ACQR5784065

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment 0001 is to provide answ ers to the questions receieved.

See continuation page for more details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Mar-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008420T0005

X 9B. DATED (SEE ITEM 11)

02-Mar-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Mar-2020

CODE

NAVFAC FAR EAST

CORE EXECUTION TEAM

PSC 473 BOX 13

FPO AP 96349-0013

N40084 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008420T0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001 INFO

The purpose of this Amendment 0001 is to provide answers to the following questions receieved:

No. Date Questions Answers 1 3/4/2020 Do you accept the required Safety Loader

Truck w/ Cab Back Crane manufactured in China?

The truck shall comply with the specs provided on beta.SAM.gov and Japanese Motor Vehicle Safety Standards. Please note that this solicitation includes the ocean transportation clause (FAR 52.247-64).

2 3/7/2020 Specification - Mandatory Characteristics for each item being purchased under this solicitation// SECTION C.f. What is a wheight distribution data?

This requirement has been deleted. Please refer the Revised(1)_Specification.

3 3/7/2020 Specification - Mandatory Characteristics for each item being purchased under this solicitation// (2) Modifications (e.) What are Retractible stays?

Please see the Revised(1)_Specification.

4 3/7/2020 Specification - Mandatory Characteristics for each item being purchased under this solicitation//(2) Modifications(L) What part is the torii?

Guard frame behind cabin

5 3/7/2020 Specification - Mandatory Characteristics for each item being purchased under this solicitation//(2) Modifications(F) What is the height of side gates (aori) auminum?

Please see the Revised(1)_Specification.

6 3/9/2020 D. DELIVERY, INSPECTION, AND

ACCEPTANCE

(2) Date:

Please kindly accept delivery 730 days.

No. The delivery date extension from 400 calendar days after the contract award to 730 calendar days after the contract award is not acceptable.

7 3/12/2020 C. OTHER MISCELLANEOUS

REQUIREMENTS

(1) Accessories

k. Tie-up chain.

Please kindly clarify your loaded item's approx. weight.

Requirement of truck payload capacity is 5.0t or above. The capacity of the chains must be equal to or above the payload capacity of the truck.

N4008420T0005

8 3/12/2020 C. OTHER MISCELLANEOUS

REQUIREMENTS

(1) Accessories

k. Tie-up chain.

Please kindly accept four (4) tie-up chain can excess 5.0t rated load.

Do we correctly understand that you want to load 5,0t of your required payload capacity?

9 3/12/2020 C. OTHER MISCELLANEOUS

REQUIREMENTS

(2) Modifications

n. D-rings (Matukan-hook).

Please kindly confirm your required D-rings are called "Marukan-hook".

We can't find D-dings called Matukan-hook with manufacturer's opinion.

Please see the Revised(1)_Specification.

10 3/15/2020 Do you extend the delivery date from 400 days to 1100 days?

No. The delivery date extension from 400 calendar days after the contract award to 1100 calendar days after the contract award is not acceptable.

All other terms and conditions remain unchanged.