 S-102 ROOF FRAMING PLANS

60023837 S-103 FLOOR PLANS

60023838 S-301 FRAMING SECTIONS AND DETAILS

60023839 S-302 CMU SECTIONS AND DETAILS

60023840 S-303 MECHANICAL OPENING SECTIONS AND DETAILS

60023841 S-401 ENLARGED PLANS

60023842 S-501 ROOF FRAMING DETAILS

60023843 S-502 SECTIONS AND DETAILS

60023844 S-503 SECTIONS AND DETAILS

60023845 A-001 GENERAL NOTES AND LEGENDS

60023846 AD101 DEMOLITION FLOOR PLANS

60023847 AD102 DEMOLITION REFLECTED CEILING PLANS

60023848 AD103 DEMOLITION ROOF PLAN

60023849 AD201 DEMOLITION ELEVATIONS

60023850 AD401 DEMOLITION ENLARGED CORE FLOOR PLAN

60023851 AD402 DEMOLITION ENLARGED CORE REFLECTED CEILING PLANS

60023852 AD403 DEMOLITION ENLARGED SLEEPING ROOM PLAN, RCP, AND

ELEVATIONS

60023853 AD501 DEMOLITION DETAILS

60023854 AD901 DEMOLITION PHOTOS

60023855 A-101 FLOOR PLANS

60023856 A-102 REFLECTED CEILING PLANS

60023857 A-103 ROOF PLAN

60023858 A-201 BUILDING ELEVATIONS

60023859 A-202 ENLARGED BUILDING ELEVATIONS

60023860 A-301 BUILDING SECTIONS

60023861 A-302 WALL SECTIONS

60023862 A-401 ENLARGED CORE FLOOR PLANS

NAVFAC SHEET

DWG NO. NO. TITLE

60023863 A-402 ENLARGED CORE REFLECTED CEILING PLANS

60023864 A-403 ENLARGED SLEEPING ROOM FLOOR PLAN AND REFLECTED

CEILING PLANS

60023865 A-404 ENLARGED SLEEPING ROOM ELEVATIONS AND DETAILS

60023866 A-405 ENLARGED TOILET ROOM PLANS AND ELEVATIONS

60023867 A-501 DETAILS

60023868 A-502 ROOF DETAILS

60023869 A-503 RAILING DETAILS

60023870 A-504 CASEWORK DETAILS

60023871 A-601 FINISH SCHEDULE AND DETAILS

60023872 A-602 DOOR SCHEDULE AND DETAILS

60023873 A-603 DOOR DETAILS

60023874 A-604 DOOR DETAILS

60023875 A-605 WINDOW SCHEDULE AND DETAILS

60023876 A-606 SIGNAGE PLANS

60023877 A-607 SIGNAGE SCHEDULE

60023878 A-608 SIGNAGE TYPES

60023879 F-001 GENERAL NOTES, LEGENDS, AND DIAGRAMS

60023880 F-002 LEGEND AND RISER DIAGRAM

60023881 F-003 LEGEND, DETAILS, AND RISER DIAGRAM

60023882 FD101 FIRE ALARM DEMOLITION PLANS

60023883 F-101 FIRE ALARM/MASS NOTIFICATION PLANS

60023884 F-102 FIRE PROTECTION PLANS

60023885 F-401 ENLARGED FIRE ALARM/MNS PLANS

60023886 P-001 LEGEND, DETAILS, AND SCHEDULES

60023887 PD101 DEMOLITION PLANS

60023888 PD401 ENLARGED DEMOLITION PLANS

60023889 PD402 ENLARGED DEMOLITION PLANS

60023890 PD403 ENLARGED DEMOLITION PLANS

60023891 P-101 SANITARY PLANS

60023892 P-102 PLUMBING DOMESTIC PIPING PLANS

60023893 P-103 PLUMBING ATTIC PLAN

60023894 P-401 ENLARGED SANITARY PIPING PLANS

60023895 P-402 ENLARGED DOMESTIC PIPING PLANS

60023896 P-403 ENLARGED PIPING PLANS

60023897 P-404 ENLARGED PIPING PLANS

60023898 P-501 DETAILS

60023899 P-701 ISOMETRIC VIEWS

60023900 M-001 GENERAL NOTES AND LEGENDS

