This document provides details for a federal solicitation and related opportunity. The solicitation is for Design-Build/Design-Bid-Build Multiple Award Construction Contracts (Regular MACC) at Commander Fleet Activities Sasebo (CFAS), Japan and other areas within the Naval Facilities Engineering Command Far East area of responsibility. The total not-to-exceed amount for all MACC contract awards is $249 million. Individual task order values will range from approximately $1 million to $3 million. Task orders will be awarded in Japanese Yen, and payments made in Yen, though the U.S. dollar equivalent will also be expressed for administrative convenience. A pre-proposal conference will be held on December 19, 2019 at 10:00AM at the CFAS base, and individual access passes are required to attend. One "seed" project is included that will be awarded concurrently with the basic MACCs, involving replacement of HVAC systems at two buildings at CFAS with a value between $1-5 million and a 510 day period of performance including cleanup. Liquidated damages of approximately $1,938 per day will apply to delays in completion of the seed project.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Description of Amendment begins on page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Jan-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008420R6500
X 9B. DATED (SEE ITEM 11)
06-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Jan-2020
CODE
NAVFAC FAR EAST
FEAD SASEBO
PSC 476 BOX 66
FPO AP 96322-1160
N40084 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008420R6500
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
The purpose of this amendment is as follows:
1) Extend proposal due date and time .
2) Provide Government Responses to Questions Received_Amendment01, Attachment L, and update List of Attachments accordingly;
3) Provide Pre-Proposal Conference Sign-In Sheet_Phase One 20R6500, Attachment M, and update List of Attachments accordingly;
4) Correct the performance period in Paragraph 4 of II. DESCRIPTION OF SEED PROJECT, to match the seed project specifications.
All other terms and Conditions remain unchanged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 21-Jan-2020 10:00 AM to 28-Jan-2020 02:00 PM.
The following have been modified:
LIST OF ATTACHMENTS
Attachment A - Regular MACC Specification (ep#1626280) dated 22 Oct 2019 (355 pages) Attachment B - Seed Project Specification (ep#1637154) dated 26 Sept 2019 (719 pages) Attachment C - Seed Project Drawings (ep#1637154) (3711 pages) Attachment D - ICAP Training Manual_v9 (93 pages) Attachment E - Contractor ICAP- Template (1 tab in Excel) Attachment F - Provision 52.204-24 (1 page) Attachment G - Construction Experience Project Data Sheet (2 pages) Attachment H - Past Performance Questionnaire (7 pages) Attachment I - Government PreProposal Inquiry Form (1 page) Attachment J - DBIDS Card – Paper Pass Request (3 tabs in Excel) Attachment K - SECNAV5512-1 (2 pages) Attachment L - Government Responses to Questions Received_Amendment01 (2 pages) Attachment M - Pre-Proposal Conference Sign-In Sheet_Phase One 20R6500 (Amendment01) (3 pages)
Notice: DFARS 252.204-7000 Disclosure of Information applies to all Documents, Exhibits, and Attachments as well as FAR 52.204-21 Basic Safeguarding of Covered Contractor Information Systems and DFARS 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls, 252.204-7009 Limitations on the Use or
N4008420R6500
Disclosure of Third-Party Contractor Reported Cyber Incident Information, and 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
II.
DESCRIPTION OF SEED PROJECT
1. There is one “seed” project for this solicitation which will be awarded at the time of award of the MACC contracts.
Title: Replace HVAC System in Bldg. PW63 and 1604 at the U.S. Fleet Activities, Sasebo, Japan (eProject # 1637154)
2. A Task Order for the seed project will be issued concurrently with the award of the basic contract for the contractor selected as the best value for the seed project.
3. In accordance with FAR 36.204, the magnitude of construction for the Seed Project is between $1,000,000 and $5,000,000 (based on the FY20 Budget Execution Rate of JPY 111.1542 = $1.00).
4. In accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work, the offeror awarded the seed project shall be required to commence work for the Seed Project within 15 days after date of award, prosecute the work diligently, and complete the entire work ready for use not later than 510 days after date of Task Order award. The time stated for completion shall include final cleanup of the premises.
5. In accordance with FAR 52.211-12 Liquidated Damages, if the offeror awarded the seed project fails to complete the work within the time specified in the Task Order for the seed project, the Contractor shall pay liquidated damages to the Government in the amount of JPY 1,938,421 for each calendar day of delay until the work is completed or accepted.
(End of Summary of Changes)