60023901 MS101 SITE PIPING DEMOLITION PLAN - AREA 'A'

60023902 MS102 SITE PIPING DEMOLITION PLAN - AREA 'B'

60023903 MS103 SITE PIPING PLAN - AREA 'A'

60023904 MS104 SITE PIPING PLAN - AREA 'B'

60023905 MD101 MECHANICAL DEMOLITION PLANS

60023906 MD102 ROOF MECHANICAL DEMOLITION PLAN

60023907 MD401 ENLARGED MECHANICAL DEMOLITION PLANS

60023908 MD402 ENLARGED MECHANICAL DEMOLITION PLAN

60023909 MD403 ENLARGED MECHANICAL DEMOLITION PLANS

60023910 MH101 MECHANICAL NEW WORK FLOOR PLANS

60023911 MH102 MECHANICAL NEW WORK ATTIC PLAN

60023912 MH401 ENLARGED MECHANICAL NEW WORK PLANS

60023913 MH402 ENLARGED MECHANCAL NEW WORK PLANS AND SECTIONS

60023914 MH403 ENLARGED MECHANICAL NEW WORK PLANS

NAVFAC SHEET

DWG NO. NO. TITLE

60023915 MP101 MECHANICAL PIPING NEW WORK PLANS

60023916 MP102 BUILDING HP502 PIPING PLANS

60023917 MP401 ENLARGED MECHANICAL PIPING NEW WORK PLANS

60023918 M-501 MECHANICAL DETAILS

60023919 M-502 MECHANCIAL DETAILS

60023920 M-503 MECHANICAL DETAILS

60023921 M-601 MECHANICAL SCHEDULES

60023922 MI001 MECHANICAL CONTROLS

60023923 MI002 MECHANICAL CONTROLS

60023924 MI101 CORE AHU CONTROLS AND SEQUENCE OF OPERATION

60023925 MI102 DOAS CONTROLS AND SEQUENCE OF OPERATION

60023926 MI103 EF AND UH CONTROLS AND SEQUENCE OF OPERATION

60023927 MI104 PTAC CONTROLS AND OPERATION

60023928 MI105 HYDRONIC SYSTEM CONTROLS

60023929 MI106 HHW AND CHW CONTROLS AND OPERATION

60023930 MI107 HHW SEQUENCE OF OPERATION

60023931 E-001 LEGEND AND GENERAL NOTES

60023932 ES101 SITE DEMOLITION PLAN

60023933 ES102 SITE PLAN

60023934 ES103 SITE PLAN

60023935 ED101 DEMOLITION PLANS

60023936 ED102 ROOF DEMOLITION PLAN

60023937 ED401 ENLARGED DEMOLITION PLANS

60023938 ED402 ENLARGED DEMOLITION PLANS

60023939 E-101 FLOOR PLANS

60023940 E-102 ATTIC PLAN

60023941 E-103 BUILDING 502 ELECTRICAL PLANS

60023942 E-401 ENLARGED PLANS

60023943 E-402 ENLARGED PLANS

60023944 E-403 ENLARGED PLANS

60023945 E-501 LIGHTING DETAILS

60023946 E-502 DETAILS

60023947 E-503 DETAILS

60023948 E-601 PANEL SCHEDULES

60023949 E-602 PANEL SCHEDULES

60023950 E-603 PANEL SCHEDULES

60023951 E-604 PANEL SCHEDULES

60023952 E-605 RISER DIAGRAM

60023953 E-701 LIGHTNING PROTECTION PLAN AND DETAILS

SECTION 01 11 00

SUMMARY OF WORK

09/08

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes a complete replacement of the HVAC and electrical systems. Construction of a new sloped metal-truss roof system with standing seam metal roof. Upgrades conforming to Minimum Antiterrorism Standards for Buildings. Renovation and reconfiguration of the first lounge into a laundry room. Renovations within the existing cenral plant for its continued use and incidental related work.

1.1.2 Location

The work shall be located at the Marine Corps Base, Camp Lejeune, North Carolina, HP504 approximately as shown. The exact location will be indicated by the Contracting Officer.

1.2 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.3 LOCATION OF UNDERGROUND FACILITIES

The Contractor will be responsible for obtaining the services of a professional utility locator to scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.3.1 Notification Prior to Excavation

Notify the Contracting Officer 48 hours prior to starting excavation work in order to permit making arrangements with public works personnel to scan the area for unmarked utilities. Obtain station digging permits prior to

SECTION 01 11 00 Page 1 starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 12 00

CUTTING AND PATCHING

01/07

PART 1 GENERAL

1.1 CUTTING

Shall be done by sawing along straight lines. The amount cut out shall be the minimum necessary to accommodate the new work. No flame cutting will be permitted without written permission of the Officer in Charge of Construction.

1.2 HOLES

Shall be rotary drilled. The size shall be the minimum necessary to accommodate the new work.

1.3 PATCHING

Shall be done with materials which match the existing in color, quality and surface texture when finished.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 12 00 Page 1

SECTION 01 12 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

01/07

PART 1 GENERAL

1.1 CONTRACTOR ACCESS AND USE OF PREMISES

1.1.1 Station Regulations

Ensure that Contractor personnel employed on the Station become familiar with and obey Station regulations. Keep within the limits of the work and avenues of ingress and egress as directed. Do not enter restricted areas unless required to do so and until cleared for such entry. Wear hard hats in designated areas. Do not enter any restricted aras unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.1.2 Working Hours

Regular working hours shall consist of an eight and one-half hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.

1.1.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Provide written request at least 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

1.1.4 Occupied and Existing Buildings

The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.

The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.

1.1.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone

SECTION 01 14 00 Page 1 service, electric service, air conditioning, heating, fire alarm, compressed air, and CATV shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.2 SECURITY REQUIREMENTS

Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area".

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 14 00 Page 2

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

04/12

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00,"Submittal Procedures."

SD-01 Preconstruction Submittals

Schedule of prices

1.3 SCHEDULE OF PRICES

1.3.1 Data Required

Within 15 calendar days of notice of award, prepare and deliver to Contracting Officer a schedule of prices (construction contract) on the forms furnished by the Government. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices therefor. Schedule of prices shall be separated by individual building numbers with subtotals for each building.

1.3.2 Schedule Instructions

Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 foot line. Identify costs for the building(s), and include work out to the 5 foot line. Workout to the 5 foot line shall include construction encompassed within a theoretical line 5 feet from the face of exterior walls and shall include attendant construction, such as cooling towers, placed beyond the 5 foot line.

1.3.3 Schedule Requirements for HVAC TAB

The field work Section 23 05 93, "TESTING, ADJUSTING, AND BALANCING FOR HVAC" shall be broken down in the Schedule of Prices and in the Construction Progress Documentation by separate line items which reflect measurable deliverables. Specific payment percentages for each line item shall be determined on a case by case basis for each contract. The line items shall be as follows:

SECTION 01 20 00 Page 1

a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. The resulting findings shall be submitted to the Government to allow correction of the design. The progress payment shall be issued after review and approval of the report.

b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report shall contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.

c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data shall be collected for one seasonal condition (either summer or winter depending on project timing).

d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.

e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.

f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data shall be compiled into a report and submitted to the Government.

On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued.

Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8 .

1.5 CONTRACTOR'S PAYMENT REQUEST

1.5.1 Proper Payment Request

A proper request for payment/invoice shall comply with all requirements specified in this Section and the contract payment clauses. If any

SECTION 01 20 00 Page 2 invoice does not comply with these requirements, it shall be returned with a statement of the reasons why it was not a proper invoice. A proper payment request/invoice includes the following information, completed forms, and number of copies indicated. Upon request, the Contracting Officer will furnish copies of Government forms.

a. Contractor's Invoice on NAVFAC Form 7300/30, which shall show the basis for arriving at the amount of the invoice. Submit one original and two copies.

b. Contractor's Monthly Estimate for Voucher (LANTNAVFACENGCOM Form 4-4330/110. Submit original and two copies.

c. Payment Certification. Furnish as specified in "FAR Clause 52.232-5 (c) Payments under Fixed-Price Construction Contracts."

Submit one original.

d. QC Invoice Certification. Furnish as specified in Section 01 45 10, "Quality Control." Submit one original.

1.5.1.1 Progress Payments

In addition to the requirements stated in Paragraph 1.5.1, "Proper Payment Request" above, the Contractor's request for progress payments shall include the following:

a. Updated Progress Schedule: Furnish an updated progress schedule as specified in contract clause FAR 52.236-15 "Schedules for Construction Contracts" and Section 01 32 16, "Construction Progress Documentation." Submit one copy.

1.5.1.2 Final Payments

The request for final payment is submitted after completion and acceptance of all work and all other requirements of the contract. Before submitting the final invoice the Contractor shall meet with the appropriate Government representatives to determine the final invoice amount, including the assessment of liquidated damages, if any, and to make sure the final release is complete and accurate. In addition to the requirements in Paragraph 1.5.1, "Proper Payment Request" above, the Contractor's request for final payment shall include the following:

a. A final release executed on the standard form provided by the Contracting Officer. Submit two originals with final payment request.

b. NC Tax certified statement and report for the prime and each subcontractor (FAR 52.229-7). Submit two copies.

c. As-built drawings (if applicable).

d. Warranties (if applicable).

e. O&M manuals (if applicable).

f. Final payrolls (FAR 52.222-6).

g. A release for an assignment of claims (if applicable). Submit three originals.

SECTION 01 20 00 Page 3

1.5.2 Procedures for Submitting Payment Request

a. The Contractor may submit only one invoice for payment each month as the work progresses.

b. The invoice shall be delivered to the ROICC Office, Administrative Branch, between five calendar days before and five calendar days after the contract award date. Invoices received outside this schedule shall be returned to the Contractor unprocessed. The Contractor will have to wait until the following month to submit their next invoice.

c. Invoices shall be delivered during normal work hours from 7:30 AM up to 4:00 PM (EST), Monday through Friday, excluding holidays.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of a proper payment request/invoice by the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to the following:

a. Reasonable retention and/or deductions due to defects in material or workmanship; potential liquidated damages; and/or failure to comply with any other requirements of the contract.

b. Claims which the Government may have against the Contractor under or in connection with this contract; and

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.

d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings"; NC State tax certified statement and report in accordance with FAR 52.229-2; labor payrolls in accordance with FAR 52.222-6; as-built drawings in accordance with Section 01 45 10, "Quality Control";

warranties and O&M manuals; and any other requirements in the contract.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off- site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment

SECTION 01 20 00 Page 4 considerations include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/ prestressed concrete products, plastic lumber (e.g. fender piles/ curbs), and high-voltage electrical cable. Materials no acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract. Requests for progress payment considerations for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation shall be stored in the Continental United States.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 20 00 Page 5

SECTION 01 20 00 Page 6

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

02/13

PART 1 GENERAL

1.1 SUBMITTALS

Submit the following in accordance with the Section 01 33 00, "Submittal Procedures."

SD-01 Preconstruction Submittals

List of contact personnel

1.2 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

a. Comprehensive general liability: $500,000 per occurrence

b. Automobile liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws,

d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,

e. Others as required by State law.

1.3 ELECTRONIC MAIL (EMAIL)

a. The Contractor is required to establish and maintain electronic mail (email) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.

b. Within 10 days after contract award; the Contractor shall provide the Contracting Officer a single (only one) email address for the ROICC office to send communications related to this contract correspondence. The ROICC office may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.

c. Multiple email addresses are not authorized.

d. It is the Contractor's responsibility to make timely distribution of all ROICC email within its own organization, including field office(s).

e. The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to their email address.

SECTION 01 30 00 Page 1

1.4 CONTRACTOR PERSONNEL REQUIREMENTS

1.4.1 Subcontractors and Personnel

Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.2 Identification Badges

Identification badges will be furnished without charge. Application for and use of badges will be as directed below. Immediately report instances of lost or stolen badges to the Contracting Officer. Employees are required to resubmit a complete 50 state criminal records check in order to renew their contractor badge.

1.4.3 Business Access Security Requirements

1.4.3.1 Business Access Definition

Contractor/subcontractor employees requiring installation access to MCB, Camp Lejeune or MCAS New River, N.C. must obtain a Business Access Identification Badge for that particular installation. Regularly scheduled delivery personnel, to include FEDEX, UPS, Pick-up and deliveries, should, also, follow the Business Access guidelines described below. Personnel requiring Business Access Identification Badges shall submit all documentation listed below. Badges are not required if the contracted position requires the employee to obtain a Common Access Card (CAC) which will be identified separately within the Government contract.

1.4.3.2 Installation Security Access Requirements

Contractor shall accomplish the security requirements below within 10 days after award or prior to performance under the contract.

1.4.3.3 Business Access Identification Badge Requirement

In order to obtain a Business Access Identification Badge for access to MCB, Camp Lejeune, and satellite activities, or MCAS New River, NC, all personnel providing services under this contract shall be required to present the documentation below to the following offices, as applicable:

MCB, Camp Lejeune, NC and its satellite activities. Report as follows:

a. Identification Card Center, 60 Molly Pitcher Road for badge (910-450-8444).

MCAS New River, NC. Report as follows:

a. Pass and Identification Office, Bldg AS-187 for badge (910-449-7695) and vehicle pass (910-449-5513).

1.4.3.4 Proof of Employee Citizenship or Legal Alien Status

Employers may participate in the E-verify program (1-888-464-4218, www.DHS.gov/e-verify) allowing U.S. employers to verify name, DOB, and SSN along with immigration information for non-citizens, against federal

SECTION 01 30 00 Page 2 databases in order to verify the employment eligibility of both citizens and non-citizen new hires.

1.4.3.5 Proof of Criminal Records Check

Commercial and contract employees must provide proof a complete 50 state criminal records check on an annual basis. The record check may be obtained from any of the following Internet investigative services: Kroll (former Infolink Screening Services) at www.kroll.com, Castle Branch at www.castlebranch.com, or any other investigative services company that provides records checks for all 50 states. These services also validate social security card numbers. All criminal history checks must be completed no more than 30 days prior to start date of contract. (Note:

These Internet screening services are listed as possible sources for obtaining a criminal background check. The United States government and the United States Marine Corps do not endorse nor are they affiliated with any of these services).

1.4.3.6 Letter Provided By Contracting Officer Indicating Contract

Letter provided by Contracting Officer indicating contract, contract period and prime contractor. Proof of employment on a valid Government contract (e.g., a letter on company letterhead from the prime contractor including contract number and term).

1.4.3.7 Photo ID

Valid state or federal issued picture identification card. Acceptable documents include state drivers license, DMV issued photo identification, or alien registration card.

1.4.3.8 National Crime Investigation Center (NCIC) Check

Provost Marshals are authorized to conduct a national crime information center (NCIC) check of all persons entering the installation, if/where applicable, the NCIC check may include drivers's license query, wants and warrants, and criminal history.

1.4.4 Denial of Access

Installation access shall be denied if it is determined that an employee:

a. Is on the National Terrorist Watch List

b. Is illegally present in the United States.

c. Is subject to an outstanding warrant.

d. Has knowingly submitted an employment questionnaire with false or fraudulent information.

e. Has been issued a debarment order and is currently banned from military installations.

f. Is a Registered Sexual Offender.

g. Has been convicted of a felony or a drug crime within the past five years.

SECTION 01 30 00 Page 3

h. Individuals who have received a DUI/DWI in the last year may be allowed access to the installation, but will not be permitted to drive on the installation.

i. Any reason the Installation Commander deems reasonable for the good order and discipline.

1.4.5 Appeal Process

All appeals should be directed to the Base Inspector's Office for any individual that has been denied access to the Base.

1.4.6 Display of Badges

Contractors/subcontractors shall prominently display their badges on their person at all times. Upon completion/termination of this contract or an individual's employment, the Contractor shall collect and turn in to the Pass & ID Office all badges. If the Contactor fails to obtain the employee's badge, the Pass & ID Office will be notified within 24 hours.

Immediately report instances of lost or stolen badges to the Contracting Officer.

1.4.7 Contractor and Subcontractor Vehicle Requirements

Each vehicle to be used in contract performance shall show the Contractor's or subcontractor's name so that it is clearly visible and shall always display a valid state license plate and safety inspection sticker. To obtain a vehicle decal, which will be valid for one year or contract period, whichever is shorter, Contractor or subcontractor vehicle operators shall provide to the Vehicle Registration Office, 60 Molly Pitcher Road (910-451-1158) or to MCAS, Building AS-187 (910-449-5513) for vehicle decal:

a. An installation sponsor request forwarded to provost Marshall office

b. A valid form of Federal or state government I.D.

c. If driving a motor vehicle, a valid driver's license, vehicle registration and proof of insurance

Upon completion/termination of this contract or an individual's employment, the Contractor shall collect and turn in to Vehicle Registration all Government vehicle decals. If any are not collected, the Contractor shall notify the Vehicle Registration Office within 24 hours.

1.4.8 Security Checks

Contractor personnel and vehicles shall only be present in locations relevant to contract performance. All Contractor personnel entering the base shall conform to all Government regulations and are subject to such checks as may be deemed necessary to ensure that violations do not occur.

Employees shall not be permitted on base when such a check reveals that their presence would be detrimental to the security of the base. Subject to security regulations, the Government will allow access to an area for servicing equipment and/or performing required services. Upon request, the Contractor shall submit to the Contracting Officer questionnaires and other forms as may be required for security purposes.

SECTION 01 30 00 Page 4

1.4.9 Subcontractor Special Requirements

1.4.9.1 Space Temperature Control, HVAC TAB, and Apparatus Inspection

All contract requirements of Section 23 09 23.13, BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC," Section 23 05 93, "TESTING, ADJUSTING, AND BALANCING FOR HVAC," and shall be accomplished directly by a first tier subcontractor. No work required by these sections shall be accomplished by a second tier subcontractor.

1.4.9.2 Telecommunication and High Voltage Work

When telecommunications and high voltage work is required, all work associated with telecommunications and high voltage shall be accomplished by a first tier subcontractor. The contractor must possess a valid North Carolina Public Utility - Electrical, contractor's license and be insured to do such work in the State of North Carolina.

1.4.9.3 Paving Associated with Utility Cuts

All pavement repairs associated with utility cuts shall be completed within 14 days of completing work within paved area.

1.5 DISCLOSURE OF INFORMATION

Contactor shall comply as follows:

a. The Contractor shall not release to anyone outside the Contractor's organization any unclassified information, regardless of medium (e.g., film, tape, document), pertaining to any part of this contract or any program related to this contact, unless -

(1) The Contracting Officer has given prior written approval; or

(2) The information is otherwise in th public domain before the date of release.

b. Requests for approval shall identify the specific information to be released, the medium to be used, and the purpose for the release. The Contractor shall submit its request to the Contracting Officer at least 45 days before the proposed date for release.

c. The Contractor agrees to include a similar requirement in each subcontract under this contract. Subcontractors shall submit requests for authorization to release through the prime contractor to the Contracting Officer.

1.6 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (CQ) representative is required on the contract, then that individual shall also have fluent English communication skills.

NOTE: If training and experience requirements of Section 01 45 10, "Quality Control" and 01 35 29, "Safety and Occupational Health Requirements" have been met the supervisor may also serve as QC Manager and Site Safety and Health Officer (SSHO).

SECTION 01 30 00 Page 5

1.7 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work.

Major subcontractors who will engage in the work shall also attend.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 30 00 Page 6

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

05/17

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional or specifically requested in addition to electronic submission. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.

1.2 USER PRIVILEGES

The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.

1.3 SUBMITTALS

Provide all submittals in accordance with Section 01 33 00 SUBMITTAL PROCEDURES and the submittal register.

SD-01 Preconstruction Submittals

List of Contractor's Personnel

1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY

1.4.1 General

The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.

1.4.2 Contractor Personnel List

Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical

SECTION 01 31 23.13 20 Page 1 submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:

First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)

1.5 SECURITY CLASSIFICATION

In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.

The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of Defense Manual 5200.01-V4: DoD Information Security Program: Controlled Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U

- UNCLASSIFIED" (U) or "FOUO - UNCLASSIFIED-FOR OFFICIAL USE ONLY" (FOUO).

1.6 ECMS UTILIZATION

Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.

Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.

1.6.1 Information Security Classification/Identification

The eCMS must be used for the transmittal of the following documents.

This requirement supersedes conflicting requirements in other sections), however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and FOUO designations for various types of project documents. Construction documents requiring FOUO status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.

Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. After uploading documents to the Submittal application, transmit the submittals and

SECTION 01 31 23.13 20 Page 2 attachments to the COR via the Transmittal application. For Submittals, select the following:

Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager

Table 1 - Project Documentation Types

SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON

As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals and Transmittals

Building Information Modeling (BIM)

U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

2. Design reviews will be performed in existing "Dr Checks"

Submittals and Transmittals

Construction Permits U Refer to rules of the issuing activity, state or jurisdiction

Submittals and Transmittals

Construction Schedules (Activities and Milestones)

U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline

Submittals, Transmittals and Scheduling App

Construction Schedules (Cost-Loaded)

FOUO After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline

Submittals, Transmittals and Scheduling App

Construction Schedules (3-Week Lookahead)

U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline

Scheduling App

DD 1354 Transfer of Real Property

U Submittals and Transmittals

SECTION 01 31 23.13 20 Page 3

SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON

Daily Production Reports

FOUO Provide weather conditions, crew size, man-hours, equipment, and materials information

Daily Report

Daily Quality Control (QC) Reports

FOUO Provide QC Phase, Definable Features of Work Identify visitors

Daily Report

Designs and Specifications

U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

2. Design reviews will be performed in existing "Dr Checks"

Submittals and Transmittals

Environmental Notice of Violation (NOV), Corrective Action Plan

U Refer to rules of the issuing activity, state or jurisdiction

Submittals and Transmittals

Environmental Protection Plan (EPP)

FOUO Submittals and Transmittals

Invoice (Supporting Documentation)

FOUO Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)

Submittals and Transmittals

Jobsite Documentation, Bulletin Board, Labor Laws, SDS

U Submittals and Transmittals

Meeting Minutes FOUO Meeting Minutes

Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet

U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

2. Design reviews will be performed in existing "Dr Checks"

Submittals and Transmittals

Photographs U Subject to base/installation restrictions

Submittals and

SECTION 01 31 23.13 20 Page 4

QCM Initial Phase Checklists

FOUO Checklists (Site Management)

QCM Preparatory Phase Checklists

FOUO Checklists (Site Management)

Quality Control Plans FOUO Submittals and Transmittals

QC Certifications U Submittals and Transmittals

QC Punch List U Punch Lists (Testing Logs)

Red-Zone Checklist U Checklists (Site Management)

Rework Items List FOUO Punch Lists (Testing Logs)

Request for Information (RFI) Post-Award

FOUO RFIs

Safety Plan FOUO Daily Report

Safety - Activity Hazard Analyses (AHA)

FOUO Daily Report

Safety - Mishap Reports

FOUO Daily Report

SCIF/SAPF

Accreditation Support Documents

FOUO Note: Some Construction Security plans may be classified as Secret.

Classified information must not be uploaded into eCMS. Refer to the Site Security Manager, as applicable.

Submittals and Transmittals

Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals and

SECTION 01 31 23.13 20 Page 5

Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)

U Refer to rules of the issuing activity, state or jurisdiction

Submittals and Transmittals

Submittals and Submittal Log

U Submittals and Transmittals

Testing Plans, Logs, and Reports

FOUO Submittals and Transmittals

Training/Reference Materials

U Submittals and Transmittals

Training Records (Personnel)

FOUO Submittals and Transmittals

Utility Outage/Tie-In Request/Approval

FOUO Submittals and Transmittals

Warranties/BOD Letter FOUO Submittals and Transmittals

Quality Assurance Reports